Comments on: Wave-energy buoys need certification before being plopped off Oregon Coast /news/2011/10/13/wave-energy-buoys-need-certification-before-being-plopped-off-oregon-coast/ Building and Construction News in Portland, Oregon and the Pacific Northwest Wed, 19 Oct 2011 21:46:09 +0000 hourly 1 https://wordpress.org/?v=6.6.6 By: Chris Johnson /news/2011/10/13/wave-energy-buoys-need-certification-before-being-plopped-off-oregon-coast/#comment-98757 Wed, 19 Oct 2011 21:46:09 +0000 /dailyblog/?p=74999#comment-98757 I’m interested in how the 395 home estimate was calculated if that information is available. If each buoy produces a max of 150 Kw, ten will produce a max of 1500 Kw. That is only 3.8 Kw per home which relates to a 16 amp service at 240 VAC. My old house has a 125 amp service and even including a diversity factor (not everybody using the max at the same time)I can’t see 16 amps even being close to enough. Is there any backup to how that estimate was made?

]]>