Lifeworks NW – Daily Journal of Commerce /news/tag/lifeworks-nw/ Building and Construction News in Portland, Oregon and the Pacific Northwest Thu, 10 Oct 2019 23:28:03 +0000 en-US hourly 1 https://wordpress.org/?v=6.6.6 /files/2023/08/favicon.webp Lifeworks NW – Daily Journal of Commerce /news/tag/lifeworks-nw/ 32 32 Crews wrapping up work on Gresham clinic /news/2019/10/10/crews-wrapping-work-gresham-clinic/ Thu, 10 Oct 2019 20:57:46 +0000 /?p=195228 Workers are applying finishing touches to a new three-story building in the Rockwood neighborhood.

The post Crews wrapping up work on Gresham clinic appeared first on Daily Journal of Commerce.

]]>
A new three-story building in Gresham will contain office and clinic space for LifeWorks NW, which provides mental health and addiction services. (Josh Kulla/91Ƶ)
A new three-story building in Gresham will contain office and clinic space for , which provides mental health and addiction services. (Josh Kulla/91Ƶ)

The ongoing redevelopment of Gresham’s neighborhood is continuing apace, including the recent completion of a new LifeWorks NW clinic.

This three-story clinic, at 18417 S.E. Oak St., near the Rockwood Rising mixed-use development, is replacing former facilities in Rockwood and Gresham. , the project’s developer, served as its own general contractor. designed the project.

Staff in the new building will provide mental health and addiction treatment. LifeWorks NW, which has operated for nearly 60 years, needed something quite a bit different than a typical commercial structure.

“With this program it’s really important to have that point of control – that single main entry with really strong controls,” Carleton Hart Architecture principal Brian Carleton said. “So, the entry could only really be at one end or the other, and the rest of the building becomes this rabbit warren of offices and meeting spaces and therapy spaces.”

One of the building’s biggest challenges is the southern location of the entrance. This faces away from a nearby MAX light-rail station to the north, from which many clinic patients and staffers will likely approach.

“How do you design the building where you’ve got the open and inviting end, but you can’t turn your back on the other street?” Carleton said. “We don’t want people to enter that end of the building, but we want to guide them and make them feel welcome as they’re coming off the MAX.”

This was accomplished by adding concrete benches and other furniture items on a back patio. In addition, a landscaped and lit path running the length of the building provides an easy route to the entrance.

Inside, the three floors serve distinctly separate purposes. The ground floor features the main lobby and a pharmacy, as well as a host of exam rooms and group meeting rooms. The second floor is dedicated to clinical services, and the third story is home to LifeWorks NW staff and information technology systems.

On the top floor, the layout was made as open as possible, Carleton Hart project architect Devin Follingstad said. Because structural steel columns bear loads, this also allows for relatively simple tenant improvements or partitions.

Also on the third floor, an employee break room is equipped with a small kitchen. Even here, the space is set up for flexibility.

Floor-to-celing glazing provides ample natural light to the main reception area at the new LifeWorks NW building in Gresham. (Josh Kulla/91Ƶ)
Floor-to-ceiling glazing provides ample natural light to the main reception area at the new LifeWorks NW building in Gresham. (Josh Kulla/91Ƶ)

“The break room is wired for future cubes if they need it,” Follingstad said. “The break room may even go away and become offices.”

Designers also convinced LifeWorks NW to include an outdoor patio on the third floor, Follingstad added.

The building – three stories of wood framing atop a slab-on-grade foundation – was relatively simple to construct, Central Bethany Development superintendent Jeff Oberst said. The difficulties, he added, were tied to materials and labor.

“We have the same woes everyone else right now has in this market,” he said. “The labor woes are terrible, so it definitely had an impact.”

Ongoing major school construction has contributed to the problem, Oberst added.

“The trades were impacted by that, and the rest of us have to compensate based on the schedules of the schools,” he said.

The new clinic’s exterior cladding includes masonry, fiber cement panels and metal panels. The project team experienced difficulties with its original supplier of bricks, Oberst said.

“After it was two and a half months late, we had to go find new brick in California,” he said.

Ground was broken a year ago, and a temporary certificate of occupancy was expected to be issued last week. A punch list of items should be addressed this month, before the arrival of staff.

LifeWorks NW contracts out some of its services, so in the new building, Wallace Medical Concern will offer primary care services and Genoa Healthcare will provide pharmacy service.

LifeWorks NW staff will occupy the building's third-floor office space. (Josh Kulla/91Ƶ)
LifeWorks NW staff will occupy the building’s third-floor office space. (Josh Kulla/91Ƶ)
Staff space on the third floor includes a kitchen and break area that is wired for future use as office space. (Josh Kulla/91Ƶ)
Staff space on the third floor includes a kitchen and break area that is wired for future use as office space. (Josh Kulla/91Ƶ)
Designers with Carleton Hart Architecture convinced LifeWorks NW to include a third-floor patio for staff use. (Josh Kulla/91Ƶ)
Designers with Carleton Hart Architecture convinced LifeWorks NW to include a third-floor patio for staff use. (Josh Kulla/91Ƶ)
The first and second floors contain patient care spaces including individual exam rooms, group session rooms and conference rooms. (Josh Kulla/91Ƶ)
The first and second floors contain patient care spaces including individual exam rooms, group session rooms and conference rooms. (Josh Kulla/91Ƶ)
LifeWorks NW staff are scheduled to occupy the building later this month. (Josh Kulla/91Ƶ)
LifeWorks NW staff are scheduled to occupy the building later this month. (Josh Kulla/91Ƶ)
The building overlooks the nearby Rockwood Rising mixed-use project, which is under construction a block away. (Josh Kulla/91Ƶ)
The building overlooks the nearby Rockwood Rising mixed-use project, which is under construction a block away. (Josh Kulla/91Ƶ)
The building's exterior materials include masonry, metal and fiber cement paneling. (Josh Kulla/91Ƶ)
The building’s exterior materials include masonry, metal and fiber cement paneling. (Josh Kulla/91Ƶ)