Oregon Cascade Plumbing & Heating – Daily Journal of Commerce /news/tag/oregon-cascade-plumbing-heating/ Building and Construction News in Portland, Oregon and the Pacific Northwest Fri, 03 Jan 2020 16:39:45 +0000 en-US hourly 1 https://wordpress.org/?v=6.6.6 /files/2023/08/favicon.webp Oregon Cascade Plumbing & Heating – Daily Journal of Commerce /news/tag/oregon-cascade-plumbing-heating/ 32 32 Big renovation following ‘a Frankenstein job’ /news/2020/01/02/big-renovation-following-frankenstein-job/ Thu, 02 Jan 2020 22:11:55 +0000 /?p=198132 Structural steel erection for a new gymnasium at Tigard High School is wrapping up as crews approach the end of a two-year, $66 million expansion and renovation project.

The post Big renovation following ‘a Frankenstein job’ appeared first on Daily Journal of Commerce.

]]>
Jose Magaña, an apprentice carpenter with Local 146 and an employee of Fred Shearer & Sons, frames an interior wall at Tigard High School. (Josh Kulla/91Ƶ)
Jose Magaña, an apprentice carpenter with Local 146 and an employee of , frames an interior wall at Tigard High School. (Josh Kulla/91Ƶ)

Structural steel erection for a new gymnasium at Tigard High School is wrapping up as crews approach the end of a two-year, $66 million expansion and renovation project.

The school, constructed during the postwar building boom, has received some 18 remodels over the years. General contractor is carrying out the latest improvements, thanks to money from a $291.3 million bond approved by voters in 2016.

“This high school was built in the 1950s; that was its first iteration,” said Eric Nesse, ‘s bond support administrator. “It’s really been a Frankenstein job with many additions. Our architect has a little historic card with all the different colors from all the different remodels.”

The project, designed by , is taking place in two phases; renovations and new construction are covering a total of approximately 153,000 square feet. In the first phase, workers expanded an existing classroom wing for business and career and technical education, built a new wing with administrative space and a large common area highlighted by a learning stair, installed new turf for athletic fields, and constructed new tennis courts.

In the second phase, now under way, crews are building a new auxiliary gym that will connect with the new common area and an expanded cafeteria.

“There will also be the courtyard,” Nesse said. “And there’s a little breezeway that will be locked with a fence across it to the old building that will create a secure area. Looking into the auxiliary gym area, this is actually sort of a pit. There’s a walkway all the way around the gym that’s kind of sunken like a pit, with the basketball court down below at a lower level.”

All of that is now evident as completion of construction is now in sight.

“We’re in phase two, but there are still some odds and ends to take care of from phase one,” Pence Construction project superintendent Kurt Schwabauer said. “They’ve been using (the new wing) all year and everyone seems to be pretty happy.”

While of Salem is finishing structural steel work for the gym, Fred Shearer & Sons of Beaverton is building walls as well as connecting new structures with existing ones.

“The ironworkers are out there, and now the framers are here from Fred Shearer and they do the interior and exterior framing,” Schwabauer said. “They’ve got a pretty big package; they’re doing the interior and exterior framing (and) they’re doing the drywall and the insulation and the weather barrier.”

Fred Shearer & Sons also is performing finish carpentry and installing custom wooden ceilings throughout much of the new space. Other major subcontractors on the job include and .

“Oregon Cascade has our plumbing and heating package,” Schwabauer said. “Their labor force does the wet side of things, and then they’ve hired Salem Heating to do the dry side.”

For now, crews are scrambling to get roofing into place and the new gym dried in as spring approaches. This summer will mark two years of work on the project.

“With final phase 2 delivery, building turnover (will be) in early August and the parking lot will be done at the end of the summer,” Schwabauer said.

Tyler Klement, an apprentice electrician with Prairie Electric, runs wire through conduit in the new auxiliary gym at Tigard High School. The campus is undergoing a two-phase, $66 million renovation and expansion project. (Josh Kulla/91Ƶ)
Tyler Klement, an apprentice electrician with Prairie Electric, runs wire through conduit in the new auxiliary gym at Tigard High School. The campus is undergoing a two-phase, $66 million renovation and expansion project. (Josh Kulla/91Ƶ)
Structural steel erection is nearly complete on the new gymnasium at Tigard High School. (Josh Kulla/91Ƶ)
Structural steel erection is nearly complete on the new gymnasium at Tigard High School. (Josh Kulla/91Ƶ)
Journeyman ironworker Jim Wright of DSL Builders welds a structural steel beam on the new auxiliary gymnasium at Tigard High School. (Josh Kulla/91Ƶ)
Journeyman ironworker Jim Wright of DSL Builders welds a structural steel beam on the new auxiliary gymnasium at Tigard High School. (Josh Kulla/91Ƶ)
Apprentice carpenter John Holley, a member of Local 1503 and an employee of Pence Kelly Construction, caulks a seam in the weather barrier around a water line. (Josh Kulla/91Ƶ)
Apprentice carpenter John Holley, a member of Local 1503 and an employee of Pence Kelly Construction, caulks a seam in the weather barrier around a water line. (Josh Kulla/91Ƶ)
Journeyman carpenter Judah Webb, an employee of DSL Builders, cuts lumber while framing interior walls at Tigard High School. (Josh Kulla/91Ƶ)
Journeyman carpenter Judah Webb, an employee of DSL Builders, cuts lumber while framing interior walls at Tigard High School. (Josh Kulla/91Ƶ)
The new auxiliary gymnasium will include an elevated walkway around the perimeter. (Josh Kulla/91Ƶ)
The new auxiliary gymnasium will include an elevated walkway around the perimeter. (Josh Kulla/91Ƶ)
Journeyman carpenter Judah Webb, an employee of DSL Builders, carries lumber as his crew frames interior walls at Tigard High School. (Josh Kulla/91Ƶ)
Journeyman carpenter Judah Webb, an employee of DSL Builders, carries lumber as his crew frames interior walls at Tigard High School. (Josh Kulla/91Ƶ)
Journeyman ironworker Zach Sweeten of DSL Builders welds a structural steel beam on the new auxiliary gymnasium. (Josh Kulla/91Ƶ)
Journeyman ironworker Zach Sweeten of DSL Builders welds a structural steel beam on the new auxiliary gymnasium. (Josh Kulla/91Ƶ)
The new cafeteria space is separated from existing food service areas by a temporary wall. (Josh Kulla/91Ƶ)
The new cafeteria space is separated from existing food service areas by a temporary wall. (Josh Kulla/91Ƶ)
A secure interior courtyard for staff and student use is being built as part of the Tigard High School expansion. (Josh Kulla/91Ƶ)
A secure interior courtyard for staff and student use is being built as part of the Tigard High School expansion. (Josh Kulla/91Ƶ)
Journeyman ironworker Jim Wright of DSL Builders grinds a fresh weld. (Josh Kulla/91Ƶ)
Journeyman ironworker Jim Wright of DSL Builders grinds a fresh weld. (Josh Kulla/91Ƶ)
Journeyman carpenter Jeremy Laperl,, an employee of DSL Builders, takes a measurement while framing interior walls at Tigard High School. (Josh Kulla/91Ƶ)
Journeyman carpenter Jeremy Laperl,, an employee of DSL Builders, takes a measurement while framing interior walls at Tigard High School. (Josh Kulla/91Ƶ)
The second phase of construction includes a new kitchen. (Josh Kulla/91Ƶ)
The second phase of construction includes a new kitchen. (Josh Kulla/91Ƶ)
Structural steel erection is nearly complete on the new gymnasium. (Josh Kulla/91Ƶ)
Structural steel erection is nearly complete on the new gymnasium. (Josh Kulla/91Ƶ)

 

The post Big renovation following ‘a Frankenstein job’ appeared first on Daily Journal of Commerce.

]]>