Portland infrastructure – Daily Journal of Commerce /news/tag/portland-infrastructure/ Building and Construction News in Portland, Oregon and the Pacific Northwest Fri, 12 Dec 2025 19:28:43 +0000 en-US hourly 1 https://wordpress.org/?v=6.6.6 /files/2023/08/favicon.webp Portland infrastructure – Daily Journal of Commerce /news/tag/portland-infrastructure/ 32 32 OTC advances I-5 Rose Quarter project despite funding gap /news/2025/12/12/i5-rose-quarter-project-advances-limited-funding/ Fri, 12 Dec 2025 19:28:43 +0000 /?p=515273 The Oregon Transportation Commission on Thursday approved moving the project to its next phase and directed ODOT to work with stakeholders.

The post OTC advances I-5 Rose Quarter project despite funding gap appeared first on Daily Journal of Commerce.

]]>

At a glance:
  • Improvement Project still lacks funding for full completion
  • allocates $167.7 million toward phase 1 construction starting in 2027
  • Micropile foundation approach adopted, reducing project costs by $45 million
  • OTC directs ODOT to collaborate with Portland, Metro and

The Commission voted Thursday to move construction of the I-5 Rose Quarter Improvement Project to its next phase despite limited funding. The Oregon Department of Transportation will use $167.7 million to pay for work set to begin in 2027.

Last year, ODOT received a $450 million grant from the Federal Highway Administration via its and Neighborhoods (RCN) program. This money was intended to pay for the Phase 1 package, including construction of the southern portion of the , completion of the southbound I-5 auxiliary lane and shoulder from I-405 to the Moda Center, and other improvements.

ODOT was able to obligate $67.5 million of the RCN funding before the remainder ($382.5 million) was rescinded by the 2025 Budget Reconciliation Act. The obligated funding can be used for preliminary engineering as well as work related to right of way and utilities.

There is $479.9 million in total funding available for the I-5 Rose Quarter Improvement Project, a staff report states. Travis Brouwer, ODOT deputy director of revenue, finance and compliance, said that funding is not sufficient to finish the project.

The available funding includes $380 million in House Bill 2017 funding. Of that portion, currently $167.7 million can go toward phase 1 construction, Brouwer said.

The funding also includes $32.4 million in federal, state and local money for preliminary engineering and construction.

“Phase 1A packages work in the corridor both in the north end near the I-5 interchange and at the south end at the I-84 interchange,” said Monica Blanchard, interim program director of the I-5 Rose Quarter Improvement Project.

Phase 1A is under way and scheduled to finish in late 2026. Its focus is on bridge maintenance, stormwater-related work, and early safety improvements. Subcontractors have been selected, the right of entry permit has been finalized, erosion control has been installed on site, and stormwater work on the drainage pond has started, Blanchard said.

ODOT completed a value engineering study and cost reduction workshop after May’s meeting. A cost reduction concept of micropiles for the highway cover foundation has been adopted. According to ODOT, micropiles offer flexibility in construction and are better suited to address subsurface obstructions if encountered. Micropiles use smaller drilling equipment than other traditional foundation types and can be better mobilized in restrictive areas. The results are a $45 million cost reduction and no impact on the construction schedule.

ODOT will continue to consider other ways project costs can be lowered, Blanchard said. In fact, eight other concepts are being evaluated. However, officials have ruled out removing the second auxiliary lane on I-84 to Weidler Street, reducing the width of the highway within the highway cover, and using buried concrete arches in lieu of girders.

Moving forward, ODOT presented three construction options to the commission. Option 1 would be construction of phase 1B with the available $167.7 million. Crews would complete some of the operational and safety improvements on I-5 between I-84 and the Broadway/Weidler off-ramp, including widening over the Rose Quarter Transit Center and removing the pinch point at the I-84 northbound on-ramp. Construction would begin in 2027, after completion of phase 1A, and allow for a continuous transition from phase 1A to phase 1B.

Option 2 would delay construction of the full Broadway Weidler Phase 1 package until the third quarter of 2028 if additional funding is secured. ODOT would use remaining preliminary engineering funds, including the RCN grant, to complete design for all of phase 1.

Under option 3, construction funding for the Broadway Weidler Phase 1 package would be reallocated or reprioritized legislatively. Design of Broadway Weidler Phase 1 would be completed with federal RCN grant funding. The team would focus on completing the phase 1A construction package. The rest of the budget would be allocated to other ODOT priorities. ODOT staff did not recommend this option because the project cost would grow each year.

However, a fourth option was proposed by Metro, the city of Portland and Albina Vision Trust. In a letter, the partners proposed something similar to option 1 but with ODOT working with them on phasing and scope of phase 1B and phase 1C.

Commissioners voted unanimously to advance option 4, which directs ODOT to work collaboratively with local and regional partners to analyze the proposed construction scope and develop a feasible plan. ODOT will return before the commission in March or April with a progress report.

The post OTC advances I-5 Rose Quarter project despite funding gap appeared first on Daily Journal of Commerce.

]]>
I-5 Rose Quarter project faces $412 million funding loss /news/2025/08/15/i5-rose-quarter-project-funding-loss/ Fri, 15 Aug 2025 18:23:12 +0000 /?p=511765 The massive transportation improvement project in Portland will lose federal funding because of Trump's "Big Beautiful Bill," putting its future – including the Albina cover – in doubt.

The post I-5 Rose Quarter project faces $412 million funding loss appeared first on Daily Journal of Commerce.

]]>

At a glance:
  • Oregon analysis shows $412M loss for project
  • Funding cut tied to GOP-led bill rescinding federal grants
  • plans to start construction this summer despite shortfall
  • Albina freeway cover and future phases remain uncertain

An effort to widen Interstate 5 through Portland and build developable in Albina stands to lose $412 million in federal funding, a state analysis found.

The I-5 Rose Quarter Improvement Project will lose $150 million in 2027-29 and $262 million in 2029-31 after the passage of a Republican-led funding bill, according to an analysis by the Oregon Department of Administrative Services‘ Chief Financial Office.

President Donald Trump’s so-called “Big Beautiful Bill,” also known at House Bill 1, rescinds unobligated funds from the Neighborhood Access and Equity grant program, according to the state’s preliminary analysis, which was released on Monday.

The Trump administration’s move to pull previously approved funding puts the project’s immediate future in doubt, according to the state analysis.

“While an initial $60 million contract for paving and stormwater work that is part of phase 1 has advanced, constructing the remainder of phase 1 and phase 2 will be exceedingly difficult, if not impossible, without federal funding,” the Financial Office stated.

The funding rescission may cloud the project’s future, because it cannot be completed without hundreds of millions of dollars in additional funding, and state is also stretched. A special session called for Aug. 29 is expected to produce money for operations and maintenance, but not major infrastructure projects such as the I-5 improvements.

The Rose Quarter project is expected to cost $2.1 billion, according to the Oregon Department of Transportation‘s most recent estimate.

“Any pause or delay will result in project cost escalation and removal of scope elements to bring down costs would significantly impact community support,” the analysis adds. “ODOT continues to evaluate the committed project financing, weighing options, as well as considering alternative investments since the total financing for the Rose Quarter Improvement Project is no longer secured.”

Joe Cortright, an economist and frequent ODOT critic, said the agency should pause the project until funding is secured.

“The idea that you would start work on this project, move forward with this project, when you’re at least $1 billion short makes no fiscal sense at all,” he said.

ODOT officials said they have no intention of delaying initial construction on the I-5 Rose Quarter Improvement Project. Construction will begin this summer and continue into late 2026, spokeswoman Rose Gerber stated in an email.

There are no plans for a ground-breaking ceremony, Gerber stated.

The first phase will include the extension of an auxiliary lane within the existing footprint of I-5 between the I-84 and the Morrison/OMSI exits, along with stormwater improvements and bridge maintenance. The work was previously approved by the . Future phases are less clear.

“The agency is reviewing project financing and determining next steps,” Gerber stated. “ODOT is committed to working with its partners to secure additional funding to construct the project.”

Cortright said he’s concerned that ODOT intends to begin the project and then request a bailout from the Legislature. That is how he described ODOT paying for the Abernethy Bridge project at Oregon City.

“They started work on it, so they’re throwing more money at it,” Cortright said. “I think the ODOT plan is to repeat that process. Get started on it … and then go to the governor and the Legislature and ask for more.”

Whether ODOT’s plans to reconnect the Albina neighborhood with a freeway cover over I-5 will happen also remains to be seen. The cover has a been a key demand of Portland’s Black community, which is seeking to reconnect the North-Northeast Portland neighborhood that was partially demolished via 20th-century urban renewal practices.

A spokesperson for , the group spearheading the effort, did not respond to messages requesting comment on Thursday.

The post I-5 Rose Quarter project faces $412 million funding loss appeared first on Daily Journal of Commerce.

]]>
I-5 Rose Quarter work to start despite lost federal funds /news/2025/07/25/i5-rose-quarter-construction-funding-loss/ Fri, 25 Jul 2025 18:35:44 +0000 /?p=511377 ODOT will start the $75 million initial phase of the I-5 Rose Quarter Improvement Project in August despite losing $412.5 million in federal funds.

The post I-5 Rose Quarter work to start despite lost federal funds appeared first on Daily Journal of Commerce.

]]>

At a glance:
  • Initial work is set to start Aug. 25, 2025
  • $412.5M in federal funding rescinded by recent legislation
  • will proceed with construction of $75M
  • Full project cost expected to range from $1.5B to $1.9B

Initial construction of the I-5 Rose Quarter Improvement Project is scheduled to begin next month despite the recent loss of $412.5 million in federal funding.

The on Thursday authorized the estimated $75 million phase 1A to proceed. Construction is scheduled to begin on Aug. 25 and continue through fall 2026. That work will primarily be deferred maintenance and . It will involve performing bridge rail retrofits, constructing stormwater treatment facilities for highway runoff to the Willamette River, handling roadway asphalt paving and lighting, installing signage and pavement markings, and building the southern portion of the southbound auxiliary lane between Interstate 84 and the Morrison Bridge.

Phase 1 is currently expected to cost around $549.75 million. Last year, the Oregon Department of Transportation (ODOT) received a $450 million and Neighborhoods grant from the Federal Highway Administration. To date, $37.5 million has been obligated for preliminary engineering of phase 1 and relocating utilities. But the remaining $412.5 million was rescinded as part of the One Big Beautiful Bill Act signed into law by President Trump earlier this month.

Approximately $146.8 million has been spent on the project to this point. Currently, there is around $303.1 million available, and that is expected to pay for professional engineering services tied to phase 1 ($51.3 million), property acquisition to gain right-of-way for phase 1 ($30.3 million), utility relocation for phase 1 ($9 million), all work in phase 1A ($75 million), and other phase 1 construction ($137.5 million).

The commission on Thursday authorized ODOT to continue design of phase 1. The work will involve building the southern portion of the (30 percent of the cover length) and multimodal improvements, completing the southbound auxiliary lane and shoulder from Interstate 405 to the Morrison Bridge exit, extending the northbound auxiliary lane and shoulder under the highway cover, installing signage for highway cover safety and construction, and widening Holladay/Hassalo Bridge, according to the project’s website. Construction is expected to start in early 2027 and finish in 2030.

Travis Brouwer, ODOT assistant director of revenue, finance and compliance, said the agency has enough money to complete phase 1A but not phase 1. There is $137.5 million available for phase 1, but construction of the highway cover is expected to cost from $400 million to $500 million. The $137.5 million will pay for construction of the northbound I-5 auxiliary lane between I-84 and the Weidler Road ramp.

The commission considered the option of pausing construction of phase 1A and seeing if funding will be made available for phase 1 by the but ultimately decided to move forward after weighing risks such as cost increases due to delays and possible lost revenue.

As part of Thursday’s action, ODOT will continue assessing cost reduction concepts to bring the total project budget within the $1.5 billion to $1.9 billion range.

The post I-5 Rose Quarter work to start despite lost federal funds appeared first on Daily Journal of Commerce.

]]>
Oregon, Washington to seek $1.9 billion for I-5 bridge work /news/2025/05/09/interstate-bridge-replacement-funding-2025/ Fri, 09 May 2025 20:28:17 +0000 /?p=508427 State transportation officials are looking to kick off the 15-year effort to replace the Interstate Bridge between Portland and Vancouver.

The post Oregon, Washington to seek $1.9 billion for I-5 bridge work appeared first on Daily Journal of Commerce.

]]>
At a glance:

  • Massive effort to replace expected to last 15 years
  • States set to request funding this summer so construction can start
  • Initial phases will include 24 construction packages and major upgrades
  • Updated cost estimate and final environmental approval expected by 2026

State transportation officials on Thursday said that this summer they will ask for $1.9 billion to begin the 15-year task of replacing the Interstate Bridge.

The project is nearing the end of environmental review, and Oregon and Washington transportation officials are looking to advance the initial phases of two dozen construction packages for building the bridge and a network of interstate expansions and local improvements in Portland and Vancouver.

“So, not to bury the lead — it’s a large (transportation plan) request — probably the largest the agency’s seen,” said Ray Mabey, the project’s assistant program administrator, at Thursday’s meeting. “That is not lost on me — the size and the meaning of that.”

The $1.9 billion would come from both Oregon and Washington state governments, as well as federal funds and expected revenue. The formal request, expected in July, would come in the form of a Statewide Transportation Improvement Program amendment.

The massive ask includes $1.3 billion for construction, $433 million for preliminary engineering, $232 million for right-of-way acquisition and $10 million for utility relocation.

Initially, Oregon taxpayers will shoulder a heavier burden, with general obligation bonds totaling $249.5 million, while Washington will kick in $119.7 million. That will even out over time, and the states will cross-bill each other for project expenses, Mabey said.

The Oregon money will help pay for right-of-way acquisitions near Marine Drive and Hayden Island.

“For the particular projects we’re talking about, the right-of-way need is greater in Oregon,” Mabey said.

The total project was estimated in 2023 to cost $5 billion to $7.5 billion. That range is expected to grow when Interstate Bridge project officials release an updated cost estimate later this year or early in 2026.

Project officials are waiting on a record of decision — a final determination under the National Environmental Policy Act. That’s expected to arrive early in 2026.

“That record of decision is really the key pivot point for us to move into delivery, to start acquiring right-of-way, starting utility relocation, final design, as well as moving into construction,” Mabey said.

Meanwhile, the Bi-State Tolling Subcommittee will soon begin its work in earnest. Tolling on the bridge risks public backlash in Oregon, where such revenue collection is virtually unknown.

Tolling rates will be set in summer 2026, said Travis Brouwer, assistant director for revenue, finance and compliance for the Oregon Department of Transportation.

“This is the first time we’ve set toll rates on a bistate level in a long time,” Brouwer said. “So, we’re going to have to make sure that this follows the law in Washington, the law in Oregon and that those mesh well together.”

Toll scenarios range from $1.55 per crossing before the bridge is completed to $4.70 post completion. All scenarios assume a low-income toll program that will charge low-income drivers less.

Drivers will need to begin opening toll payment accounts and placing transponders in their vehicles, Brouwer said.

The project will take 15 years to build, Mabey said.

“It would take a lot less if we could actually close the interstate and build the whole program,” he said. “But when I asked ( Director Kris Strickler) if we could do that, he said no, and he’s right. So, we need to maintain three through-lanes of traffic in each direction during construction to keep the goods and services and people moving through this corridor.”

The transportation officials sought to assure commissioners that the Trump administration remains committed to the project, for which grants were awarded under the Biden administration.

“What we have heard from this administration is a desire to get this project built and moving forward,” Mabey said. “We see that as a strong sign of support.”

The post Oregon, Washington to seek $1.9 billion for I-5 bridge work appeared first on Daily Journal of Commerce.

]]>
KPFF Consulting Engineers /news/2025/04/25/kpff-sustainable-engineering-portland/ Fri, 25 Apr 2025 14:50:27 +0000 /?p=507460 KPFF sets the standard in sustainable civil and structural engineering with iconic Portland projects and a bold embodied carbon reduction plan.

The post KPFF Consulting Engineers appeared first on Daily Journal of Commerce.

]]>


, founded in 1960, has established itself as a leader in civil, structural, and transportation engineering, serving a wide range of industries, including commercial, residential, and public infrastructure projects. The firm’s collaborative approach ensures that designs meet both functional and aesthetic needs. Notable projects include the in Portland, the largest commercial Living Building, which features construction and operates with net-zero energy, water, and waste. KPFF provided civil and services, ensuring sustainability and resilience.

KPFF’s commitment to sustainability is demonstrated in more than 800 LEED-certified projects, including the first LEED Platinum public housing project, in Portland. The firm also pioneered Portland’s first integrated green street neighborhood, New Columbia. Additionally, in 2024, KPFF updated its Action Plan, committing to reducing embodied carbon in structural engineering projects by 2050.

With a focus on sustainable development and a strong presence in Portland, where its office has become one of the largest civil and structural engineering firms, KPFF continues to shape the built environment. The firm’s work supports the growth of sustainable, thriving communities across the Pacific Northwest, with a strong emphasis on collaboration and innovation.

The post KPFF Consulting Engineers appeared first on Daily Journal of Commerce.

]]>