Sunrise Water Authority – Daily Journal of Commerce /news/tag/sunrise-water-authority/ Building and Construction News in Portland, Oregon and the Pacific Northwest Mon, 27 Dec 2021 18:03:25 +0000 en-US hourly 1 https://wordpress.org/?v=6.6.6 /files/2023/08/favicon.webp Sunrise Water Authority – Daily Journal of Commerce /news/tag/sunrise-water-authority/ 32 32 Bids going out for FFA-designed Sunrise Water Authority campus /news/2021/12/22/bids-going-out-for-ffa-designed-sunrise-water-authority-campus/ Wed, 22 Dec 2021 19:05:37 +0000 /?p=263303 From start to finish in the pandemic, The Sunrise Water Authority's new office building is the first project designed by FFA Architecture and Interiors while entirely remote.

The post Bids going out for FFA-designed Sunrise Water Authority campus appeared first on Daily Journal of Commerce.

]]>
The ‘s new 15,000-square-foot administrative building is designed with water features and to reach a low Energy Utilization Index of 15. (Renderings courtesy of FFA Architecture and Interiors)

From start to finish in the pandemic, The Sunrise Water Authority’s new office building is the first project designed by FFA Architecture and Interiors while entirely remote.

, a principal, said the firm landed the project the week after everybody started working from home in spring 2020 and it was an adjustment at first.

When you have a team of five people in an office, he added, the communication is pretty fluid. But when you have to jump on a remote call to talk about it – it changes things.

Sunrise Water Authority will move from its current facility on S.E. 129th Avenue in Happy Valley to a 5-acre parcel of land at the northeast corner of Southeast 172nd Avenues and Southeast Armstrong Circle, also in Happy Valley.

The campus will centralize the company with a new administrative and shop building. The complex will also include a staff courtyard, parking areas, materials storage and a fuel island.

The Sunrise Water Authority is the clean water supplier for Happy Valley, Damascus and . Gelbrich said because of this a lot of the positioning of the buildings and design is tied to the expression of water. For instance, a slopped site is typically a flaw that needs to be corrected, but instead FFA incorporates it into the design.

All of the water that hits the building’s roof will spill onto a lower roof basin, routed to scuppers, then cascade down the side of the buildings in a waterfall. The water then runs over to the rain gardens, where it is soaked into the soil or directed to an existing wetland at the bottom of the site. Even with a little rainfall, Gelbrich said people will see the water be collected and flow down to the wetland.

FFA has also designed the main 15,000-square-foot administrative building to reach a low Energy Utilization Index of 15 and readied the 5,700-square-foot Shop Building to eventually be net-zero.

The main building’s orientation, plus and concrete structure, is designed to reduce heat gain. These measures — combined with an efficient VRF mechanical system, LED light fixtures and a large photovoltaic array on the roof — will allow the building to reach the low EUI. In the future, the PV array can also be expanded to the one-story Shop Building that has a CLT structure.

The project will go out to bid on Jan. 5 and work is expected to be complete in 2023.

 

The post Bids going out for FFA-designed Sunrise Water Authority campus appeared first on Daily Journal of Commerce.

]]>
Reservoir project involves huge excavation effort /news/2018/09/21/reservoir-project-involves-huge-excavation-effort/ Fri, 21 Sep 2018 21:26:30 +0000 /?p=180092 An $8.5 million project is under way to create a new 3 million-gallon concrete water reservoir off of Southeast Verlie Street in Happy Valley.

The post Reservoir project involves huge excavation effort appeared first on Daily Journal of Commerce.

]]>
The existing 2.5 million-gallon reservoir off of Verlie Street in Happy Valley will be renovated while a new 3 million-gallon reservoir is built by Ward-Henshaw Construction. (Josh Kulla/91Ƶ)
The existing 2.5 million-gallon reservoir off of Verlie Street in Happy Valley will be renovated while a new 3 million-gallon reservoir is built by . (Josh Kulla/91Ƶ)

A new 3 million-gallon concrete water reservoir is being built off of Southeast Verlie Street in Happy Valley, and it’s a jarring sight amid some single-family homes in the suburb.

A massive amount of earth has been scooped out of the hillside by , the excavation subcontractor for the new $8.5 million reservoir project being carried out by the and general contractor Ward-Henshaw Construction of Canby. In all, more than 44,000 cubic yards of dirt and 8,000 cubic yards of bedrock will be excavated and hauled from the site in order to allow the new reservoir to sit alongside an existing 2.5 million-gallon concrete tank at the same grade.

“It’s a huge amount of dirt and a huge amount of rock,” said Wade Hillard, senior superintendent in charge of the jobsite for Ward-Henshaw Construction. “The first step was just getting all the mass excavation out, and now we’re at the rock excavation.”

The project is one of the largest undertaken by the Sunrise Water Authority in recent years and comes in belated response to population growth.

“We’re a little behind on keeping up with that,” said Dan Fraijo, project manager for the water provider. “So, this will bring us up to par. But not too much extra.”

Space has been reserved for more than a decade for the new reservoir. The project is part of the agency’s 20-year capital improvement plan.

Ron Balch, a heavy equipment operator with Landis & Landis Construction, excavates at the site of a new reservoir under construction in Happy Valley. (Josh Kulla/91Ƶ)
Ron Balch, a heavy equipment operator with Landis & Landis Construction, excavates at the site of a new reservoir under construction in Happy Valley. (Josh Kulla/91Ƶ)

Excavation and construction is expected to take around 16 months to complete. A further five months will be needed for backfill and final grading, with a final goal, Fraijo said, of getting the new reservoir online by late summer 2019.

Because of its sensitive location in the middle of an affluent suburb, the project is being carried out with restrictions on noise and hours of operation. There even are a pair of decibel meters on fences to the east and west sides of the excavation site to ensure adherence to agreed-upon noise limits.

“This job is interesting just because it’s in the tight quarters of this neighborhood,” Hillard said. “So, the logistics and access and stuff has been a little bit of a fight keeping the neighbors happy, keeping the owners happy and keeping it on schedule. It’s a constant grind.”

Technically, a reservoir is little more than a round concrete tank placed atop a large concrete slab and footings. But this reservoir is being constructed with seismic resilience in mind; it’s not a conventional post-tensioned concrete structure.

“Everything is independent of each other,” Hillard said. “If you look at a house or a school, you have your concrete footing and your rebar sticking out and then your wall would sit on top of that rebar and everything’s tied together with steel and concrete. Whereas on this reservoir it’s completely independent of each other.”

Instead, the concrete core walls sit on rubber pads and are strengthened on the interior by vertical seismic tendons similar to post-tensioned cables.

An existing reservoir will undergo renovation while the new 3 million-gallon Reservoir 11 is constructed. (Josh Kulla/91Ƶ)
An existing reservoir will undergo renovation while the new 3 million-gallon Reservoir 11 is constructed. (Josh Kulla/91Ƶ)

“You don’t have any rebar connecting things, so you have the seismic cables and you have rubber,” Hillard said. “In theory, if there’s ever a seismic event the wall is independent of the footing.”

Concrete reservoirs are not only stronger than their steel counterparts, but also far easier to maintain over time.

“The biggest difference is there is basically zero maintenance on the concrete reservoirs; it’s all poured and done,” Hillard said. “If you have a steel tank you have to go in probably on a yearly basis because they’re coated and they’re not going to last as long.”

That’s a huge consideration in the face of regional population growth and the need to build further infrastructure in coming years, which is exactly what the Sunrise Water Authority is planning for. It has plans to build another reservoir and has already contracted with Clackamas River Water for storage space in a new 6 million-gallon reservoir that agency is building off of Southwest 152nd Avenue as part of an eight-year, $40 million series of infrastructure projects.

“There is another reservoir planned at this same elevation further east within the next five to 10 years just to keep up with that curve,” Fraijo said.

The post Reservoir project involves huge excavation effort appeared first on Daily Journal of Commerce.

]]>