Willamette Water Supply Program – Daily Journal of Commerce /news/tag/willamette-water-supply-program/ Building and Construction News in Portland, Oregon and the Pacific Northwest Thu, 04 Mar 2021 21:06:47 +0000 en-US hourly 1 https://wordpress.org/?v=6.6.6 /files/2023/08/favicon.webp Willamette Water Supply Program – Daily Journal of Commerce /news/tag/willamette-water-supply-program/ 32 32 One piece of a $1.3 billion infrastructure puzzle /news/2021/03/02/one-piece-1-3-billion-infrastructure-puzzle/ Tue, 02 Mar 2021 22:52:09 +0000 /?p=254781 Crews are busy constructing raw water facilities to serve Beaverton, Hillsboro and other portions of Washington County.

The post One piece of a $1.3 billion infrastructure puzzle appeared first on Daily Journal of Commerce.

]]>
A crew from Pacific Foundation works to drill foundation shafts where a pipeline to carry raw water will be installed 60 feet beneath the surface and run under
A Pacific Foundation crew is working in Wilsonville to drill foundation shafts for a pipeline that will be installed 60 feet beneath the surface. (Josh Kulla/for the 91Ƶ)

An effort to build new raw water facilities for the west side of the Portland-metro area is well under way in Wilsonville.

The facilities are at the site of the existing Willamette River Water Treatment Plant, which was developed in partnership between the city of Wilsonville and in 2002. It was designed and built with the intention of future expansion, which is now coming to pass.

Now, the – a partnership between the Tualatin Valley Water District and the cities of Beaverton and Hillsboro – is carrying out this expansion as part of a massive $1.3 billion project involving construction of over 30 miles of pipeline, a new water treatment plant in Sherwood, pump stations, and other infrastructure to supply water to customers in unincorporated Washington County as well as Beaverton and Hillsboro.

The raw water intake facilities being built by general contractor Kiewit Corporation consist of expanded or upgraded fish screens, an intake pipe, a caisson, a pump station building and related equipment. Once completed, raw water from will be pumped through a 66-inch pipeline from Wilsonville to a new state-of-the-art water filtration plant in Sherwood’s Tonquin Employment Area. Ground is scheduled to be broken on that plant later this year.

In Wilsonville, part of the work also includes seismic earthwork. It’s scheduled for completion in June.

Construction of the raw water facilities is being done in phases; completion is expected by 2024. The full Willamette Water Supply Program effort will not wrap up until at least 2026.

Right now, crews from Condon-Johnson & Associates, Pacific Foundation, Kiewit Corporation and subcontractors are involved in drilling related to the seismic earthwork on the lower site near the river. Preparation is under way for installation of the southern end of the 66-inch pipeline.

On the upper (north) side of the site, crews last month began installing new water and sewer utilities and connections to existing utilities. Those pieces will serve a new electrical building that provides power for the pump station and other infrastructure.

Meanwhile, Arrowhead Creek is receiving a trenchless crossing. Crews are building and excavating the launch and receiving shafts. Work on the trenchless pipeline crossing itself is set to begin in April.

Late last month, workers began installing a large underground vault (to hold a large meter and valves) in the northwest corner of the upper side of the site.

To learn more about the project, visit: .

A crew from Pacific Foundation works to drill foundation shafts where a pipeline to carry raw water will be installed 60 feet beneath the surface and run underneath Arrowhead Creek. (Josh Kulla Photography)
Pacific Foundation workers drill foundation shafts for a pipeline that will run underneath Arrowhead Creek. (Josh Kulla/for the 91Ƶ)
A heavy equipment operator with Condon-Johnson uses an auger to drill a pre-grout shaft as part of the foundation work being done. (Josh Kulla Photography)
A heavy equipment operator with Condon-Johnson & Associates uses an auger to drill a pre-grout shaft as part of foundation work. (Josh Kulla/for the 91Ƶ)
A Pacific Foundation employee removes soil from an auger. (Josh Kulla Photography)
A Pacific Foundation employee removes soil from an auger. (Josh Kulla/for the 91Ƶ)
A crew from Pacific Foundation works to drill foundation shafts where a pipeline to carry raw water will be installed 60 feet beneath the surface and run under
Drilling is under way at the project site. (Josh Kulla/for the 91Ƶ)
0303_raw_water_intake_06_web
(Josh Kulla/for the 91Ƶ)
The Wilsonville Raw Water Intake Project includes development of water intake and transmission facilities at the Willamette River Water Treatment Plant, including installation of a 66-inch raw water pipeline, construction of a new electrical building, and associated improvements to Willamette River Water Treatment Plant Park. (Josh Kulla Photography)
The project includes development of water intake and transmission facilities at the Willamette River Water Treatment Plant, including installation of a 66-inch raw water pipeline, construction of a new electrical building, and associated improvements to Willamette River Water Treatment Plant. (Josh Kulla/for the 91Ƶ)
A crew from Condon-Johnson carries out deep foundation grouting at the edge of the Willamette River to shore up soil for the construction of a new raw water intake. (Josh Kulla Photography)
A Condon-Johnson & Associates crew carries out deep foundation grouting at the edge of the Willamette River to shore up soil for construction of a new raw water intake. (Josh Kulla/for the 91Ƶ)
A Condon-Johnson employee oversees drilling work. (Josh Kulla Photography)
A Condon-Johnson employee oversees drilling work. (Josh Kulla/for the 91Ƶ)
Employees of Pacific Foundation assist with a foundation drilling operation. (Josh Kulla Photography)
Pacific Foundation employees assist with a foundation drilling operation. (Josh Kulla/for the 91Ƶ)
A crew from Pacific Foundation works to drill foundation shafts where a pipeline to carry raw water will be installed 60 feet beneath the surface and run under
(Josh Kulla/for the 91Ƶ)
A crew from Pacific Foundation works to drill foundation shafts where a pipeline to carry raw water will be installed 60 feet beneath the surface and run under
(Josh Kulla/for the 91Ƶ)

The post One piece of a $1.3 billion infrastructure puzzle appeared first on Daily Journal of Commerce.

]]>
An immense investment in infrastructure /news/2019/11/21/immense-investment-infrastructure/ Thu, 21 Nov 2019 21:19:43 +0000 /?p=196661 Multiple projects under way are part of the $1.3 billion Willamette Water Supply Program in Washington County.

The post An immense investment in infrastructure appeared first on Daily Journal of Commerce.

]]>
Emery & Sons Construction laborers, from left, Jordan Allenby, Trey Renoud and Anthony Duvall backfill around a new water pipeline in Washington County. (Josh Kulla/91Ƶ)
laborers, from left, Jordan Allenby, Trey Renoud and Anthony Duvall backfill around a new water pipeline in Washington County. (Josh Kulla/91Ƶ)

One of the largest construction projects in Oregon right now is taking place mostly underground.

The $1.3 billion is an amalgam of dozens of infrastructure projects that together over the next six years will provide a long-term water supply for the west side of the Portland-metro area. The is the managing partner for all of the work, which began in 2015 with construction of a 2.7-mile-long pipeline along the new Southwest 124th Avenue in unincorporated Washington County.

That project was the first of many involving a host of municipal, county and regional partners that together will total more than 30 miles of finished pipeline by 2026. Supportive infrastructure will include a new water treatment plant in Sherwood’s Tonquin Employment Area, a raw water intake facility on the river in Wilsonville and a new reservoir on Cooper Mountain with twin 15 million gallon tanks. Plus, these efforts will be accompanied by a number of large road projects.

It’s a massive undertaking, and one that the water district hopes will secure enough fresh water to accommodate anticipated an increase in population in Washington County by as many as 200,000 people by 2040.

“An engineering firm and a contractor are hired to do each individual project,” said Libby Bakke of Barney & Worth, a Portland-based communications firm helping coordinate public outreach. “For such a large, complex project, it’s been on time and on budget. It’s one of Oregon’s largest infrastructure projects and it’s been very successful so far at getting pipe in the ground.”

Erik Elkins, safety coordinator for Emery & Sons Construction Group, peers down into a trench holding the leading edge of a 66-inch water line. The line is part of the greater Willamette Water Supply Program, a $1.3 billion project to supply water to Washington County. (Josh Kulla/91Ƶ)
Erik Elkins, safety coordinator for Emery & Sons Construction Group, peers down into a trench holding the leading edge of a 66-inch water line. The project is part of the greater Willamette Water Supply Program. (Josh Kulla/91Ƶ)

The Willamette Water Supply Program is the public banner under which the Tualatin Valley Water District, consulting firm , Washington County, the cities of Hillsboro, Beaverton, Sherwood, Wilsonville and others are operating. Throughout the early planning stages, a premium was placed on being able to carry out road and pipe projects simultaneously to save both time and money. The first such project was Southwest 124th Avenue, but many others will be done in the same fashion. All are being constructed to the latest seismic standards.

“On six projects we’re partnering with Washington County,” said Andre Tolme, a construction manager with the Willamette Water Supply Program. “We’re working with their land-use and transportation departments to determine where they plan to do road widening and improvements or build new roads. Then we’re constructing our large-diameter water pipelines at the same time as the road construction. It saves money for public agencies, the taxpayers and rate payers, and significantly decreases the impact to the public.”

Maintaining transparency is a key part of the entire endeavor and the reason for extensive public outreach. The Willamette Water Supply Program recently benefited from the award of a $640 million U.S. Environmental Protection Agency grant. It came via the Water Infrastructure Finance and Innovation Act program established by the Obama administration.

“It’s huge,” said Joelle Bennett, deputy director for the Willamette Water Supply Program. “Large projects across the country compete for this funding, and it impacts all rate-paying customers.”

Tim Fowler, an operating engineer with Emery & Sons Construction, compacts a load of backfill gravel with water prior to filling a pipeline trench. (Josh Kulla/91Ƶ)
Tim Fowler, an operating engineer with Emery & Sons Construction Group, compacts a load of backfill gravel with water prior to filling a pipeline trench. (Josh Kulla/91Ƶ)

Currently, several general contractors’ crews are carrying out sizable pipeline and road projects. The most noteworthy ones are a pair of large pipeline efforts near the edge of the urban growth boundary west of Cooper Mountain in Beaverton. There, a 7,000-foot-long pipe is being installed along Roy Rogers Road in partnership with Washington County, which is improving that road at the same time. An even larger project is being carried out along Scholls Ferry Road west to Tile Flat Road: General contractor Emery & Sons Construction Group is laying over 10,000 feet of 66-inch-diameter, cement-lined steel pipe next to a massive residential development being constructed up to the edge of the UGB by developer .

With all the Willamette Water Supply Program projects numbered by phase and geography, the so-called Scholls Area Pipeline Project is actually three separate major projects totaling 7.2 miles of pipeline. Phase one is the project along Roy Rogers Road, which will see some 7,000 feet of pipe installed during the course of 2020. Phase two is the 10,000-foot stretch being constructed along Scholls Ferry and Tile Flat roads north to the new reservoir site. Phase three will see the pipeline extended from the reservoir at Grabhorn Road north to Farmington Road, with construction there anticipated to start in 2022.

Emery & Sons crews are currently backfilling new sections of pipeline and preparing to excavate a new section along the east side of Tile Flat Road.

“The hardest thing with this project was coordinating with the developer (Polygon Northwest) to widen the road and develop their property,” Tolme said, pointing east across open fields toward newly installed erosion control measures.

Crews have completed 3,200 feet of the new segment and are now grouting and finishing the interior of the last stretch of completed line in preparation for hydrostatic pressure testing. Then excavation will resume.

Emery & Sons Construction is installing over 10,000 feet of pipe as part of the Scholls Area Pipeline Project, a 7.2-mile portion of the larger Willamette Water Supply Program. (Josh Kulla/91Ƶ)
Emery & Sons Construction Group is installing over 10,000 feet of pipe as part of the Scholls Area Pipeline Project. (Josh Kulla/91Ƶ)

“They’re doing the interior grouts for the welded joints,” Emery & Sons project manager Ryan Knox said. “Also, our inspector is in there checking out the work, so we have an opening up here and a manway where they are working their way through the pipe.”

Construction on this phase began in early 2019 and is expected to wrap up in November 2020.

By then, Willamette Water Supply Program construction will be entering its busiest stretch.

“2021 and ’22 will be the busiest construction years, where we’ll have 10 projects simultaneously going,” Tolme said. “We have three others right now that are just getting started.”

An overview of the Willamette Water Supply Program is available at

Laborer Trey Renoud of Emery & Sons Construction compacts backfill material. (Josh Kulla/91Ƶ)
Trey Renoud compacts backfill material. (Josh Kulla/91Ƶ)
Erik Elkins, safety coordinator for Emery and Sons Construction, prepares to check on a crew working in a pipeline trench. (Josh Kulla/91Ƶ)
Erik Elkins prepares to check on a crew working in a pipeline trench. (Josh Kulla/91Ƶ)
Crews are laying over 10,000 feet of 66-inch diameter water pipe along Southwest Scholls Ferry Road and the surrounding area during phase two of the Scholls Area Pipeline Project. (Josh Kulla/91Ƶ)
Crews are laying over 10,000 feet of 66-inch diameter water pipe along Southwest Scholls Ferry Road and the surrounding area during phase two of the Scholls Area Pipeline Project. (Josh Kulla/91Ƶ)

The post An immense investment in infrastructure appeared first on Daily Journal of Commerce.

]]>