Woodburn High School – Daily Journal of Commerce /news/tag/woodburn-high-school/ Building and Construction News in Portland, Oregon and the Pacific Northwest Fri, 08 Jan 2021 23:30:11 +0000 en-US hourly 1 https://wordpress.org/?v=6.6.6 /files/2023/08/favicon.webp Woodburn High School – Daily Journal of Commerce /news/tag/woodburn-high-school/ 32 32 Bright future building in wake of tragedy /news/2021/01/05/bright-future-awaits-school-tragedy/ Tue, 05 Jan 2021 23:32:17 +0000 /?p=252838 Nearly nine years after a fire destroyed career and technical education space at Woodburn High School, new space is rising.

The post Bright future building in wake of tragedy appeared first on Daily Journal of Commerce.

]]>
An ironworker with Local 29 and Volk Steel Erectors welds a beam in place as part of an outdoor walkway at Woodburn High School. (Josh Kulla/91Ƶ)
An ironworker with Local 29 and Volk Steel Erectors welds a beam into place for a new walkway at . (Josh Kulla/for the 91Ƶ)

In May 2012 a devastating fire tore through Woodburn High School and destroyed its career and technical education (CTE) wing.

But a replacement building and another two-story classroom building are finally on the horizon. General contractor is tackling both on the north side of campus.

The CTE building will have 10,180 square feet and the classroom building will have 17,200 square feet. That space will allow the school to retire 10 portable classrooms that were set up in the wake of the fire.

“There’s a lot going on,” Triplett Wellman Contractors Superintendent Nikita Cherepanov said. “That building going up there, that’s a CTE building; it’s going to have a shop and a video room. They used to have a trades program. And (the space) burned down.”

Cherepanov is quite familiar with the school.

“I am from Woodburn originally, and I graduated from this high school in 1996,” he said. “What a small world, right?”

The new CTE facility won’t replace all of the trades education space lost in the fire. But the technology and equipment will be state of the art.

“I remember going to that shop and that welding class, but now it doesn’t exist because it all burned down,” Cherepanov said. “Hence, the CTE (building) to replace it, because right now they just have one classroom and they just can’t facilitate that program with the limited space that they have.”

The two-story addition will hold eight classrooms. Both new buildings are slab-on-grade, with structural steel and steel-stud framing. A covered, curvy walkway will connect the two structures.

Crews have encountered challenges while installing the steel beams for the walkway, Cherepanov said. They’re heavy and curvy, and present unusual hurdles for surveying and measuring.

“But at least in this situation we do have a point of radius – that’s it over there, that stake,” he said, pointing to a spot between the two new structures. “Sometimes you don’t have that where you have a clear sweep, so then that’s even more difficult. This one it works out that we do have it, so that you can still pull a string and a tape and do your arch and you know you can make it work.”

The new buildings are scheduled for completion this summer, ahead of the start of the 2021-22 school year.

A two-story classroom addition with 17,200 square feet of space is being constructed alongside a 10,180 square foot CTE facility at Woodburn High School by general contractor Triplett Wellman Construction. (Josh Kulla/91Ƶ)
A two-story classroom addition will have 17,200 square feet of space. (Josh Kulla/for the 91Ƶ)
A curving covered walkway built with structural steel will connect the new classroom building with the new CTE wing at Woodburn High School. (Josh Kulla/91Ƶ)
A new, curvy walkway will connect the new CTE wing and the new classroom building at Woodburn High School. (Josh Kulla/for the 91Ƶ)
A crew of ironworkers with Local 29 and Volk Steel Erectors work together to raise a curved steel beam into place as part of the covered walkway connecting the two new buildings. (Josh Kulla/91Ƶ)
A crew of ironworkers with Local 29 and Volk Steel Erectors work together to raise a steel beam into place for the new walkway. (Josh Kulla/for the 91Ƶ)
A curving covered walkway built with structural steel will connect the new classroom building (background) with the new CTE wing at Woodburn High School. (Josh Kulla/91Ƶ)
A curvy, covered walkway will connect new spaces being constructed at Woodburn High School. (Josh Kulla/for the 91Ƶ)
A new 10,180 square foot CTE building is being built as part of a sizable new expansion at Woodburn High School that will finally replace a wing of the school destroyed in a 2012 fire. (Josh Kulla/91Ƶ)
The CTE building will help replace space that was destroyed by fire in 2012. (Josh Kulla/for the 91Ƶ)
A new softball field is being installed at Woodburn High School as part of a large new building expansion project. (Josh Kulla/91Ƶ)
A new softball field is being built at Woodburn High School as part of the expansion. (Josh Kulla/for the 91Ƶ)
A two-story classroom addition with 17,200 square feet of space is being constructed alongside a 10,180 square foot CTE facility at Woodburn High School by general contractor Triplett Wellman Construction. (Josh Kulla/91Ƶ)
A two-story, 17,200-square-foot building will hold eight classrooms. (Josh Kulla/for the 91Ƶ)
A new 10,180 square foot CTE building is being built as part of a sizable new expansion at Woodburn High School that will finally replace a wing of the school destroyed in a 2012 fire. (Josh Kulla/91Ƶ)
A new, 10,180-square-foot CTE building is being constructed as part of a sizable expansion at Woodburn High School. (Josh Kulla/for the 91Ƶ)
Constructions trades, audio-visual and other professional skills will be taught in the new CTE wing at Woodburn High School currently being built by general contractor Triplett Wellman Construction. (Josh Kulla/91Ƶ)
Construction, audiovisual and other professional skills will be taught in the new CTE wing at Woodburn High School. (Josh Kulla/for the 91Ƶ)
A courtyard previously occupied by classroom space will separate the new CTE wing from the existing building. (Josh Kulla/91Ƶ)
A courtyard previously occupied by classroom space will separate the new CTE wing from the existing school building. (Josh Kulla/for the 91Ƶ)
The new classroom wing as viewed from the new CTE facility at Woodburn High School. (Josh Kulla/91Ƶ)
The walkway, at left, will connect the new classroom wing with the new CTE building. (Josh Kulla/for the 91Ƶ)
0106_woodburn_high_12_web
(Josh Kulla/for the 91Ƶ)
Ironworkers with Local 29 and Volk Steel Erectors rig a curved beam in place for an outdoor walkway at Woodburn High School. (Josh Kulla/91Ƶ)
Ironworkers with Local 29 and Volk Steel Erectors rig a curved beam at Woodburn High School. (Josh Kulla/for the 91Ƶ)
Ironworkers with Local 29 and Volk Steel Erectors rig a curved beam in place for an outdoor walkway at Woodburn High School. (Josh Kulla/91Ƶ)
Ironworkers with Local 29 and Volk Steel Erectors rig a curvy beam for placement at Woodburn High School. (Josh Kulla/for the 91Ƶ)
0106_woodburn_high_15_web
(Josh Kulla/for the 91Ƶ)
Ironworkers with Local 29 and Volk Steel Erectors erect a beam as part of an outdoor walkway at Woodburn High School. (Josh Kulla/91Ƶ)
Ironworkers with Local 29 and Volk Steel Erectors maneuver a beam into place. (Josh Kulla/for the 91Ƶ)
Carpenters with Triplett Wellman Construction sheath an exterior wall of the CTE wing with plywood. (Josh Kulla/91Ƶ)
Carpenters with Triplett Wellman Contractors sheath an exterior wall of the CTE wing with plywood. (Josh Kulla/for the 91Ƶ)
A Local 29 ironworker with Volk Steel Erectors hammers in an expansion bolt into a structural steel connection on the top of a covered walkway. (Josh Kulla/91Ƶ)
A Local 29 ironworker with Volk Steel Erectors hammers an expansion bolt into a structural steel connection for a new walkway. (Josh Kulla/for the 91Ƶ)