DeWitt Construction – Daily Journal of Commerce /news/tag/dewitt-construction/ Building and Construction News in Portland, Oregon and the Pacific Northwest Mon, 15 Nov 2021 17:02:31 +0000 en-US hourly 1 https://wordpress.org/?v=6.6.6 /files/2023/08/favicon.webp DeWitt Construction – Daily Journal of Commerce /news/tag/dewitt-construction/ 32 32 Massive structure beginning to take shape /news/2020/05/19/massive-structure-beginning-take-shape/ Tue, 19 May 2020 20:40:22 +0000 /?p=246459 Portland International Airport’s new Parking Addition and Consolidated Rental Car facility is gaining steel elements.

The post Massive structure beginning to take shape appeared first on Daily Journal of Commerce.

]]>
An ironworker with Arizona-based Schuff Steel Company sets an I-beam on the Parking Addition and Consolidated Rental Car project at Portland International Airport. (Josh Kulla/91Ƶ)
An ironworker with Arizona-based Schuff Steel Company sets an I-beam on the Parking Addition and Consolidated Rental Car project at Portland International Airport. (Josh Kulla/91Ƶ)

At roughly 1.6 million square feet, the Parking Addition and Consolidated Rental Car (PACR) facility being constructed at Portland International Airport easily has the biggest footprint of any current project in the metro area.

It’s a whole lot of structural steel.

“It’s just a really, really big structure,” said Chris Hermreck, a senior project manager with general contractor Construction. “We’re building this garage that’s the size of these entire two (existing) buildings.”

The 2,400-space parking garage, designed by , is being constructed via a progressive design-build contract. The new, seismically resilient (category 4) structure will hold offices, long-term parking, rental car service and offices, and a parking toll plaza.

The latter is already up and running, which enabled demolition and clearance of the old plaza, which sat where the new parking garage is on the rise. A new garage for rental car fueling, cleaning and storage has also been constructed.

One of the most significant phases of work in the entire project is under way: Ironworkers from Phoenix, Arizona-based Schuff Steel Co. have begun structural work on the 100,000-square-foot office building and five-level parking garage. Also, Carr Construction has been contracted to perform miscellaneous steel work.

The first sections of structural steel are being erected for a new 1.6 million-square-foot parking garage at Portland International Airport. (Josh Kulla/91Ƶ)
The first sections of structural steel are being erected for a new 1.6 million-square-foot parking garage at Portland International Airport. (Josh Kulla/91Ƶ)

Up to 50 ironworkers could be on site at one time when steel work reaches its peak later this summer, Hermreck estimated. The first column was set April 20, he added, and completion of structural work is anticipated sometime during the fourth quarter of this year.

Along with the sheer scope of work, steel erection is also challenged by the project location inside restricted Federal Aviation Administration airspace. This meant a traditional tower crane could not be used on site. Instead, crews are using a massive crawler crane with an articulated boom arm.

“This was a specially considered crane for a lot of reasons,” Hermreck said. “For capacity, and also because of the way it lays down at night. This has the reach and capacity and also the ability to get low enough.”

is part of the five-year, $2 billion-plus program in which nearly all of Portland International Airport is receiving upgrades. Construction of a new main terminal, the so-called T-Core project, is the centerpiece.

When it comes to PACR, work involves modifications to the existing P2 parking structure as well as significant improvements to surface roadways and underground utilities. Existing parking garages will connect to the new one.

Union ironworkers with Schuff Steel Company set an I-beam at Portland International Airport. Steel erection on the PACR project began last month and is expected to finish late this year. (Josh Kulla/91Ƶ)
Union ironworkers with Schuff Steel Company set an I-beam at Portland International Airport. Steel erection on the PACR project began last month and is expected to finish late this year. (Josh Kulla/91Ƶ)

JE Dunn is self-performing the concrete work for this project, while continues excavation and pile driving to accommodate construction of the new parking structure. Other major subcontractors on the job include and JH Kelly Mechanical.

Once the new garage is complete, a temporary exit road will be shut down and a new exit connecting the new P3 garage and exit plaza will be installed.

The entire project should wrap up in 2021, according to the Port of Portland.

Union ironworkers with Schuff Steel Co. are erecting the first sections of a 1.6 million-square-foot parking garage at Portland International Airport. (Josh Kulla/91Ƶ)
Union ironworkers with Schuff Steel Co. are erecting the first sections of a 1.6 million-square-foot parking garage at Portland International Airport. (Josh Kulla/91Ƶ)
A below-grade tunnel will funnel traffic out of the new parking garage at Portland International Airport. (Josh Kulla/91Ƶ)
A below-grade tunnel will funnel traffic out of the new parking garage at Portland International Airport. (Josh Kulla/91Ƶ)
An ironworker helps erect 1.6 million-square-foot paarking garage at Portland International Airport. (Josh Kulla/91Ƶ)
An ironworker helps erect 1.6 million-square-foot paarking garage at Portland International Airport. (Josh Kulla/91Ƶ)
JE Dunn Construction is building the Parking Addition and Consolidated Rental Car project at Portland International Airport. (Josh Kulla/91Ƶ)
JE Dunn Construction is building the Parking Addition and Consolidated Rental Car project at Portland International Airport. (Josh Kulla/91Ƶ)
A union ironworker sets an I-beam on a parking garage at Portland International Airport. (Josh Kulla/91Ƶ)
A union ironworker sets an I-beam on a parking garage at Portland International Airport. (Josh Kulla/91Ƶ)
Schuff Steel Co. of Phoenix, Arizona, is performing steel erection on a 1.6 million-square-foot parking garage at Portland International Airport. (Josh Kulla/91Ƶ)
Schuff Steel Co. of Phoenix, Arizona, is performing steel erection on a 1.6 million-square-foot parking garage at Portland International Airport. (Josh Kulla/91Ƶ)
The new parking garage will be connected to an existing seven-level structure. (Josh Kulla/91Ƶ)
The new parking garage will be connected to an existing seven-level structure. (Josh Kulla/91Ƶ)
A union ironworker sets an I-beam. (Josh Kulla/91Ƶ)
A union ironworker sets an I-beam. (Josh Kulla/91Ƶ)
Steel erection on a new parking garage and operations addition is under way at Portland International Airport. (Josh Kulla/91Ƶ)
Steel erection on a new parking garage and operations addition is under way at Portland International Airport. (Josh Kulla/91Ƶ)

The post Massive structure beginning to take shape appeared first on Daily Journal of Commerce.

]]>
Complex transportation improvements advancing at PDX /news/2019/10/04/complex-transportation-improvements-advancing-pdx/ Fri, 04 Oct 2019 21:10:59 +0000 /?p=195059 A critical project under way at Portland International Airport will add a new six-story, 2,400-space parking garage, a four-story office building with an on-site car rental facility and a new exit plaza.

The post Complex transportation improvements advancing at PDX appeared first on Daily Journal of Commerce.

]]>
Excavation is under way on a project to construct a new parking garage and rental car facility at Portland International Airport. (Josh Kulla/91Ƶ)
Excavation is under way on a project to construct a new parking garage and rental car facility at Portland International Airport. (Josh Kulla/91Ƶ)

The five-year, $2 billion-plus program calls for upgrading nearly all of Portland International Airport, piece by piece. Construction of a new main terminal is the heart of the initiative. But another critical project now under way will add a new six-story, 2,400-space parking garage, a four-story office building with an on-site car rental facility and a new exit plaza.

The new Parking Additions and Consolidated Rental Car Facility is expected to significantly help travelers and airport employees enter and exit the grounds.

“We’re really looking at it more as a transportation improvement around the whole airport,” spokeswoman Kama Simonds said.

and Construction are using a progressive design-build model that allows for rapid and timely changes as needed.

The scope of work includes new offices for airport operations, additional long-term parking, a consolidated rental car facility, new rental car offices and a new and relocated parking toll plaza. Efforts that will enable these additions include modifications to the existing P2 parking structure as well as significant upgrades to surface roadways and underground utilities.

Work began over a year ago, and much has taken place since. The exit plaza building and travel lanes are nearly complete, and a new parking garage for rental car fueling, cleaning and storage has also been constructed. Another important portion of the project involves moving underground utilities out of the new buildings’ footprint.

JE Dunn is self-performing the concrete work for this project, and plenty of that remains – especially for the new parking structure. Crews are also building temporary ramps from the existing parking structures to provide egress while the new parking garage is built.

Finally, crews are excavating and pile driving to accommodate construction of the new parking structure. Because of the sensitivity of the radar systems and others used in the airport control tower, vibratory pile driving is being used instead of traditional drilling.

Much of the work involves temporary structures or solutions that will enable crews to complete permanent ones. That’s the case with a roadway being built to connect the parking structures with the new exit plaza. Once the new garage is complete, the temporary road will come out and a new roadway running straight east from the new P3 garage to the new exit plaza will be built.

Cement masons with Local 555 and JE Dunn Construction finish concrete on a new exit plaza at Portland International Airport. (Josh Kulla/91Ƶ)
Cement masons with Local 555 and JE Dunn Construction finish concrete on a new exit plaza at Portland International Airport. (Josh Kulla/91Ƶ)

“Ultimately, they will all come out on level three on P3, and it will be an elevated roadway all the way out of here,” said Anna Tindall, a Port of Portland civil engineering inspector. “You can see the squares down there – those are the piles they’ve already driven for the elevated roadway. This will all end up being an elevated roadway.”

Another crucial part of the will be the addition of a second light-rail track to the airport terminal. Currently, TriMet‘s MAX Red Line moves to and from the main terminal via a single spur line that will be replaced. The addition of a second track will ease MAX scheduling throughout the system.

Various phases of this project will roll out in stages. The new rental car storage garage is already up and running, while the new exit plaza should open in November. Then the temporary road will be constructed to clear space for construction of the P3 garage. But in the meantime, ironworkers are already building the rebar cages for the concrete beams that will tie the P2 and P3 structures together.

The complicated dance of scheduling and logistics should produce a finished parking garage by mid-2021, Simonds said.

“It’s super complex, and we’re moving everything around,” she said. “It’s crowded, and we’re making these small, micro-adjustments to make it better. But a big fix is still a couple of years off.”

A new ramp will lead from an existing parking garage to the airport exit, while a new parking garage will be constructed next to the existing structure. The two will be connected via a complicated series of new concrete supports. (Josh Kulla/91Ƶ)
A new ramp will lead from an existing parking garage to the airport exit, while a new parking garage will be constructed next to the existing structure. The two will be connected via a complicated series of new concrete supports. (Josh Kulla/91Ƶ)
Journeyman cement mason Tony Webb of Local 555 and JE Dunn Construction performs finish work on a slab at a new exit plaza. (Josh Kulla/91Ƶ)
Journeyman cement mason Tony Webb of Local 555 and JE Dunn Construction performs finish work on a slab at a new exit plaza. (Josh Kulla/91Ƶ)
Aaron Ramirez, and Jovany Reyes, both apprentice cement masons with Local 555 and JE Dunn Construction, perform finish work on a fresh slab in the new airport exit plaza. (Josh Kulla/91Ƶ)
Aaron Ramirez, and Jovany Reyes, both apprentice cement masons with Local 555 and JE Dunn Construction, perform finish work on a fresh slab in the new airport exit plaza. (Josh Kulla/91Ƶ)
A new, more efficient exit plaza will speed the parking payment process. (Josh Kulla/91Ƶ)
A new, more efficient exit plaza will speed the parking payment process. (Josh Kulla/91Ƶ)
A new exit plaza is part of an overhaul of the airport's parking and car rental facilities. (Josh Kulla/91Ƶ)
A new exit plaza is part of an overhaul of the airport’s parking and car rental facilities. (Josh Kulla/91Ƶ)
A new section of exit ramp is being installed in the circular helix that leads out of the structure. (Josh Kulla/91Ƶ)
A new section of exit ramp is being installed in the circular helix that leads out of the structure. (Josh Kulla/91Ƶ)
Journeyman piledriver Mike Smith, a member of Local 196 and an employee of DeWitt Construction, uses a circle burner to trim the end of a circular pile. (Josh Kulla/91Ƶ)
Journeyman piledriver Mike Smith, a member of Local 196 and an employee of DeWitt Construction, uses a circle burner to trim the end of a circular pile. (Josh Kulla/91Ƶ)
A temporary ramp is being built from the existing parking structure exit to accomodate construction of the new parking garage. (Josh Kulla/91Ƶ)
A temporary ramp is being built from the existing parking structure exit to accomodate construction of the new parking garage. (Josh Kulla/91Ƶ)

The post Complex transportation improvements advancing at PDX appeared first on Daily Journal of Commerce.

]]>
Photos: Digging downtown for new office development /news/2018/05/10/photos-digging-downtown-for-a-new-office-development/ Thu, 10 May 2018 20:41:42 +0000 /?p=175314 Excavation is under way at 250 Taylor, a future 10-story office building spanning a half block in downtown Portland.

The post Photos: Digging downtown for new office development appeared first on Daily Journal of Commerce.

]]>

Excavation and foundation work is under way on , a 10-story office building spanning a half block on Southwest Taylor Street between Second and Third avenues. Co. is the general contractor for the project, which was designed by for .

Work at the site began last summer with demolition of a single-story commercial building and the six-story Ancient Order of United Workmen Temple building. Demolition work was completed in early November 2017, and Turner Construction crews returned to the site in March. Currently, crews are busy installing soldier pile and tie-backs, and removing dirt from the site to accommodate a two-level parking garage. The project should be fully excavated within two weeks.

Pours of the foundation, a mat footing three to six feet thick consisting of about 5,000 cubic yards of concrete, will be completed over the course of three Saturdays next month. A luffing crane will be installed in June as well. The parking garage and electrical vault will be poured over the course of the summer, and the structure will be back at street grade around September. All ten stories above grade will consist of post-tensioned concrete self-performed by Turner Construction. The project is slated for completion by fall 2019.

Because the site’s southwest portion abuts the 124-year-old Auditorium Building, extra care has been taken in excavating and shoring along that portion of the property. Excavation that would normally be done in five-foot lifts was instead done in three-foot lifts, and crews were limited to cutting only what could be lagged and backfilled before end of day.

Construction crews also had to take extra precaution to not disturb an 18-inch cast-iron water line that was built in the early 1900s and runs through the site. Temporary shoring was built to retain the dirt around the pipe and ensure that it didn’t move, and the project team worked closely with the city during permitting to ensure that tie-backs are all set at proper depth and angle in order to avoid the pipe.

The project team also includes KPFF Consulting Engineers (structural and civil engineering), Glumac (mechanical, electrical and plumbing engineering), GeoDesign Inc. (geotechnical engineering) and Lango Hansen Landscape Architects.

The office building is part of a nearly full-block development that will also include a 20-story hotel, also designed by Ankrom Moisan Architects and to be built by Turner Construction. That project is in the permitting phase.

DeWitt Construction employees Tyler Elliott, left, an apprentice pile driver with Local 196, and Nick Underwood, an apprentice laborer with Local 737, lift a casing and drill bit onto a drill rig while installing tiebacks.
DeWitt Construction employees Tyler Elliott, left, an apprentice pile driver with Local 196, and Nick Underwood, an apprentice laborer with Local 737, lift a casing and drill bit onto a drill rig while installing tiebacks.

0511_3rd_taylor_office_sa_02_web

Crews with DeWitt Construction chip out lean mix from around pile beams.
Crews with DeWitt Construction chip out lean mix from around pile beams.
DeWitt Construction employee Geoff Banford, a piledriver with Local 196, operates a drilling rig.
DeWitt Construction employee Geoff Banford, a piledriver with Local 196, operates a drilling rig.
Charles Pacheco, a journeyman operating engineer with Local 701 and employee of DeWitt Construction, sets up a dial indicator before load testing a tieback.
Charles Pacheco, a journeyman operating engineer with Local 701 and employee of DeWitt Construction, sets up a dial indicator before load testing a tieback.
Nick Underwood refuels an excavator.
Nick Underwood refuels an excavator.
The site is being excavated down to varying levels between approxminately 25 and 35 feet below grade.
The site is being excavated down to varying levels between approxminately 25 and 35 feet below grade.
Apprentice laborer Michael Takayoshi makes a birdsmouth cut in the lagging.
Apprentice laborer Michael Takayoshi makes a birdsmouth cut in the lagging.
Pile drivering crews with DeWitt Construction install tiebacks.
Pile drivering crews with DeWitt Construction install tiebacks.
Crews with DeWitt Construction install lagging.
Crews with DeWitt Construction install lagging.
Charles Pacheco prepares to tention tieback cables.
Charles Pacheco prepares to tention tieback cables.

0511_3rd_taylor_office_sa_12_web 0511_3rd_taylor_office_sa_13_web 0511_3rd_taylor_office_sa_14_web

Jessica Pence, a field technician with GeoDesign, Inc., records design loads of tiebacks.
Jessica Pence, a field technician with GeoDesign, Inc., records design loads of tiebacks.

0511_3rd_taylor_office_sa_16_web

The development will eventually encompass about 7/8ths of the block, with the four-story Auditorium Building, center, being the only existing structure remaining.
The development will eventually encompass about 7/8ths of the block, with the four-story Auditorium Building, center, being the only existing structure remaining.

The post Photos: Digging downtown for new office development appeared first on Daily Journal of Commerce.

]]>