Newest Portland-area Cinetopia copes with construction delay

By: Lindsey O'Brien//September 19, 2011//

Newest Portland-area Cinetopia copes with construction delay

Lindsey O'Brien//September 19, 2011//

Listen to this article

A major renovation of the Westfield Mall in , Wash., is still on schedule for completion in November, but its opening will no longer coincide with the grand opening of the adjoining Cinetopia movie theater.

The opening date of the two-story movie theater has been set back, potentially until February, because of delays in procuring some finishes for the theater, according to Ben Warren, project manager for .

Crews this week are pouring concrete and continuing to work on the facility’s electric, HVAC and plumbing systems, Warren said.

Hillsboro-based construction management and general contracting company Robinson Construction built the first two Cinetopia theaters in Vancouver and Beaverton, and has been working on the Westfield Mall location since January.

Cinetopia advertises that its newest location will include four extra-large screens, ranging between 65 to 80 feet.