PPS releases tentative schedule for bond projects

By: Reed Jackson//February 8, 2013//

PPS releases tentative schedule for bond projects

Reed Jackson//February 8, 2013//

Listen to this article

An eight-year timeline is starting to take form for Portland Public Schools to tackle construction with $482 million of bond money approved by voters in November.

This spring, the design process for a renovation of Roosevelt High School will begin with input from students, teachers and members of the North Portland community, according to a schedule released by the district’s operations staff.

This summer, PPS will begin replacing roofs and making seismic safety upgrades to Wilson High School, Alameda School, Bridlemile School, Laurelhurst School and Lewis School.

Also, at some point this year, planning will begin for the renovation of Faubion School, according to the schedule.

In 2015, the design process will begin for a renovation of Grant High School. And over the next eight summers, PPS will complete roofing, seismic and accessibility improvements on 63 schools.