Southwest Washington is聽abuzz with school construction.
Vancouver Public Schools, for instance, has under way multiple projects being for with money from a $458 million bond measure passed by voters in 2017.
On the Washington State University-Vancouver campus, crews are building new space for iTech Preparatory 鈥 a STEM (science, technology, engineering and math)-focused magnet school that serves students throughout the district. The school, which opened in 2012, has students in grades 6 through 12; middle school pupils currently attend classes in district administration offices while high school students occupy a leased building on the WSU campus.
鈥淲e’ve never had a facility where we could house all the grades at one location,鈥 said Todd Horenstein, an assistant superintendent and director of facility support services for Vancouver Public Schools.
The new building will have approximately 80,000 square feet of space over three stories and be able to serve up to 700 students. LSW Architects of Vancouver designed the facility, which is being built by Hillsboro general contractor Robinson Construction.

The project’s budget is around $30 million, Horenstein said. The building is being constructed to Washington Sustainable Schools Protocol, an energy efficiency process with standards roughly akin to Leadership in Energy and Environmental Design silver, he added.
Currently, site work is under way at one end of the iTech Preparatory site. Meanwhile, ironworkers and carpenters are building formwork and installing rebar in preparation for concrete slab foundation and footer pours.
On Northeast 28th Street in Vancouver, ground was broken this past summer on a replacement for Peter S. Ogden Elementary School. LSW Architects and Robinson Construction are handling this project as well.
The two-story building will be wood-framed over slab-on-grade foundations. It will be able to accommodate as many as about 500 students.
Foundation work already is complete. Currently, first-floor walls, both on the interior and exterior, are being built and placed by crews from DSL Framing.
Meanwhile, on MacArthur Boulevard, two schools are being built anew. Marshall Elementary School and McLoughlin Middle School will be constructed as a single two-story structure on open land between existing facilities.

The two schools will be physically connected by a shared kitchen and mechanical space, as well as a media center able to be partitioned. However, each school will function separately, Horenstein said.
LSW Architects designed this project too, but Skanska USA Building is the general contractor for this project. Currently, crews from Tapani Underground, Skanska and Prairie Electric are carrying out site work, underground utility installation and form work for upcoming foundation concrete pours.
Instead of standard steel or wood framing, however, cross-laminated timber structural elements will be used atop a concrete foundation. This will be one of the first educational buildings in the Portland-metro area to feature such construction.
Evergreen Public Schools, another school district in Vancouver, also has projects on tap. Voters in February approved a $695 million bond measure. Numerous construction projects totaling more than $800 million will be completed by 2024, according to the district’s website.