Josh Kulla//January 25, 2019//
General contractor Bremik Construction is seeking bids from subcontractors for a number of scopes of work related to the Hollydale Elementary School classroom addition project in Gresham.
The project includes an addition containing six classrooms as well as interior and exterior renovations and associated site work. For the current phase of work, roofing-related trades will not be included.
Scopes included are: surveying; selective structure demolition; erosion and sediment control; cast-in-place concrete, supply and installation of reinforcing steel; polished concrete; brick veneer; structural and miscellaneous steel; aluminum ladders; rough carpentry; casework, countertops and paneling; vapor retarder; insulation; weather barrier; unit skylights, metal-framed skylights; caulking; expansion control; doors, frames and hardware; storefront and glazing assemblies; access doors; metal stud framing; temporary heating; ceramic tile; resinous flooring; resilient base and carpeting; painting and sealants; marker boards and tack boards; interior signage; compartments and cubicles; toilet accessories; fire extinguishers and cabinets; bicycle shelters; kitchen equipment and supply; roller window shades; fire sprinklers; plumbing; HVAC; electrical and low voltage; site demolition, earth work and utilities; asphalt paving; site striping; chain-link fences and gates; site concrete, curbs and gutters; landscape and irrigation; progressive general construction clean up and site services.
A pre-bid conference is scheduled for 3:30 p.m. on Feb. 1 at the project site, at 505 S.W. Birdsdale Drive in Gresham.
BBL Architects designed the project, which is being paid for with money from a $291 million Gresham-Barlow School District bond approved by voters in 2016.
Construction is tentatively set to begin April 22, and be substantially completed by Dec. 13.