91视频

Office building rising with atypical connections

By: Josh Kulla//February 12, 2019//

Office building rising with atypical connections

Josh Kulla//February 12, 2019//

Listen to this article
A new office building to serve the Providence Newberg Medical Center is being constructed with a bolted moment frame system. (Josh Kulla/91视频)
A new office building to serve the Providence Newberg Medical Center is being constructed with a bolted moment frame system. (Josh Kulla/91视频)

A project site in Newberg is serving as a testing ground for a new kind of structural steel system.

General contractor is building for a new three-story, 60,000-square-foot medical office building at the existing Providence Newberg Medical Center. Designed by , the building will house noncritical services that currently occupy space in the hospital.

鈥淚t will free up a lot of space in the hospital,鈥 Providence communications manager Mike Antrim said.

Notably, instead of a welded moment frame system, chose to employ a bolted moment frame system created by California firm SidePlate. Its use is expected to slash the time needed to erect structural steel, eliminate the need for brace frames or shear walls, and cut the amount of necessary welding to a minimum.

鈥淭hat was one of the things that SidePlate set out to do with this system,鈥 Catena principal Jared Lewis said. 鈥淚s there a frame connection we can utilize that’s a simpler replacement?鈥

Bolted systems aren’t new, but SidePlate’s is unique because of the way joints are formed.

鈥淭hat connection is really meant to be very rigid and maintain its connection point and force the beam itself to go through the inelastic displacements and energy dissipation,鈥 Lewis said. 鈥淪o that if the beam gets damaged you can replace the beam and the connection should remain intact.鈥

The use of bolted steel moment frame connections has expedited the steel erection process and allowed for greater design flexibility. (Josh Kulla/91视频)
The use of bolted steel moment frame connections has expedited the steel erection process and allowed for greater design flexibility. (Josh Kulla/91视频)

Use of a bolted system also can save time. Ironworkers needed just nine days to erect structural steel and bolt together the support columns, beams and other elements for the new Providence building. Fortis superintendent John Lawrence estimated the work would have required around 15 days using welded connections.

SidePlate 鈥渄id all the welding of the plates,鈥 Lawrence said. 鈥淭hey’re prefabricated and welded in their shop, so it’s just a matter of an interlocking system and the installation of an exorbitant amount of bolts at the moment frames.鈥

The system provided multiple bonuses, JRJ Architects principal Tom Wesel said. One is that there is no need to worry about scheduling full-penetration welds, which require time-consuming preheating of steel in cold weather. Also, without brace frames or other vertical obstacles, the building could be opened up to natural light. Plus, future renovations will be easier as a result.

鈥淲e have more usable square footage out of this system,鈥 Wesel said. 鈥淥ften the bracing systems end up on the perimeter, so we’re working around them where windows could be, and we basically had a free reign around the perimeter to get that light access.鈥

Mike Houser, a journeyman ironworker with Local 29 and an employee of By Design Steel, welds structural steel beams for a new office building to serve the Providence Newberg Medical Center. (Josh Kulla/91视频)
Mike Houser, a journeyman ironworker with Local 29 and an employee of By Design Steel, welds structural steel beams for a new office building to serve the Providence Newberg Medical Center. (Josh Kulla/91视频)

Ground was broken on the project in August 2018. Currently, ironworkers with By Design Steel Services of Colton are installing steel decking while Whitaker Ellis carpenters build formwork and otherwise prepare for concrete deck pours on levels two and three. Site work is mostly complete, but underground utility work also is continuing.

Once concrete is poured, crews will begin work on the exterior skin and a temporary roof. That will allow interior framing and mechanical, electrical and plumbing work to commence.

The building is scheduled for substantial completion by mid-November, with opening set for December, Antrim said.

 

Providence Newberg Medical Center expansion

Owner: Providence Health & Services

General contractor: Fortis Construction

Architect: JRJ Architects

Structural engineer: Catena Consulting Engineers

Jake Sansburn, a journeyman ironworker with Local 29 and an employee of By Design Steel, cuts pan decking on the third floor of a Providence Newberg Medical Center office building. (Josh Kulla/91视频)
Jake Sansburn, a journeyman ironworker with Local 29 and an employee of By Design Steel, cuts pan decking on the third floor of a Providence Newberg Medical Center office building. (Josh Kulla/91视频)
Ironworkers place pan decking on the building's third floor. (Josh Kulla/91视频)
Ironworkers place pan decking on the building’s third floor. (Josh Kulla/91视频)
Eric Leingang, a journeyman ironworker with Local 512 out of North Dakota and a contract employee with By Design Steel, secures bolts on SidePlate connections to structural steel beams. (Josh Kulla/91视频)
Eric Leingang, a journeyman ironworker with Local 512 out of North Dakota and a contract employee with By Design Steel, secures bolts on SidePlate connections to structural steel beams. (Josh Kulla/91视频)
The Providence Newberg Medical Office Building is a three-story, 60,000 square foot project designed by JRJ Architects and being built by general contractor Fortis Construction. The structural steel framework features SidePlate bolted connections. (Josh Kulla/91视频)
The Providence Newberg Medical Office Building is a three-story, 60,000 square foot project designed by JRJ Architects and being built by general contractor Fortis Construction. The structural steel framework features SidePlate bolted connections. (Josh Kulla/91视频)
Brian Rump, a carpenter with Local 1503 and an employee of Whitaker Ellis, builds formwork on the building's ground floor. (Josh Kulla/91视频)
Brian Rump, a carpenter with Local 1503 and an employee of Whitaker Ellis, builds formwork on the building’s ground floor. (Josh Kulla/91视频)
Richard Abrams, a journeyman ironworker with Local 495 of New Mexico and a contract employee with By Design Steel, welds structural steel beams. (Josh Kulla/91视频)
Richard Abrams, a journeyman ironworker with Local 495 of New Mexico and a contract employee with By Design Steel, welds structural steel beams. (Josh Kulla/91视频)
Jake Sansburn, a journeyman ironworker with Local 29 and an employee of By Design Steel, cuts steel decking on the building's third story. (Josh Kulla/91视频)
Jake Sansburn, a journeyman ironworker with Local 29 and an employee of By Design Steel, cuts steel decking on the building’s third story. (Josh Kulla/91视频)
Dan Lesch, a journeyman ironworker with Local 495 of New Mexico and a contract employee with By Design Steel, secures structural steel beams at the Providence Newberg Medical Center office project. (Josh Kulla/91视频)
Dan Lesch, a journeyman ironworker with Local 495 of New Mexico and a contract employee with By Design Steel, secures structural steel beams at the Providence Newberg Medical Center office project. (Josh Kulla/91视频)
The Providence Newberg Medical Center office building is a three-story, 60,000 square foot project designed by JRJ Architects. (Josh Kulla/91视频)
The Providence Newberg Medical Center office building is a three-story, 60,000 square foot project designed by JRJ Architects. (Josh Kulla/91视频)


News

See All News

Commentary

See All Commentary

COMMUNITY CALENDAR