Offices, classrooms, a dental clinic and more

By: Josh Kulla//October 3, 2019//

Offices, classrooms, a dental clinic and more

Josh Kulla//October 3, 2019//

Listen to this article
Journeyman ironworker Trevor O'Connor, a member of Local 29 and an employee of R2M2 Rebar & Stressing, builds formwork at the Fourth and Montgomery project in downtown Portland. (Josh Kulla/91视频)
Journeyman ironworker Trevor O’Connor, a member of Local 29 and an employee of R2M2 Rebar & Stressing, builds formwork at the project in downtown Portland. (Josh Kulla/91视频)

A former surface parking lot on the Portland State University campus is quickly becoming a seven-story, 175,000-square-foot mixed-use building.

The 4th and Montgomery Building is rising on three-quarters of a block bounded by Southwest Montgomery and Harrison streets, and Fourth and Fifth avenues. designed the approximately $104 million project, which is being built by construction manager/general contractor . The building will be occupied by ‘s Graduate School of Education, the joint Oregon Health & Science University-PSU School of Public Health, Portland Community College dental programs, and Portland’s Bureau of Planning and Sustainability.

Crews broke ground in December 2018, and substantial completion is expected by November 2020, according to PSU. The building will have ground-level commercial space, classrooms, a dental clinic, and both academic and nonacademic offices.

SRG Partnership’s design matches the curved streetcar path that clips the block’s northeast corner. All sidewalks and access to the building will be generous and open.

To accommodate a significant grade change, designers used landscape walks, stairs, walls, benches and planters to define a central courtyard space while offering multiple access points.

Inside, the ground floor will feature retail spaces and a lobby. A central staircase will bring people to classrooms and offices for tenants on the second floor and above.

The design’s aim is for a Leadership in Energy and Environmental Design gold rating. Sustainable features include a green roof with 62 percent coverage, a rooftop solar array, a large stormwater planter and a dedicated outside air system with radiant heating and cooling.

In addition, the building will have a high-efficiency envelope and exterior metal-panel cladding with punched window openings and bird-safe exterior glazing.

Currently, construction crews are gaining speed after a slow start that included additional excavation after the discovery of waste underneath the parking lot.

The Fourth and Montgomery building will contain 175,000 square feet of office and classroom space. (Josh Kulla/91视频)
The 4th and Montgomery building will contain 175,000 square feet of office and classroom space. (Josh Kulla/91视频)

鈥淲e had an old building that they had torn down, and they buried quite a few things that we had to dig through and dispose of in the right manner,鈥 Andersen Construction superintendent Paul Rovianek said. 鈥淚t was nothing really crazy 鈥 just some roofing material, some bricks and different things like that. It’s surprising they buried all of that, but we sent it off and put it in the right spot.鈥

The new building will feature seven stories of post-tensioned concrete decks and reinforced concrete columns constructed around double building cores housing elevators and stairwells. The first two levels will feature oversized spaces, with ceilings ranging from 20 to 25 feet on the ground level and 16 feet on the second floor. Ceilings on levels three through seven will be 12 feet.

Andersen’s subsidiary, Andersen Structures Inc., is performing all of the project’s concrete work, and the firm’s carpenters are constructing formwork, installing shoring systems and stripping old formwork as the project moves forward.

鈥淲e just have the typical guys right now for this stage of the project,鈥 Rovianek said, noting that concrete was being poured for the third level. 鈥淲e have concrete and (mechanical, electrical and plumbing workers); the electricians and plumbers are here full time and the fire sprinkler guys are just in and out putting in sleeves and blue bangers.鈥

Excavation work is also wrapping up with installation of a communications vault, while ironworkers from Local 29 and R2M2 Rebar and Stressing are laying down rebar for the concrete decks.

鈥淚t’s a lot of the usual suspects,鈥 Rovianek said with a laugh.

Justus Anthony, an apprentice carpenter with Local 1503 and Andersen Structures Inc., places a piece of plywood decking around the base of a concrete column. (Josh Kulla/91视频)
Justus Anthony, an apprentice carpenter with Local 1503 and Andersen Structures Inc., places a piece of plywood decking around the base of a concrete column. (Josh Kulla/91视频)
Crews with Andersen Structures, Inc. lay down decking for the third level of the Fourth and Montgomery project on the PSU campus downtown. (Josh Kulla/91视频)
Crews with Andersen Structures, Inc. lay down decking for the third level of the 4th and Montgomery project on the PSU campus downtown. (Josh Kulla/91视频)
Andersen Structures Inc. carpenter William Sweatt constructs formwork for the building core on the Fourth and Montgomery project on the PSU campus. (Josh Kulla/91视频)
Andersen Structures Inc. carpenter William Sweatt constructs formwork for the building core on the 4th and Montgomery project on the PSU campus. (Josh Kulla/91视频)
Carpenters construct formwork and pour concrete for building core shear walls at the Fourth and Montgomery project site. (Josh Kulla/91视频)
Carpenters construct formwork and pour concrete for building core shear walls. (Josh Kulla/91视频)
Peter Albright, an apprentice carpetner with Local 1503 and Andersen Structures, Inc., constructs a steel wall form for the building core. (Josh Kulla/91视频)
Peter Albright, an apprentice carpetner with Local 1503 and Andersen Structures, Inc., constructs a steel wall form for the building core. (Josh Kulla/91视频)
The 4th and Montgomery project is being built with MAX and Streetcar lines running on three sides of the building. (Josh Kulla/91视频)
The 4th and Montgomery project is being built with MAX and Streetcar lines running on three sides of the building. (Josh Kulla/91视频)
Andersen Structures Inc. carpenters prepare a concrete pump for use on the third deck of the 4th and Montgomery project site. (Josh Kulla/91视频)
Andersen Structures Inc. carpenters prepare a concrete pump for use on the third deck of the 4th and Montgomery project site. (Josh Kulla/91视频)
William Sweatt, a journeyman carpenter with Local 1503 and Andersen Structures Inc., hands a colleague a piece of shoring. (Josh Kulla/91视频)
William Sweatt, a journeyman carpenter with Local 1503 and Andersen Structures Inc., hands a colleague a piece of shoring. (Josh Kulla/91视频)
The ground floor of the Fourth and Montgomery building will feature 21-foot ceilings. (Josh Kulla/91视频)
The building’s ground floor will feature 21-foot ceilings. (Josh Kulla/91视频)
The $97 million Fourth and Montgomery Building on the Portland State University campus will serve three university programs and the city of Portland's Bureau of Planning and Sustainability. (SRG Partnership)
The $104 million 4th and Montgomery Building on the Portland State University campus will serve three university programs and the city of Portland’s Bureau of Planning and Sustainability. (SRG Partnership)