Josh Kulla//November 25, 2019//

Evergreen Public Schools in Vancouver, Washington, is putting to work $695 million of bond money approved by voters in February 2018. Dozens of school buildings are being renovated or replaced; one of the first is Sifton Elementary School, in Northeast Vancouver.
General contractor Pence Construction is tackling the $38 million project to replace an existing school built in 1958. The new, two-story, 62,000-square-foot Sifton Elementary will be the first of multiple new schools produced from a prototype design by LSW Architects.
Construction crews broke ground in April. These days, large glulam structural members are being erected for the gymnasium and auditorium, and exterior and interior walls are being framed. Soon, other tradespeople will arrive on site to begin rough-in work, but right now framers are working to get the building roofed and dried in before weather becomes harsher.
Wood framing is being used for the new school.
鈥淚t was a judgment call that we made early on in the design process,鈥 R&C Management Group senior project manager Dan Bodell said. 鈥淭wo years ago, construction costs were going nuts. Now, it’s not the same month-to-month creep that was going on; it’s a little more like a three-percent-a-year kind of cost creep. But we had to think: What can we do in the bones of the building to save money? And that’s why we went to wood framing.鈥
Crews with Salem-based DSL Builders are framing interior walls away from the main building and using a crane to fly them into place.
鈥淓verybody will do some level of pre-fabbing,鈥 Bodell said. 鈥淏ut here it’s all being done on site. At PS 22 they’re framing them in place and standing them up 鈥 not building them 100 feet away and swinging them into place. It’s just about different styles.鈥
鈥淧S 22鈥 is a new school, not yet named, being built by general contractor Triplett Wellman Contractors on Northeast 162nd Avenue. Meanwhile, a replacement for the existing Image Elementary School is being built by Emerick Construction on Northeast 131st Avenue. All three project teams are expected to finish their work by summer 2020, in time for the facilities to open for the 2020-21 school year.