91视频

School builders working through site challenges

By: Josh Kulla//November 26, 2019//

School builders working through site challenges

Josh Kulla//November 26, 2019//

Listen to this article
Carpenters with Northwest Framing Systems install roof joists at Image Elementary School in Vancouver, Washington. (Josh Kulla/91视频)
Carpenters with Northwest Framing Systems install roof joists at Image Elementary School in Vancouver, Washington. (Josh Kulla/91视频)

Multiple school construction projects are under way in Vancouver, Washington, for . The district last year gained voters’ approval for a $695 million bond, and money is being put to work.

One of the projects under way is a replacement for Image Elementary School. General contractor is building the school on a parcel of former farmland near the intersection of Northeast 131st Avenue and 52nd Street.

鈥淚t’s a really significantly different site,鈥 Evergreen Public Schools spokeswoman Gail Spolar said. 鈥淚t doesn’t have a school on it, but (crews) have had some interesting things to take care of (on the site) before they started constructing the new school.鈥

‘ design for the two-story, approximately 62,000-square-foot facility calls for use of mass-timber structural elements, including glulam beams and columns. Laminated veneer lumber will be used extensively in the framing.

An open interior design will allow for tall ceilings, large learning stairs and a media center. The gymnasium and family resource center will be isolated from the rest of the school to allow for public use.

Excavation and site work began in June.

鈥淚t’s a little challenging because we have the wetland that’s all part of it,鈥 Emerick Construction project manager Alicia LaManna said. 鈥淪o, the soil makeup underneath the site is quite interesting in how it’s been filled in over the decades of being a farmland. We had quite a lot of excavation that we had to do before we could even start the foundations.鈥

Journeyman carpenters Aaron Dobroth, left, and Mitchell Cummings, both employees of Northwest Framing Systems, install exterior walls on the classroom wing of Image Elementary School. (Josh Kulla//91视频)
Journeyman carpenters Aaron Dobroth, left, and Mitchell Cummings, both employees of Northwest Framing Systems, install exterior walls on the classroom wing of Image Elementary School. (Josh Kulla//91视频)

In addition to excavation, however, plenty of fill was required to level off the site before construction could take place. Fortunately, there was a ready supply available from excavation taking place for a new elementary school (not yet named) being built on Northeast 162nd Avenue between 39th and 43rd streets.

鈥淭he export from 22 鈥 it was quality material,鈥 said Dan Bodell, a project manager with . 鈥淲e also ended up taking dirt from underneath the building here and we were able to use it elsewhere on this site, and we went ahead and rearranged all of that. And then we brought this other material in to bring the whole site up.鈥

As a result, much of the site has been raised. Also, extensive groundwater required construction of a massive stormwater retention chamber on the east side of the site. Multiple temporary wells were used to pump out groundwater during excavation for the slab-on-grade foundation.

鈥淓verything has been brought up four or five feet so that we weren’t down in the wet,鈥 Bodell said. 鈥淎nd that goes back to all the engineering that goes into handling the rainwater 鈥 making sure we’re not flooding (adjacent residences) when the rains come because all of a sudden you have a hard surface here.鈥

After the new Image Elementary School opens (fall 2020 is the target date), the existing one 鈥 near the intersection of Northeast 122nd Avenue and 44th Street 鈥 will serve as a temporary facility on a rotating basis for other schools being replaced by new ones on their current properties.

Emerick Construction is self-performing the concrete work at Image Elementary School. (Josh Kulla/91视频)
Emerick Construction is self-performing the concrete work at Image Elementary School. (Josh Kulla/91视频)
Journeyman carpenter and crew foreman Michael Nottingham of Northwest Framing Systems cuts studs. (Josh Kulla/91视频)
Journeyman carpenter and crew foreman Michael Nottingham of Northwest Framing Systems cuts studs. (Josh Kulla/91视频)
Carpenters with Northwest Framing Systems install roof joists. (Josh Kulla/91视频)
Carpenters with Northwest Framing Systems install roof joists. (Josh Kulla/91视频)
Erik Halstead, a carpenter with Emerick Construction and member of Local 1503, constructs formwork at Image Elementary School. (Josh Kulla/91视频)
Erik Halstead, a carpenter with Emerick Construction and member of Local 1503, constructs formwork at Image Elementary School. (Josh Kulla/91视频)
Michael Nottingham of Northwest Framing Systems cuts studs. (Josh Kulla/91视频)
Michael Nottingham of Northwest Framing Systems cuts studs. (Josh Kulla/91视频)
The school's design is from a prototype by LSW Architects that is being used by Evergreen School District on three new elementary schools. (Josh Kulla/91视频)
The school’s design is from a prototype by LSW Architects that is being used by Evergreen School District on three new elementary schools. (Josh Kulla/91视频)
Apprentice carpenter Issac Guerrero, a member of Local 1503 and an employee of Emerick Construction, constructs foundation formwork. (Josh Kulla//91视频)
Apprentice carpenter Issac Guerrero, a member of Local 1503 and an employee of Emerick Construction, constructs foundation formwork. (Josh Kulla//91视频)
Mitchell Cummings frames an exterior wall. (Josh Kulla/91视频)
Mitchell Cummings frames an exterior wall. (Josh Kulla/91视频)
Journeman carpenter Aaron Dobroth of Northwest Framing Systems sheets an exterior wall. (Josh Kulla/91视频)
Journeman carpenter Aaron Dobroth of Northwest Framing Systems sheets an exterior wall. (Josh Kulla/91视频)
Chuck Johnson, carpentry foreman for Emerick Construction and a member of Local 1503, carries a piece of rebar across foundation formwork at Image Elementary. (Josh Kulla/91视频)
Chuck Johnson, carpentry foreman for Emerick Construction and a member of Local 1503, carries a piece of rebar across foundation formwork at Image Elementary. (Josh Kulla/91视频)
Crews are now framing the interior of the classroom wing at Image Elementary. (Josh Kulla/91视频)
Crews are now framing the interior of the classroom wing at Image Elementary. (Josh Kulla/91视频)


News

See All News

Commentary

See All Commentary

COMMUNITY CALENDAR