Superblock construction keeping crews busy

By: Josh Kulla//January 21, 2020//

Superblock construction keeping crews busy

Josh Kulla//January 21, 2020//

Listen to this article
Johnny Gentry, a journeyman ironworker with Local 29 and an employee of R2M2 Rebar & Stressing, lays out rebar for the Saltwood South foundation slab. (Josh Kulla/91Ƶ)
Johnny Gentry, a journeyman ironworker with Local 29 and an employee of R2M2 Rebar & Stressing, lays out rebar for the foundation slab at South. (Josh Kulla/91Ƶ)

Construction of ‘s sizable mixed-use development for Prometheus Real Estate Group is moving along in Northwest Portland.

Saltwood, designed by , will be a pair of six-story buildings with ground-floor commercial space topped by five floors of apartments. The project will occupy space on master-planned property bounded by Northwest 20th and 21st avenues and Northwest Savier and Quimby streets.

General contractor is working on Saltwood North, where crews recently poured the first post-tensioned concrete deck slab in the below-grade parking area.

Meanwhile, at Saltwood South, general contractor has completed the first of three planned foundation slab pours – one accounting for 1,200 cubic yards of concrete in one day.

Ground was broken on Saltwood North in August 2019, and then on Saltwood South in October.

“We’re just the one level below grade,” R&H Construction project manager Mitch Smith said. “On the north, obviously they’re two down. We’re one down and then five over one – the same going up. Schedule-wise, it will be interesting because they started two months before us, but we’ve always planned that we’ll catch them coming up. So we’ll probably start framing at the same time.”

Both buildings will be U-shaped, with a central courtyard opening to the south. Saltwood South will have an overall floor area of roughly 228,000 square feet, with 42,000 additional square feet in the basement, which is slightly larger than the overall building footprint.

Saltwood South’s exterior will feature primarily brick masonry with metal panel accents and a hint of wood.

Crews with R&H Construction began work last fall on Saltwood South, one of a pair of mixed-use buildings in the Con-Way Master Plan area of Northwest Portland. (Josh Kulla//91Ƶ)
Crews with R&H Construction began work last fall on Saltwood South, one of a pair of mixed-use buildings in the Con-Way Master Plan area of Northwest Portland. (Josh Kulla//91Ƶ)

“From what I can tell, in general they are very similar buildings,” Smith said. “It’s kind of a prototype that the owners like, with a nice, open courtyard. The courtyard is something that seems to be important to them, and with it they want to bring a lot of character to the building.”

At Saltwood South, ironworkers with R2M2 Rebar & Stressing are laying down the rebar for the building’s foundation slab and the first set of support columns. Meanwhile, carpenters with Marion Construction Co. are preparing formwork as waterproofers with Sawtooth Caulking install vapor barrier on the lagging walls that will serve as a form for the foundation walls.

Also, Konell Construction is performing excavation, and Bear Electric and Tapani Plumbing are preparing in-slab conduit and plumbing assemblies.

A second large foundation slab pour of roughly 1,000 cubic yards is in the works, Smith said.

“The concrete plants right now can’t get us enough mud during the weekdays to pull off a big pour like that locally, just because there are so many projects going on,” he said. “And it’s only going to get worse. That’s why Bremik did their pours on Saturdays, which is what we have to do as well.”

It’s about how many yards you can get down per hour, he added.

“When you have the larger pours, just do the math,” Smith said. “On ours you have a 1,200-cubic-yard pour the first one, and if they’re only going to give you 80 yards per hour it’s going to take you 15 hours to physically put the mud down and not even finish it or any of that. So that’s what’s really pushed us to move to Saturday pours.”

The project team is aiming to finish Saltwood South by August 2021.

Apprentice ironworker Valeriy Silanov, a member of Local 29 and an employee of R2M2 Rebar and Stressing, cuts ties on a load of rebar. (Josh Kulla/91Ƶ)
Apprentice ironworker Valeriy Silanov, a member of Local 29 and an employee of R2M2 Rebar and Stressing, cuts ties on a load of rebar. (Josh Kulla/91Ƶ)
Ironworkers Valente Elizalde, left, and Valeriy Silanov, both members of Local 29 and employees of R2M2 Rebar & Stressing, lay rebar for the foundation slab. (Josh Kulla/91Ƶ)
Ironworkers Valente Elizalde, left, and Valeriy Silanov, both members of Local 29 and employees of R2M2 Rebar & Stressing, lay rebar for the foundation slab. (Josh Kulla/91Ƶ)
Journeyman carpenter and crew foreman Nick Brundridge, a member of Local 1503 and an employee of Marion Construction Company, clamps a column form into place. (Josh Kulla/91Ƶ()
Journeyman carpenter and crew foreman Nick Brundridge, a member of Local 1503 and an employee of Marion Construction Company, clamps a column form into place. (Josh Kulla/91Ƶ)
Makoa Bamba of Sawtooth Caulking nails vapor barrier to the lagging walls that will serve as a form for below-grade concrete walls. (Josh Kulla/91Ƶ)
Makoa Bamba of Sawtooth Caulking nails vapor barrier to the lagging walls that will serve as a form for below-grade concrete walls. (Josh Kulla/91Ƶ)
Apprentice ironworker Valeriy Silanov, right, and journeyman Elizalde Valente, both members of Local 29 and employees of R2M2 Rebar & Stressing, carry a load of rebar. (Josh Kulla/91Ƶ)
Apprentice ironworker Valeriy Silanov, right, and journeyman Elizalde Valente, both members of Local 29 and employees of R2M2 Rebar & Stressing, carry a load of rebar. (Josh Kulla/91Ƶ)
Shane Sporer, an installer with Sawtooth Caulking, trims a piece of vapor barrier. (Josh Kulla/91Ƶ)
Shane Sporer, an installer with Sawtooth Caulking, trims a piece of vapor barrier. (Josh Kulla/91Ƶ)
Valeriy Silanov guides a load of rebar. (Josh Kulla/91Ƶ)
Valeriy Silanov guides a load of rebar. (Josh Kulla/91Ƶ)
Johnny Gentry lays down rebar at the Saltwood South project. (Josh Kulla/91Ƶ)
Johnny Gentry lays down rebar at the Saltwood South project. (Josh Kulla/91Ƶ)
Nick Brundridge clamps a column form into place. (Josh Kulla/91Ƶ()
Nick Brundridge clamps a column form into place. (Josh Kulla/91Ƶ)
Journeyman carpenter Etzael Velez, a member of Local 1503 and an employee of Marion Construction Company, a rebar cage after lowering a form into place. (Josh Kulla/91Ƶ)
Journeyman carpenter Etzael Velez, a member of Local 1503 and an employee of Marion Construction Company, a rebar cage after lowering a form into place. (Josh Kulla/91Ƶ)
A carpenter with Local 1503 and Marion Construction Company constructs formwork for a building core. (Josh Kulla/91Ƶ)
A carpenter with Local 1503 and Marion Construction Company constructs formwork for a building core. (Josh Kulla/91Ƶ)
Valente Elizalde ties rebar for the foundation slab. (Josh Kulla/91Ƶ)
Valente Elizalde ties rebar for the foundation slab. (Josh Kulla/91Ƶ)
Nick Brundridge clamps a column form into place. (Josh Kulla/91Ƶ()
Nick Brundridge clamps a column form into place. (Josh Kulla/91Ƶ)
Jesus Gonzales, a journeyman carpenter with Local 1503 an employee of Marion Construction Company, trims a wall form. (Josh Kulla/91Ƶ)
Jesus Gonzales, a journeyman carpenter with Local 1503 an employee of Marion Construction Company, trims a wall form. (Josh Kulla/91Ƶ)