91视频

Williams Plaza gaining upgrades, a floor at a time

By: Josh Kulla//March 10, 2020//

Williams Plaza gaining upgrades, a floor at a time

Josh Kulla//March 10, 2020//

Listen to this article
Kurt Morris, an apprentice plumber with Peninsula Plumbing, performs a leak test on a newly installed bathtub at the Williams Plaza building in Northwest Portland. (Josh Kulla/91视频)
Kurt Morris, an apprentice plumber with Peninsula Plumbing, performs a leak test on a newly installed bathtub at the building in Northwest Portland. (Josh Kulla/91视频)

Years ago, Home Forward put into motion its 鈥85 Stories Initiative鈥 to improve much of its low-income housing stock. Several buildings in Portland have received attention, and now Williams Plaza, a nine-story building at 2041 N.W. Everett St., in the Nob Hill neighborhood, is finally getting some.

A tight budget has forced project designers and engineers to become creative, but they have been meeting the challenge.

鈥淭his project is design-build, which yields a lot of benefits from the start,鈥 said Matt Bokar, a senior associate at . 鈥淎t the start, a lot of that just goes into scoping. So it’s about getting a handle on the stuff we have to do and then the stuff we want to do and then the stuff we hope to be able to do.鈥

Permits for building alterations and mechanical alterations at Williams Plaza total slightly more than $7 million. Budget constraints exist for any affordable housing project, Bokar added, so Salazar Architect is working very closely with general contractor Construction to ensure as many upgrades as possible are completed.

鈥淔rom the start we are working to really organize the scope into those three buckets,鈥 he said. 鈥淭hen as the design process unfolds you try to make space in the budget and the schedule for the stuff you want to do.鈥

Much of the investment is going into renovating units’ bathrooms and kitchens. Williams Plaza has 101 apartments (a mix of studios and one-bedroom units) occupied by tenants who are age 55 or older, or have a disability.

鈥淭his one is really systems-heavy,鈥 said Leslie Cretan, a senior project manager. 鈥淚t’s a heavy plumbing job, and even though it started mainly as a bathroom remodel we had to pretty much gut the bathrooms to do the replacement of the plumbing.鈥

A renovation of the nine-story Williams Plaza building is expected to be finished this September. (Josh Kulla/91视频)
A renovation of the nine-story Williams Plaza building is expected to be finished this September. (Josh Kulla/91视频)

The building’s security systems, corridor lighting, mechanical systems and rooftop generator all are being upgraded or replaced. An old boiler is being replaced by individual water heaters, and the ground-floor community room, lobby, mail room and garbage room are being expanded and improved. And while the building’s electrical wiring will remain for now, dilapidated baseboard heaters are being replaced by more efficient wall heaters.

鈥淲ith this project the timing was just perfect,鈥 Cretan said. 鈥淲e were already having water leaks all over the place and shut-off valves that wouldn’t shut off.鈥

New shut-off valves were installed to allow better control of water flow.

鈥淣ow you’ll be able to shut it down at the unit and not affect anyone else’s water and go in and fix whatever you need to fix,鈥 said Brian Ames, the project superintendent for Walsh Construction.

Other work taking place includes: abatement of flooring and joint compound containing asbestos; installation of new rooftop exhaust fans and roofing as well as new exhaust fans in each bathroom unit; installation of new stove tops and splash guards; and more. A lot of these touches, including new luxury vinyl plank flooring, came via suggestions from residents.

鈥淐ommunity meetings were held during design, and we were blessed to have an active and engaged population,鈥 Bokar said. 鈥淲e held three meetings to walk residents through scoping and sequencing of the work.鈥

Tenants are remaining in the building while improvements take place. In this case, the work is being done one floor at a time, with residents being shifted to a 鈥渉otel鈥 floor (the sixth) on a temporary basis. The sixth floor will then be the final level to be renovated.

鈥淲e just moved everybody back from the sixth floor into the fifth floor,鈥 Ames said. 鈥淭hat took us two days. And then we go through and clean the hotel floor and make sure it’s ready for the next group.鈥

Work is proceeding from the top down, with floors 9, 8, 7 and 5 already completed. Crews currently are working on the fourth floor and the ground floor.

鈥淲e’ll go back at the end to the hotel unit, which just got new bathrooms, and we’ll do the remaining scope items there at the tail end,鈥 Ames said.

The project schedule calls for completion by September.

Isael Chiuhaque, left, a carpenter with Union Construction, sands drywall at the Williams Plaza affordable housing building in Northwest Portland. Also pictured, from left, are Sellwood Contracting owner Jose Luis and carpenters Harvey Platero and Jose Martinez. (Josh Kulla/91视频)
Isael Chiuhaque, left, a carpenter with Union Construction, sands drywall at the Williams Plaza affordable housing building in Northwest Portland. Isael Chiuhaque, left, a carpenter with Union Construction, sands drywall at Williams Plaza in Northwest Portland. Sellwood Contracting owner Jose Luis, second from left, and carpenters Harvey Platero, third from left, and Jose Martinez also work on cabinet installations.(Josh Kulla/91视频)
Paul Wilson, a journeyman sprinkler fitter with Local 669 and a crew foreman with Patriot Fire Protection, installs a fire sprinkler line at the doorway of a refurbished apartment. (Josh Kulla/91视频)
Paul Wilson, a journeyman sprinkler fitter with Local 669 and a crew foreman with Patriot Fire Protection, installs a fire sprinkler line at the doorway of a refurbished apartment. (Josh Kulla/91视频)
A renovated kitchen features updated appliances, fixtures and cabinetry. (Josh Kulla/91视频)
A renovated kitchen features updated appliances, fixtures and cabinetry. (Josh Kulla/91视频)
Journeyman carpenter Gary Hanson, a member of Local 1503 and an employee of RDF Builders, installs blocking to support towel holders, cabinetry and other items in a bathroom. (Josh Kulla/91视频)
Journeyman carpenter Gary Hanson, a member of Local 1503 and an employee of RDF Builders, installs blocking to support towel holders, cabinetry and other items in a bathroom. (Josh Kulla/91视频)
All bathrooms at Williams Plaza are being gutted and renovated with new shower and tub assemblies, toilets and sinks. Grab bars for accessibility are also being added. (Josh Kulla/91视频)
All bathrooms at Williams Plaza are being gutted and renovated with new shower and tub assemblies, toilets and sinks. Grab bars for accessibility are also being added. (Josh Kulla/91视频)
Isael Chiuhaque, a carpenter with Union Construction, sands sheetrock in the refurbished community room. (Josh Kulla/91视频)
Isael Chiuhaque, a carpenter with Union Construction, sands sheetrock in the refurbished community room. (Josh Kulla/91视频)
Journeyman electrician Aaron Agilera of Merit Electric wires a kitchen wall receptacle to the circuit breaker panel of an apartment undergoing renovation. (Josh Kulla/91视频)
Journeyman electrician Aaron Agilera of Merit Electric wires a kitchen wall receptacle to the circuit breaker panel of an apartment undergoing renovation. (Josh Kulla/91视频)


News

See All News

Commentary

See All Commentary

COMMUNITY CALENDAR