91视频

Ex-industrial building becoming creative office space

By: Josh Kulla//March 27, 2020//

Ex-industrial building becoming creative office space

Josh Kulla//March 27, 2020//

Listen to this article
A second floor is being added to the Premier Gear building, a former machine shop being converted to creative office space. (Josh Kulla/91视频)
A second floor is being added to the Premier Gear building, a former machine shop being converted to . (Josh Kulla/91视频)

A 97-year-old single-story warehouse slightly north of Portland’s has received several renovations over the years. The latest one might be the most extensive.

The Premier Gear & Machine Works building, on nearly a full block bounded by Northwest 17th and 18th avenues and Savier and Thurman streets, is being gutted and transformed into creative office space. is the developer. The project team includes , and .

鈥淥verall it’s an addition, square foot wise because we’re adding a second level,鈥 Lorentz Bruun Construction project engineer Mark Drahota said. 鈥淩ight now it’s about 40,000 square feet, and with the second level we’re going to add roughly 15-20,000 more square feet, so it will be roughly 60,000 square feet when it’s all said and done.鈥

The adaptive reuse project includes a substantial seismic upgrade. Steel, buckling-restrained brace frames and shear walls were installed to connect the roof to the rest of the building.

The outside of the building is not going to experience wholesale change. That’s reserved for the interior, where crews are adding a mezzanine level, new entrances, new windows for the south side of the building and a large covered outdoor terrace.

The new design incorporates the building’s original features and pays tribute to the legacy throughout the additional space, which is being constructed with heavy timber 鈥 mainly glulam beams and columns and Douglas fir car decking flooring on the mezzanine level.

Carpenter Brent Williams of Framing Force Inc. drills a slot for a connector bolt in a glulam beam. (Josh Kulla/91视频)
Carpenter Brent Williams of Framing Force Inc. drills a slot for a connector bolt in a glulam beam. (Josh Kulla/91视频)

An elevated sky-bridge will connect the north and south halves of the mezzanine level, while an outdoor patio for tenant use will be notched into the building on the south side.

Construction crews are continuing to encounter remnants of previous building expansions, Drahota said.

鈥淎s we’ve dug into the building we’ve found different issues, old-school stuff,鈥 he said. 鈥淭hat’s definitely been the biggest challenge.鈥

Different construction types were used for each project, leading to some unique discoveries last summer during the demolition and abatement phase.

鈥淭here was asbestos abatement and little bit of lead abatement, but not very much,鈥 Drahota said. 鈥淚t was mostly just warehouse space, but there was some existing office space that had some stuff we had to do. But it definitely had to be taken care of. It was a lot of work to remove all the existing beams and clear the space.鈥

The building’s south side featured newer concrete tilt panels, but the older north side was mostly board-formed with a heavy timber interior. The latter featured some hefty 14-inch-by-30-inch solid Douglas fir beams carved from old growth that is long since gone.

鈥淚t’s a menagerie of styles,鈥 Lorentz Bruun project superintendent Bruce Fabian said.

Approximately 150 window openings had to be cut into the existing concrete exterior walls as part of demolition, according to Fabian.

鈥淎t one we had four saws running at one time just to make schedule,鈥 he said.

The core-and-shell renovation of the nearly full-block building is scheduled for completion this summer. (Josh Kulla/91视频)
The core-and-shell renovation of the nearly full-block building is scheduled for completion this summer. (Josh Kulla/91视频)

Then there are vintage overhead gantry cranes, including at least three that formerly graced the warehouse. One will remain on its rails as a reminder of earlier times.

鈥淎 lot of the crane rails were supported by timbers, as well, and we actually left some of those existing crane rails up,鈥 Drahota said.

But now, carpenters with Framing Force of Molalla are installing the last of the car decking flooring and glulam beams, while mechanical, electrical and plumbing subcontractors prep for rough-in work. Crews with Nuwave Concrete of Forest Grove are also on site finishing the massive new floor slab.

Other members of the project team include: Humber Design Group, which performed civil engineering; MFIA Inc., which carried out MEP design and engineering; and Shapiro Didway Landscape Architecture.

Project completion is scheduled for June 2020, although the COVID-19 pandemic could lead to that date changing.

Cement mason Marcos Pi帽eda of Nuwave Concrete uses a bull float to perform finish work. (Josh Kulla/91视频)
Cement mason Marcos Pi帽eda of Nuwave Concrete uses a bull float to perform finish work. (Josh Kulla/91视频)
The core-and-shell renovation will create two floors of creative office space. (Josh Kulla/91视频)
The core-and-shell renovation will create two floors of creative office space. (Josh Kulla/91视频)
Alejo Colorado, a cement mason with Nuwave Concrete, uses a hand trowel to perform finish work. (Josh Kulla/91视频)
Alejo Colorado, a cement mason with Nuwave Concrete, uses a hand trowel to perform finish work. (Josh Kulla/91视频)
David Jackson installs car decking on the second level. (Josh Kulla/91视频)
David Jackson installs car decking on the second level. (Josh Kulla/91视频)
Cristian Madrigal, a cement mason with Nuwave Concrete, finishes a floor slab. (Josh Kulla/91视频)
Cristian Madrigal, a cement mason with Nuwave Concrete, finishes a floor slab. (Josh Kulla/91视频)
Cement masons with Nuwave Concrete finish a floor slab.
Cement masons with Nuwave Concrete finish a floor slab.
Daniel Medina runs the hose as Alberto Guadarama places concrete. (Josh Kulla/91视频)
Daniel Medina runs the hose as Alberto Guadarama places concrete. (Josh Kulla/91视频)
Heavy timber structural elements are being used to add a second level to the building. (Josh Kulla/91视频)
Heavy timber structural elements are being used to add a second level to the building. (Josh Kulla/91视频)
Michael Zuniga, a carpenter with Framing Force, installs car decking. (Josh Kulla/91视频)
Michael Zuniga, a carpenter with Framing Force, installs car decking. (Josh Kulla/91视频)
A new second story will add about 20,000 square feet of space to the building. (Josh Kulla/91视频)
A new second story will add about 20,000 square feet of space to the building. (Josh Kulla/91视频)


News

See All News

Commentary

See All Commentary

COMMUNITY CALENDAR