Alex Jensen//March 30, 2021//

| $750,000 Address: 12005 N. Burgard Road. Applicant: Ryan Pickrel of Faster Permits Owner: Northwest Pipe Co. Contractor: Tapio Construction Inc. The work includes installation of foundational and structural steel support for replacement equipment inside and adjacent to the existing building for mixed metal recovery system for recycled materials. The alterations also include concrete foundations and structural steel support for equipment, equipment maintenance access and electrical rooms. |
![]() |
|
UNDER INSPECTION
|
$19,106,515 Address: 401 N. Schmeer Road Applicant: Dale Poppe of Mackenzie is the applicant Owner: Not listed. Contractor: Guy Blanchard (Sierra Construction Company Inc.) Plans call for a new tilt-up distribution building with site and tenant improvements. |
| $6,737,046 Address: 1530 N.E. 67th Ave. Applicant: Mike Coyle of Faster Permits Owner: NWB Halsey LLC c/o West Coast Self Storage Group LLC Contractor: Eric Gambee Construction Inc. Plans call for a new four-story storage facility, parking, landscaping, and site improvements. |
![]() |
![]() |
$1,500,000 Address: Portland International Airport’s Concourse B at 7000 N.E. Airport Way. Applicant: Mike Coyle of Faster Permits Owner: Port of Portland Contractor: Hoffman Skanska LLC The work includes a composite metal system. |
| $1,100,000 Address: 1225 N.E. Second Ave. Applicant: Warren Tyler of PKA Architects Owner: Legacy Emanuel Hospital & Health Center Contractor: Out to bid. Plans call for installation of an underground storage tank serving emergency generators for the Holladay Park Hospital Building, which includes Unity Center for Behavioral Health and Research spaces. |
UNDER REVIEW
|
|
UNDER REVIEW
|
$522,975 Address: 7000 N.E. Airport Way Applicant: Mike Coyle of Faster Permits Owner: Port of Portland Contractor: Hoffman Skanska LLC The work includes metal wall panels. |
| $1,400,000 Address: 4380 S. Macadam Ave. Applicant: Stacy Bengtson of LRS Architects Owner: Clarity Ventures RF Contractor: Balfour Beatty Construction LLC Plans call for demolition of walls to create locker rooms, restrooms, a conference room, a fitness room, a mail room, a galley, a lobby area, a lounge, an office, a break room and an open office on the first floor. The alterations also include a new motherÃs room and remodel of the lobby and corridors on the second floor, and a remodel of bathrooms, corridors on the third through fifth floors. Also, the work includes ceiling, flooring, finishes, plumbing and electrical. |
![]() |
|
UNDER REVIEW
|
$917,000 Address: 3245 S.W. Pavilion Loop, unit SJH Applicant: Marcus Morgan of PKA Architects Owner: OregonÃs Medical Department Contractor: Fortis Construction Inc. The work includes installation of a new housekeeping pad, finishes and electrical on the third floor. |
| $592,000 Address: 3246 S.W. Pavilion Loop, unit SJH Applicant: Marcus Morgan of PKA Architects Owner: OregonÃs Medical Department Contractor: Out to bid. The work includes installation of an air handling unit, a pump, piping and electrical on the third floor. |