91视频

Park improvement project proceeding

By: Josh Kulla//April 6, 2021//

Park improvement project proceeding

Josh Kulla//April 6, 2021//

Listen to this article
Employees of general contractor Fulcrum Construction excavate new utility trenches as part of the Beaverton Fountain Park Improvements project. (Josh Kulla/91视频)
employees excavate new utility trenches as part of the City Park Fountain improvement project in . Work is expected to wrap up late this summer. (Josh Kulla/for the 91视频)

After more than 20 years of use, the popular City Park Fountain, in the heart of Beaverton, is finally getting an extensive and complex overhaul.

With annual required maintenance reaching critical mass, the city decided several years ago to replace the fountain’s exhausted mechanical equipment housed in an underground vault. New water filtration and circulation equipment will be housed in a new above-ground facility. In addition, aged playground equipment is being replaced at the park.

Construction at the site, near the Beaverton City Library, began in January and is scheduled to finish by late summer. General contractor Fulcrum Construction of Beaverton is spearheading the work. , the primary consultant for the city, has overseen the project’s design.

While the Library Fountain Improvement Project may not be large in terms of scale and scope, the fountain has attained a symbolic value far greater than the $3 million cost of work. Historically, more than 55,000 people per year have visited the water feature 鈥 a figure that is expected to grow in the future.

鈥淭his is obviously an iconic piece of Beaverton and this is going to enhance that,鈥 said Aaron Lee, a construction project manager for the city. 鈥淏ut we really are trying to, collectively as a city, 鈥 create a downtown experience.鈥

New, programmable fountain jets with LED lighting, and even sound, are being installed. Drainage around the plaza is being improved to help new chemical and UV filtration equipment perform more efficiently. The main fountain components came from Crystal Fountains, a Toronto firm considered one of the world’s top manufacturers of water features.

鈥淚’m not sure exactly what that will look like, or how we’ll do events and things like that,鈥 Lee said. 鈥淏ut there is a certain amount of automation and connectivity that will allow us to do a lot of really cool things that we obviously can’t do now.鈥

At the heart of the project is a complicated plan to remove a below-grade concrete vault housing the fountain’s mechanical, electrical and plumbing systems. Replacement systems will be placed inside a single-story pump house at the park’s southwest corner.

鈥淥ne of the issues is that the vault is 15 or 16 feet deep, so it requires confined space entry,鈥 Lee said. 鈥淵ou can’t just pop down there and get entry and do what you need to do. That will alleviate a lot of the maintenance issues.鈥

The pump house will feature brick masonry cladding to match the Beaverton City Library as part of an effort to tie together various city facilities in the downtown area. Future plans, Lee said, call for creation of a series of trails and walking paths to provide further connectivity between these elements.

Some existing materials are being reused and repurposed. An existing underground surge tank, which holds water from the fountain that is then filtered and recirculated, has been refurbished and recertified for use with the new water feature. Also, a good deal of the soil being excavated from the site during construction is being moved for off-site use elsewhere.

鈥淚t’s a pretty significant cost savings,鈥 Lee said.

The involvement of local contractors is also noteworthy. Fulcrum Construction is a COBID-certified company based in Beaverton, and many of its employees happen to live just blocks away from the job site.

鈥淚t’s very important to us; it’s our city,鈥 said Israel Rodriguez, the company owner. 鈥淚t helps commuting a lot, and as soon as it showed up, we bid. We also bid for other work for the Beaverton School District 鈥 things that are nearby. It is important for us, as well as for logistics; it’s economics.鈥

For a small firm that works almost exclusively in the public sector, that’s a big deal.

鈥淭hat’s all we do,鈥 Rodriguez said. 鈥淚t’s very important. We were blessed to get this job and the workforce is super happy with the work.鈥

Major subcontractors involved in the project include: Nuwave Concrete of Forest Grove; Cochran Inc., which is performing electrical work; and Outside the Lines, an Anaheim, California-based firm that specializes in water feature installations.

Beaverton Public Works Director Chad Lynn said the public is eager to see the fountain reopen after a closure already over a year. However, an exact date for that has not been determined, due to the ongoing pandemic.

鈥淲e can’t wait to get back into the fountain,鈥 Lynn said. 鈥淚t’s a centerpiece of the community with the adjacency to the library and downtown.鈥

A concrete vault containing plumbimg and mechanical equipment for the water feature (foreground) is awaiting removal. It will be replaced by an above-ground pump house that will house all-new mechanical and filtration equipment. (Josh Kulla/91视频)
A concrete vault containing plumbing and mechanical equipment for the water feature (foreground) is awaiting removal. It will be replaced by an above-ground pump house and new mechanical and filtration equipment. (Josh Kulla/for the 91视频)
Employees of general contractor Fulcrum Construction excavate new utility trenches as part of the Beaverton Fountain Park Improvements project. (Josh Kulla/91视频)
Employees of general contractor Fulcrum Construction excavate utility trenches. (Josh Kulla/for the 91视频)
Employees of general contractor Fulcrum Construction excavate new utility trenches as part of the Beaverton Fountain Park Improvements project. (Josh Kulla/91视频)
(Josh Kulla/for the 91视频)
An existing surge tank will be overhauled and re-used in the construction of a new water feature at Beaverton Fountain Park. It represents a significant cost savings on the project. (Josh Kulla/91视频)
An existing surge tank will be reused in construction of a new water feature at the park. (Josh Kulla/for the 91视频)
Fulcrum Construction is the general contractor for the Beaverton Fountain Park Improvements project and is self-performing the excavation scope of work. (Josh Kulla/91视频)
Fulcrum Construction, the project’s general contractor, is self-performing the excavation scope of work. (Josh Kulla/for the 91视频)
An existing play structure will stay in place but receive a new rubberized surface for added safety. (Josh Kulla/91视频)
An existing play structure will stay in place but receive a new rubberized surface to improve safety. (Josh Kulla/for the 91视频)
Fulcrum Construction is the general contractor for the Beaverton Fountain Park Improvements project and is self-performing the excavation scope of work. (Josh Kulla/91视频)
(Josh Kulla/for the 91视频)
Fulcrum Construction is the general contractor for the Beaverton Fountain Park Improvements project and is self-performing the excavation scope of work. (Josh Kulla/91视频)
Beaverton-based Fulcrum Construction is self-performing excavation for the Library Fountain Improvement Project. (Josh Kulla/for the 91视频)
Employees of general contractor Fulcrum Construction excavate new utility trenches as part of the Beaverton Fountain Park Improvements project. (Josh Kulla/91视频)
Fulcrum Construction workers excavate utility trenches as part of the project. (Josh Kulla/for the 91视频)
Nuwave Concrete of Forest Grove has started foundation work for a new pumphouse in the southwest corner of the site. (Josh Kulla/91视频)
Nuwave Concrete of Forest Grove has started foundation work for a new pump house in the southwest corner of the site. (Josh Kulla/for the 91视频)


News

See All News

Commentary

See All Commentary

COMMUNITY CALENDAR