91Ƶ

Bull Run water project gets green light to resume

By: Chuck Slothower//June 26, 2025//

In September 2024, a worker operated a roller at the Bull Run Filtration Plant project site. The Portland Water Bureau halted work at the site in February. (Chuck Slothower/91Ƶ file)

Bull Run water project gets green light to resume

Chuck Slothower//June 26, 2025//

Listen to this article

Construction of the $2.1 billion water infrastructure project can resume after a hearings officer gave the go-ahead, the announced.

“As of Monday, we’re going to start doing minor work to prepare the site, and we anticipate to be in full swing within a month,” Water Bureau spokesman Brandon Zero said Thursday.

Construction of the megaproject has been halted since February, after the Oregon Board of Appeals ruled that another hearings officer had not adequately considered community natural resources in approving the project’s conditional use.

Hearings officer Liz Fancher ruled Monday with approval of the project’s conditional use exception.

“This decision allows us to move forward to protect public health, and to provide resilience to wildfires, landslides, flooding and other natural disasters,” Mayor Keith Wilson stated in a news release on Wednesday. “The city is eager to put hundreds of construction tradespeople back to work to complete these critical water system improvements.”

A joint venture of and Corp. is building the project.

The project, which comprises a plant near the Clackamas County line and a network of pipelines, has faced opposition from a neighborhood group, the Cottrell Community Planning Organization.

The project team is working to meet a Sept. 30, 2027, deadline to deliver filtered water to the Water Bureau’s approximately 1 million customers in the Portland-metro area. The deadline was imposed on the Water Bureau by the after was repeatedly found in drinking water.