91ÊÓÆµ

Conway Construction

Mar 10, 2015

Jury: all bridge project parties at fault

A jury has ruled that Morrison Bridge owner Multnomah County is entitled to $4.4 million in damages for a botched project that replaced the span’s steel grating with a polymer deck that started deteriorating shortly after it was installed.

Mar 2, 2015

Portland span still needs long-term fix

Multnomah County engineers are still debating the best fix for the deteriorating Morrison Bridge deck.

Nov 25, 2014

Best fix for Morrison Bridge still being sought

Multnomah County officials are holding off on major repairs to the Morrison Bridge until an investigation takes place to determine replacement materials for failing deck panels.

Feb 23, 2012

Morrison Bridge work to be completed earlier than expected

In the wake of a delay last summer, the $4.2 million project to replace open steel grating on the Morrison Bridge is finally close to completion.

Sep 7, 2011

County sticks with Morrison Bridge contractor; work to resume

After almost two months of being stalled, work to replace the steel grating on the Morrison Bridge with lightweight fiber-reinforced polymer panels may finally resume, according to Multnomah County.

Jul 18, 2011

Morrison Bridge work presents challenges

Work is under way to make the Morrison Bridge safer by replacing 50-year-old steel grating with fiber-reinforced polymer panels. The aging grating is slippery and has contributed to the bridge being the worst in Portland for fatal accidents.