Day CPM – Daily Journal of Commerce /news/tag/day-cpm/ Building and Construction News in Portland, Oregon and the Pacific Northwest Fri, 16 Apr 2021 00:25:42 +0000 en-US hourly 1 https://wordpress.org/?v=6.6.6 /files/2023/08/favicon.webp Day CPM – Daily Journal of Commerce /news/tag/day-cpm/ 32 32 Building Blocks: Nestucca Valley K-8 school /news/2021/04/15/building-blocks-nestucca-valley-k-8-school/ Fri, 16 Apr 2021 00:25:38 +0000 /?p=256335 A full remodel of an existing elementary school in Cloverdale is nearly done. A 40,745-square-foot addition will allow the school moving forward to serve students in grades K-8.

The post Building Blocks: Nestucca Valley K-8 school appeared first on Daily Journal of Commerce.

]]>
0416_bldg_blocks_school_01_web
A renovated school in Cloverdale will be able to serve students in grades K-8. (courtesy of )

PROJECT: Nestucca Valley School District K-8 School (Nestucca K-8)

LOCATION: 36925 U.S. 101 South, Cloverdale

SIZE: 8.96 acres with a larger undeveloped adjacent parcel of 28.3 acres

COST: $25 million

START DATE: April 2019

ANTICIPATED END DATE: May 2021

OWNER: Nestucca Valley School District

OWNER’S REPRESENTATIVE:

ARCHITECT:

ENGINEER:

CONTRACTOR: O’Brien & Company

NUMBER OF WORKERS EMPLOYED: 100

0416_bldg_blocks_school_02_web
A 40,745-square-foot addition was constructed for the school to accommodate greater capacity. (courtesy of O’Brien & Company)

SIGNIFICANCE OF PROJECT: This project involves a full remodel of an existing elementary school so that it’s able to serve students in grades K-8. The building also serves as a central location for the community during a natural disaster. The remodel encompasses 28,203 square feet, and a single-story addition is 40,745 square feet. The structure is wood-framed with glu-lams, an aluminum storefront, stained/polished concrete, an interior wood storefront, and a poured-in-place rubber surfacing playground with all new equipment. The new building includes classrooms, administrative offices, commons, a gymnasium, a kitchen, career and technical education labs, music space, and a secure front entry on the south side. New site work includes a stormwater management system, an entry plaza, outdoor learning areas, a community garden, and new vehicular circulation including parent and bus drop-off with parking. The existing school remained open during construction.

One of the biggest challenges affecting the entire project was the COVID-19 pandemic, which impacted all aspects from lead times to manpower. O’Brien & Co. and its team persevered, and the project is wrapping up four to five months ahead of the original completion date and under budget. To keep all parties involved safe, the company kept a “Social Distancing Officer” on site at all times and required temperature checks at check-in. Also, mask use was required at all times, and the firm followed all AGC and CDC COVID-19 safety guidelines.

“Building Blocks” is a 91Ƶ feature that spotlights noteworthy projects either under construction or approaching the start of construction. To submit a project for consideration, please visit: djcoregon.com/building-blocks.

The post Building Blocks: Nestucca Valley K-8 school appeared first on Daily Journal of Commerce.

]]>
As 2020 nears end, so does school project /news/2020/12/23/2020-nears-end-school-project/ Wed, 23 Dec 2020 21:55:10 +0000 /?p=252531 Twality Middle School, in Tigard, is receiving final touches in preparation for the eventual return of students and staff.

The post As 2020 nears end, so does school project appeared first on Daily Journal of Commerce.

]]>
Earlier this month, employees performed concrete finish work on the new sidewalk outside Twality Middle School in Tigard. (Josh Kulla/for the 91Ƶ)

In 2020, school construction has continued to be a bright spot for the building industry in the Portland-metro area. In Tigard, the $46 million Twality Middle School modernization is one such project that has kept crews busy. After ground was broken in late 2019, builders persevered throughout challenging times. The team expected to obtain a temporary certificate of occupation late this month.

“What’s left is just some finish stuff and the punch list and that’s about it,” said Greg Yoder, the project superintendent for general contractor Triplett Wellman Contractors. “The owner has their movers out here, and they’ve been out here for a good week moving stuff into the building one semi after another.”

designed the project, which is part of an overhaul of an entire school campus that includes Templeton Elementary School nearby. The latter was rebuilt in a similar fashion as Twality Middle School, and completed in summer 2019.

Much of the existing middle school was demolished. A few portions were kept and remodeled, but most of the space was built anew. Twality Middle School now has a new gymnasium, library/media center, common areas, visual arts classrooms, maker space, centralized administrative offices and two U-shaped wings of wired-for-technology classrooms.

“It’s almost a new building,” Shawn Christensen, a project manager with , the owner’s representative for Tigard-Tualatin School District, told the 91Ƶ late last year.

All of the space is spread over two stories, with the ground floor nestled into a hillside. This provides a daylit basement and convenient access to the ground level from both floors. The upper floor opens to parking and the main entrance facing Southwest 97th Avenue, while the lower floor opens at the rear of the building to a pair of courtyards and bus parking.

Earlier this month, IES Commercial & Industrial was on site finishing low-voltage electrical work, while Hydro-Temp Mechanical crews were completing plumbing and HVAC work in the school kitchen and other areas. Personnel from the Beaverton office of Diversified were completing audio-visual systems work. Other workers were finishing the gymnasium’s wood floor.

Triplett Wellman considers school projects its bread and butter, and Twality certainly fits in that category. But COVID-19 has made every project somewhat unique because of the challenges presented to the workforce and suppliers of materials. This has been the case since March.

“We were way out ahead on our schedule, and then COVID hit and I think at one point out here in one week’s time we had seven or eight guys come down with it,” Yoder said. “And I know our steel fabricator, he was hit with it, so their immediate action was to shut their shop down. They were down a week so that had a little bit of an impact on us.”

Finding work-arounds and persevering through delays and other obstacles has become second nature.

“I think a lot of times, what causes these schedule impacts is guys don’t order their material when they should and then they want to blame it on whatever they can,” Yoder said. “But if you order months ahead you’ll usually get it. You’ve got to adjust for it, so you definitely have to be looking way ahead. But I’m satisfied with where we’re at. We’re going to get the building done when we’re supposed to.”

The new library and media center features expanded overhead space to make it more comfortable for students. It also opens to an outdoor courtyard. (Josh Kulla/91Ƶ)
The new library/media center at Twality Middle School features expansive overhead space. It also opens to an outdoor courtyard. (Josh Kulla/for the 91Ƶ)
The new gymnasium has a new state-of-the-art wood floor. (Josh Kulla/91Ƶ)
The school’s new gymnasium has a state-of-the-art wood floor. (Josh Kulla/for the 91Ƶ)
New furniture is being staged in the commons area in preparation for the completion of the project. (Josh Kulla/91Ƶ)
New furniture occupies the commons area ahead of project completion. (Josh Kulla/for the 91Ƶ)
1228_twality_middle_school_05_web
(Josh Kulla/for the 91Ƶ)
New locker rooms show that the average middle school locker size has not changed in over a half-century. (Josh Kulla/91Ƶ)
New locker rooms have ample space for numerous occupants at one time. (Josh Kulla/for the 91Ƶ)
The new kitchen features a pair of huge walk-in freezers for food stores. (Josh Kulla/91Ƶ)
The new kitchen features a pair of huge walk-in freezers for food stores. (Josh Kulla/for the 91Ƶ)
The back side of the school is entered through the lower floor, and is the primary means of bus circulation and pickup. (Josh Kulla/91Ƶ)
From the back side, entry into the school takes place on the lower floor. This is the primary means of bus circulation. (Josh Kulla/for the 91Ƶ)

The post As 2020 nears end, so does school project appeared first on Daily Journal of Commerce.

]]>
Nonprofit found to make use of former Multnomah County jail /news/2020/05/08/nonprofit-found-make-use-former-multnomah-county-jail/ Fri, 08 May 2020 23:45:15 +0000 /?p=246611 Helping Hands Reentry Outreach Centers has signed a five-year lease agreement for the former Wapato Jail building.

The post Nonprofit found to make use of former Multnomah County jail appeared first on Daily Journal of Commerce.

]]>
Helping Hands Reentry Outreach Centers has agreed to a five-year lease at the former Wapato Jail building, now known as the Bybee Lakes Hope Center, in North Portland. (Sam Tenney/91Ƶ file)
Helping Hands Reentry Outreach Centers has agreed to a five-year lease at the former building, now known as the , in North Portland. (Sam Tenney/91Ƶ file)

Helping Hands Reentry Outreach Centers has signed a five-year lease agreement for the former Wapato Jail building, real estate investor Jordan Schnitzer announced recently.

Schnitzer, president of , agreed to lease the 155,400-square-foot Bybee Lakes Hope Center for the token amount of $1 a year.

“After two years of looking for the right partner, we are now entering into a five-year lease with Helping Hands Reentry Outreach Centers to renovate and repurpose the project formerly known as Wapato,” Schnitzer stated in a news release. “Since purchasing the property in 2018, we have entertained numerous proposals from credible nonprofits to help homeless and others in need.”

Schnitzer stated that he was impressed after meeting with Helping Hands founder Alan Evans, who was homeless for 27 years before establishing the nonprofit in 2002. It’s based in Seaside, and now has 11 facilities in Multnomah, Clatsop, Yamhill and Tillamook counties.

The lease agreement is a milestone in the yearslong effort to put the never-used jail building to some useful purpose. Schnitzer had pushed for a social-service tenant, saying he would otherwise demolish the building. In October 2019, Schnitzer went so far as to unveil plans for a 314,000-square-foot warehouse. The former jail, completed in 2004, is in an industrial area dotted with fulfillment centers and other facilities.

Developer Marty Kehoe, who acquired the building from , sold it to Harsch for $5 million in April 2018.

The project team that will convert the jail into a shelter and reentry center was assembled by construction manager . , an affiliate of – the ex-jail’s original builder – has been selected as general contractor. Architecture and engineering services were awarded to

Otak will work with VLMK Engineering + Design, Interface Engineering and Knot to provide functional architecture, way-finding and interior design.

The Bybee Lakes Hope Center will pair supportive services with transitional housing. Helping Hands will open three of the nine wings at the facility and house up to 228 beds in the first year of operation, Harsch announced. At full capacity, the center will be able to serve 525 individuals.

The post Nonprofit found to make use of former Multnomah County jail appeared first on Daily Journal of Commerce.

]]>
Something old, something new /news/2019/12/23/something-old-something-new-2/ Tue, 24 Dec 2019 00:28:07 +0000 /?p=197757 Existing concrete shell structures will be kept and renovated, and eventually connect with a new, two-story building to serve Twality Middle School in Tigard.

The post Something old, something new appeared first on Daily Journal of Commerce.

]]>
Julian Quintanilla, a carpenter with Triplett Wellman Contractors, welds a structural steel support bracket at Twality Middle School in Tigard. (Josh Kulla/91Ƶ)
Julian Quintanilla, a carpenter with , welds a structural steel support bracket at Twality Middle School in Tigard. (Josh Kulla/91Ƶ)

It was a balancing act, according to the project team.

That is, when facing a decision of whether to keep a portion of Twality Middle School in Tigard and add to it, or simply demolish the entire existing facility and construct a new one, officials opted for the former. Existing concrete shell structures will be kept and renovated, and eventually connect with a new, two-story building.

“It’s almost a new building,” said Shawn Christensen, a project manager with , the owner’s representative for Tigard-Tualatin School District. “We kept 27,000 square feet worth of the concrete boxes in the gym, which is going to stay a gym. There’s another gym that we’re converting to locker rooms. And then we’ve kept the cafeteria, and we are converting that to music rooms. Everything else got torn down.”

designed the $46 million project, and Woodburn-based Triplett Wellman Contractors is serving as general contractor. The school will gain a new gymnasium, media center, common areas, visual arts classrooms, maker space, centralized administrative offices and a full suite of wired-for-technology classrooms.

All of it is spread over two stories, with the ground floor nestled into a hillside. This will give the impression of a daylit basement and provide convenient access across both floors.

General contractor Triplett Wellman is self-performing framing and concrete work on the Twality Middle School project. (Josh Kulla/91Ƶ)
General contractor Triplett Wellman Contractors is self-performing framing and concrete work for the Twality Middle School renovation and expansion. (Josh Kulla/91Ƶ)

The school’s orientation will be roughly north to south, with the existing structures situated at the site’s south end. Construction is being split into two phases; currently, the first phase is under way at the site’s north end.

“The big push right now is just the framing,” said Greg Yoder, site superintendent for Triplett Wellman Contractors. “The site contractor was here today – it’s Catworks out of Vancouver (Washington), and they’re doing all the dirt work. And then we’ve got (PDX) Electric doing our electric, and Hydro-Temp is our plumber. And they’ve got both the wet and the dry side, so plumbers have been working getting the slab-on-grade stuff in.”

The building will have slab-on-grade foundations with wood framing and glulam columns and beams for structural support over the typical long spans found in schools. A curtainwall system will bring let natural light into the building from the west side, where new parking and bus pathways will be built. Both levels of the new building’s east side will feature vertically accented metal panels and glazing.

The project is part of a two-pronged remodel of a campus that also includes Templeton Elementary School. The latter was rebuilt in a similar fashion, with a portion of the 1960s-era building retained. That project was completed this past summer, and students and staff are now using the new space.

The project team decided to take a similar approach with the Twality project, though it remains uncertain whether it’s the most cost-effective one.

“We kept the (old) gym operational during construction, so it’s been a significant challenge to keep that gym free of noise and issues,” Christensen said. “They were thinking there would be budget savings with these giant concrete boxes, but as far as we’ve gotten into the building I’m thinking we might not have saved money by keeping the boxes.”

But the move allowed officials burdened by construction at both schools to maintain gym space.

“There were definitely complications associated with that for sure,” Christensen added. “And honestly they needed the gym. They only have a small gym down there at the elementary school, so using this gym has allowed them to run PE (classes) for 1,100 students.”

Similar choices were made with the old school cafeteria, which will tie in with the new building.

“It will all be connected,” Christensen said.

Triplett Wellman employee Nick Kornilkin works to place an exterior framed wall panel. (Josh Kulla/91Ƶ)
Triplett Wellman employee Nick Kornilkin works to place an exterior framed wall panel. (Josh Kulla/91Ƶ)
A crew with Catworks excavates a trench for electrical conduit feeding the main electrical room at Twality Middle School. (Josh Kulla/91Ƶ)
A crew with excavates a trench for electrical conduit to feed the main electrical room at Twality Middle School. (Josh Kulla/91Ƶ)
The school's old gymnasium building, background, has been retained and will be connected with the new two-story structure. (Josh Kulla/91Ƶ)
The school’s old gymnasium building, background, has been retained and will connect with the new two-story structure. (Josh Kulla/91Ƶ)
Triplett Wellman employee Michael Gilliland punches openings for anchor bolts in a weather barrier strip. (Josh Kulla/91Ƶ)
Triplett Wellman employee Michael Gilliland punches openings for anchor bolts in a weather barrier strip. (Josh Kulla/91Ƶ)
Framing work is beginning atop the new building's slab-on-grade foundation. (Josh Kulla/91Ƶ)
Framing work is beginning atop the new building’s slab-on-grade foundation. (Josh Kulla/91Ƶ)
Triplett Wellman carpenter Michael Gilliland drills an anchor bolt opening on the bottom of a wall panel. (Josh Kulla/91Ƶ)
Triplett Wellman carpenter Michael Gilliland drills an anchor bolt opening on the bottom of a wall panel. (Josh Kulla/91Ƶ)
Nick Kornilkin, left, and Victor Gostevskyh help erect an exterior wall panel. (Josh Kulla/91Ƶ)
Nick Kornilkin, left, and Victor Gostevskyh help erect an exterior wall panel. (Josh Kulla/91Ƶ)
Much of the old Twality Middle School building has been demolished, with a new two-story structure being constructed to connect with an existing gymnasium and cafeteria. (Josh Kulla/91Ƶ)
Much of the old Twality Middle School building has been demolished; however, some remaining space will connect to a new two-story structure. (Josh Kulla/91Ƶ)
Triplett Wellman carpenter Victor Gostevskyh affixes a strip of weather barrier to the underside of a wall panel. (Josh Kulla/91Ƶ)
Triplett Wellman carpenter Victor Gostevskyh affixes a strip of weather barrier to the underside of a wall panel. (Josh Kulla/91Ƶ)
Triplett Wellman carpenter Michael Gilliland drills openings on the bottom of a wall panel for anchor bolts. (Josh Kulla/91Ƶ)
Triplett Wellman carpenter Michael Gilliland drills openings in the bottom of a wall panel for anchor bolts. (Josh Kulla/91Ƶ)
Nick Kornilkin, second from right, helps guide a wall panel into place. (Josh Kulla/91Ƶ)
Nick Kornilkin, second from right, helps guide a wall panel into place. (Josh Kulla/91Ƶ)

The post Something old, something new appeared first on Daily Journal of Commerce.

]]>
CM-GC sought for elementary school project in Tigard /news/2018/12/18/cm-gc-sought-elementary-school-project-tigard/ Tue, 18 Dec 2018 17:14:36 +0000 /?p=183427 The Tigard-Tualatin School District is looking for a firm to take on the role of construction manager-general contractor and build the new Art Rutkin Elementary School.

The post CM-GC sought for elementary school project in Tigard appeared first on Daily Journal of Commerce.

]]>

The Tigard-Tualatin School District is looking for a firm to take on the role of construction manager-general contractor and build the new Art Rutkin Elementary School. It will be constructed on a 20-acre site in Tigard’s River Terrace area.

jt

The 91Ƶ Project Center is the region’s leading source of construction project bidding information and documents. With 100s of projects at any given time, you’re guaranteed to find your next project, and all the information you need to bid on it. Subscribe to the 91Ƶ Project Center today

To view the Project Center listing related to this story, click the link(s) below.

The arrivals of families to the developing area are expected to bring more than 400 new elementary school students over the next decade. Meanwhile, the three existing elementary schools that serve the area – Alberta Rider, Deer Creek and Mary Woodward – already are overcrowded.

The $36 million project is being paid for with money from a $291 million bond approved by voters in 2017. Construction is anticipated to start by February 2020 and finish in time to accommodate the start of the 2021-22 school year.

Prospective bidders can send requests for proposal documents by emailing Juliet Jacobsen of , the owner’s representative for the project, at juliet.jacobsen@otak.com.

A mandatory pre-bid conference for the project will take place at 11 a.m. on Dec. 19 at the district’s Hibbard Building, at 6960 S.W. Sandburg St. in Tigard. All bids are due by 3 p.m. on Jan. 10, 2019.

The post CM-GC sought for elementary school project in Tigard appeared first on Daily Journal of Commerce.

]]>
Photos: Team tops out downtown courthouse /news/2018/11/09/photos-downtown-courthouse-project-topped-out/ Fri, 09 Nov 2018 21:32:51 +0000 /?p=181982 Ironworkers placed the final structural beam Friday atop the 17-story Multnomah County Central Courthouse project.

The post Photos: Team tops out downtown courthouse appeared first on Daily Journal of Commerce.

]]>

A celebration was held Friday to mark the topping out of the Multnomah County Central Courthouse project in downtown Portland. The final structural beam was placed atop the 17-story tower by ironworkers with Local 29 working for Alliance Industrial Group.

The project’s groundbreaking was held in October 2016, and construction manager/general contractor began major work on the $324.5 million project in spring 2017. Ongoing façade work is expected to last through next April, and interiors and finishes will be completed near the end of 2019. Commissioning will begin next summer and run through early 2020, and a grand opening is scheduled for that spring.

The project’s design team includes , the prime architect, and , which is handling courts programming and design. is the owner’s representative for .

Ironworkers with Local 29 and employees of Alliance Industrial Group, from left, Curtis Crouch, an apprentice, and journeymen Jason Makes and Fenton Mayes check the spread of the beam before it is raised into place.
Ironworkers with Local 29 and employees of Alliance Industrial Group, from left, Curtis Crouch, an apprentice, and journeymen Jason Makes and Fenton Mayes check the spread of the beam before it is raised into place.
Joshua Dodson, vice president of owner's represantative Day CPM, signs the beam.
Joshua Dodson, vice president of owner’s represantative Day CPM, signs the beam.
Liz Smith Currie, right, senior policy advisor for Multnomah County Chairwoman Deboray Kafoury, and Willie Myers, executive secretary treasurer of the Columbia Pacific Building Trades Council and a Prosper Portland board member, sign the beam before the start of the ceremony.
Liz Smith Currie, right, senior policy advisor for Multnomah County Chairwoman Deborah Kafoury, and Willie Myers, executive secretary treasurer of the Columbia Pacific Building Trades Council and a Prosper Portland board member, sign the beam before the start of the ceremony.

1109_mccc_topout_04_web

Heather Mayther, a journeyman carpenter with Hoffman Structures Inc. who began work on the project last summer as a fifth-term apprentice, speaks about bringing her daughters, seven-year-old triplets, to visit the site to inspire them with the potential of a career in the trades. The project is utilizing apprentice labor of at least 20 percent per trade, 20 percent of which are minorities and 25 percent of which are women.
Heather Mayther, a journeyman carpenter with Hoffman Structures Inc. who began work on the project last summer as a fifth-term apprentice, speaks about bringing her daughters, seven-year-old triplets, to visit the site to inspire them with the potential of a career in the trades. The project is utilizing apprentice labor of at least 20 percent per trade, 20 percent of which are minorities and 25 percent of which are women.
Multnomah County Chairwoman Deboray Kafoury speaks in the building's main lobby, which will contain a grand staircase up to third-floor jury assembly areas featuring views of the Willamette River, Hawthorne Bridge and Mt. Hood.
Multnomah County Chairwoman Deborah Kafoury speaks in the building’s main lobby, which will contain a grand staircase up to third-floor jury assembly areas featuring views of the Willamette River, Hawthorne Bridge and Mt. Hood.
Union ironworkers with Alliance Industrial Group prepare the beam to be hoisted atop the structure.
Union ironworkers with Alliance Industrial Group prepare the beam to be hoisted atop the structure.
Ironworkers wait atop the structure for the beam to be lifted into place.
Ironworkers wait atop the structure for the beam to be lifted into place.
Union ironworkers with Alliance Industrial Group wait for the hook to be lowered before rigging the beam.
Union ironworkers with Alliance Industrial Group wait for the hook to be lowered before rigging the beam.
Ironworkers wait atop the structure for the beam to be lifted into place.
Ironworkers wait atop the structure for the beam to be lifted into place.
The beam is hoisted up on the building's west side along Southwest First Avenue.
The beam is hoisted up on the building’s west side along Southwest First Avenue.
Ironworkers Local 29 members guide the beam into place.
Ironworkers Local 29 members guide the beam into place.
A worker on the buiding's tenth floor watches as the beam is set in place.
A worker on the building’s tenth floor watches as the beam is set in place.
Ironworkers pose for a photo atop the beam to commemorate structural completion of the courthouse.
Ironworkers pose for a photo atop the beam to commemorate structural completion of the courthouse.
The 17-story is being erected at the west end of the Hawthorne Bridge.
The 17-story is being erected at the west end of the Hawthorne Bridge.

The post Photos: Team tops out downtown courthouse appeared first on Daily Journal of Commerce.

]]>
Salem Public Library project up for bidding /news/2018/10/26/salem-public-library-project-up-for-bidding/ Fri, 26 Oct 2018 22:54:31 +0000 /?p=181485 A request for proposals has been issued for a firm to provide design-build services for a package of safety improvements at the Salem Public Library’s main building in downtown.

The post Salem Public Library project up for bidding appeared first on Daily Journal of Commerce.

]]>
A package of improvements on tap for the Salem Public Library will include seismic improvements and ADA upgrades. (Sam Tenney/91Ƶ)
A package of improvements on tap for the Salem Public Library will include seismic improvements and upgrades. (Sam Tenney/91Ƶ)

has been issued for a firm to provide design-build services for a at the Salem Public Library‘s main building in downtown.

The three-story Brutalist-style building, constructed in 1972, will receive a seismic retrofit as well as upgrades to ensure compliance with the Americans with Disabilities Act. Also, new mechanical systems and ductwork will be installed, and additional seismic work will improve the auditorium and adjacent parking garage.

jt

The 91Ƶ Project Center is the region’s leading source of construction project bidding information and documents. With 100s of projects at any given time, you’re guaranteed to find your next project, and all the information you need to bid on it. Subscribe to the 91Ƶ Project Center today

To view the Project Center listing related to this story, click the link(s) below.

Other work will involve replacing all library bookshelves, security cameras and the public address system.

According to the city, a 2014 engineering study by Portland firm found the library and parking structure do not meet standards for life safety, and that users, staff and volunteers would be at risk in the event of a major earthquake. This prompted the city to pursue passage of a bond measure to pay for the work. Voters in 2017 approved an $18.6 million general obligation bond.

City officials hope to select a designer and contractor by the end of the year. Construction is set to start in early 2020 and wrap up by May 2021.

Questions about RFP specifications may be emailed to John Nibler of owner’s representative at john.nibler@otak.com.

Questions regarding the RFP process may be directed to Shawna Self, contracts and procurement manager for the city of Salem, at 503-588-6445 or sself@cityofsalem.net.

Bid proposals must be filed with the city before 2 p.m. on Nov. 7.

The post Salem Public Library project up for bidding appeared first on Daily Journal of Commerce.

]]>
Builder sought to take on project at Tigard school /news/2017/09/07/builder-sought-to-take-on-project-at-tigard-school/ Thu, 07 Sep 2017 22:03:40 +0000 /?p=167830 The Tigard-Tualatin School District is looking for a builder to construct a high-tech, $6.5 million addition to the district’s alternative high school.

The post Builder sought to take on project at Tigard school appeared first on Daily Journal of Commerce.

]]>

The Tigard-Tualatin School District is looking for a builder to construct a high-tech, $6.5 million addition to the district’s alternative high school.

The project to build the Durham Education Center addition is being paid for with money from a $291 million bond approved by voters in 2016. The new facility is intended to bring together users of the Durham Center’s various programs, which include dropout recovery and an online academy.

The district received an exemption from state law requiring competitive bidding for projects that receive public money. Officials will consider both the bid price, as well as qualifications and experience.

The project will feature a high level of risk and technical complexity due to the amount of other construction work occurring near the site, the presence of students nearby and budget limitations, according to the district’s request for proposals.

The new construction will feature a two-story, 15,000-square-foot building, including classrooms, common areas, offices, flex space, a kitchen and an outdoor, covered play area as well as improvements to a parking lot and other areas.

The Durham Center’s two existing buildings will remain in use throughout the project.

As a facility, the building is expected to produce as much energy as it uses.

and have been retained as architect and owner’s representative, respectively.

The post Builder sought to take on project at Tigard school appeared first on Daily Journal of Commerce.

]]>
Ground broken on courthouse project /news/2016/10/05/ground-broken-on-courthouse-project/ Wed, 05 Oct 2016 14:41:01 +0000 /?p=156843 Despite its design not yet being approved and construction months away from beginning, a groundbreaking was held Tuesday for the Multnomah County Central Courthouse.

The post Ground broken on courthouse project appeared first on Daily Journal of Commerce.

]]>

Despite its design not yet being approved and construction months away from beginning, a groundbreaking was held Tuesday for the Multnomah County Central Courthouse. Major work on the project is slated to begin in the spring of 2017; in the meantime, the demolition of the Veritable Quandary building and tree removal will begin next month, and the new building’s design will be reviewed for the second time by the Historic Landmarks Commission on Oct. 24.

The planned courthouse, designed by and , will have 17 stories and reach 325 feet in height. It will contain a total of about 440,000 square feet that will include courtrooms, offices for district attorneys, public defenders, and sheriffs. The building will connect to the historic Jefferson Station office condominium building at Southwest First Avenue and Jefferson Street, triggering review of the project by the Historic Landmarks Commission.

has so far acquired all but two of the nine units at Jefferson Station, which will undergo renovations and be used as high-volume courts dealing with traffic and parking infractions, small claims, and landlord-tenant disputes.

will serve as the construction manager/general contractor on the project, and will serve as the owner’s representative. The building is slated for completion in 2020.

Elected officials, dignitaries and project partners turn the first ceremonial dirt on the site. The groundbreaking was held far in advance of major construction beginning to allow outgoing Multnomah County commissioners who pushed for the project and are leaving office at the end of the year to participate in the ceremony.
Elected officials, dignitaries and project partners turn the first ceremonial dirt on the site. The groundbreaking was held far in advance of major construction beginning to allow outgoing Multnomah County commissioners who pushed for the project and are leaving office at the end of the year to participate in the ceremony.
Groundbreaking shovels are adorned with gavels at the end of the handle.
Groundbreaking shovels are adorned with gavels at the end of the handle.
The courthouse will be built on a site at the west end of the Hawthorne Bridge bounded by Southwest First Avenue and Naito Parkway and Madison and Jefferson streets.
The courthouse will be built on a site at the west end of the Hawthorne Bridge bounded by Southwest First Avenue and Naito Parkway and Madison and Jefferson streets.
Oregon Supreme Court Chief Justice Thomas Balmer, right, hands a gavel-adorned shovel to Veritable Quandary owner Denny King, who watched the groundbreaking from the patio of the recently-closed restaurant. "I'm not sure I cherish that," King joked about the shovel.
Oregon Supreme Court Chief Justice Thomas Balmer, right, hands a gavel-adorned shovel to Veritable Quandary owner Denny King, who watched the groundbreaking from the patio of the recently-closed restaurant. “I’m not sure I cherish that,” King joked about the shovel.

The post Ground broken on courthouse project appeared first on Daily Journal of Commerce.

]]>
Photos: Work wrapping on bus maintenance facility /news/2016/08/26/photos-work-wrapping-on-oregon-city-bus-maintenance-facility/ Fri, 26 Aug 2016 18:19:26 +0000 /?p=155464 P&C Construction is wrapping up work on TMF14, a $9 million transportation and maintenance facility for Oregon City School District.

The post Photos: Work wrapping on bus maintenance facility appeared first on Daily Journal of Commerce.

]]>

Work is wrapping up on , a $9 million transportation and maintenance facility for Oregon City School District. is service as the construction manager/general contractor on the yearlong project, a 30,000-square-foot tilt-up concrete and structural steel building. The facility includes a multiple-bay garage for servicing the district’s fleet of school buses, administrative offices, a driver’s lounge and dispatch area, and maintenance shop. is the project’s designer, and served as the owner’s representative.

0826_OC_Transport_01_WEB 0826_OC_Transport_02_WEB 0826_OC_Transport_03_WEB 0826_OC_Transport_04_WEB 0826_OC_Transport_05_WEB 0826_OC_Transport_06_WEB 0826_OC_Transport_07_WEB 0826_OC_Transport_08_WEB 0826_OC_Transport_09_WEB

The post Photos: Work wrapping on bus maintenance facility appeared first on Daily Journal of Commerce.

]]>