Evergreen Public Schools – Daily Journal of Commerce /news/tag/evergreen-public-schools/ Building and Construction News in Portland, Oregon and the Pacific Northwest Tue, 26 Nov 2019 22:21:25 +0000 en-US hourly 1 https://wordpress.org/?v=6.6.6 /files/2023/08/favicon.webp Evergreen Public Schools – Daily Journal of Commerce /news/tag/evergreen-public-schools/ 32 32 School builders working through site challenges /news/2019/11/26/school-builders-working-site-challenges/ Tue, 26 Nov 2019 22:21:25 +0000 /?p=196795 A parcel of former farmland in Vancouver, Washington, is gaining a new elementary school to replace one that sits on a different property.

The post School builders working through site challenges appeared first on Daily Journal of Commerce.

]]>
Carpenters with Northwest Framing Systems install roof joists at Image Elementary School in Vancouver, Washington. (Josh Kulla/91Ƶ)
Carpenters with Northwest Framing Systems install roof joists at Image Elementary School in Vancouver, Washington. (Josh Kulla/91Ƶ)

Multiple school construction projects are under way in Vancouver, Washington, for . The district last year gained voters’ approval for a $695 million bond, and money is being put to work.

One of the projects under way is a replacement for Image Elementary School. General contractor is building the school on a parcel of former farmland near the intersection of Northeast 131st Avenue and 52nd Street.

“It’s a really significantly different site,” Evergreen Public Schools spokeswoman Gail Spolar said. “It doesn’t have a school on it, but (crews) have had some interesting things to take care of (on the site) before they started constructing the new school.”

‘ design for the two-story, approximately 62,000-square-foot facility calls for use of mass-timber structural elements, including glulam beams and columns. Laminated veneer lumber will be used extensively in the framing.

An open interior design will allow for tall ceilings, large learning stairs and a media center. The gymnasium and family resource center will be isolated from the rest of the school to allow for public use.

Excavation and site work began in June.

“It’s a little challenging because we have the wetland that’s all part of it,” Emerick Construction project manager Alicia LaManna said. “So, the soil makeup underneath the site is quite interesting in how it’s been filled in over the decades of being a farmland. We had quite a lot of excavation that we had to do before we could even start the foundations.”

Journeyman carpenters Aaron Dobroth, left, and Mitchell Cummings, both employees of Northwest Framing Systems, install exterior walls on the classroom wing of Image Elementary School. (Josh Kulla//91Ƶ)
Journeyman carpenters Aaron Dobroth, left, and Mitchell Cummings, both employees of Northwest Framing Systems, install exterior walls on the classroom wing of Image Elementary School. (Josh Kulla//91Ƶ)

In addition to excavation, however, plenty of fill was required to level off the site before construction could take place. Fortunately, there was a ready supply available from excavation taking place for a new elementary school (not yet named) being built on Northeast 162nd Avenue between 39th and 43rd streets.

“The export from 22 – it was quality material,” said Dan Bodell, a project manager with . “We also ended up taking dirt from underneath the building here and we were able to use it elsewhere on this site, and we went ahead and rearranged all of that. And then we brought this other material in to bring the whole site up.”

As a result, much of the site has been raised. Also, extensive groundwater required construction of a massive stormwater retention chamber on the east side of the site. Multiple temporary wells were used to pump out groundwater during excavation for the slab-on-grade foundation.

“Everything has been brought up four or five feet so that we weren’t down in the wet,” Bodell said. “And that goes back to all the engineering that goes into handling the rainwater – making sure we’re not flooding (adjacent residences) when the rains come because all of a sudden you have a hard surface here.”

After the new Image Elementary School opens (fall 2020 is the target date), the existing one – near the intersection of Northeast 122nd Avenue and 44th Street – will serve as a temporary facility on a rotating basis for other schools being replaced by new ones on their current properties.

Emerick Construction is self-performing the concrete work at Image Elementary School. (Josh Kulla/91Ƶ)
Emerick Construction is self-performing the concrete work at Image Elementary School. (Josh Kulla/91Ƶ)
Journeyman carpenter and crew foreman Michael Nottingham of Northwest Framing Systems cuts studs. (Josh Kulla/91Ƶ)
Journeyman carpenter and crew foreman Michael Nottingham of Northwest Framing Systems cuts studs. (Josh Kulla/91Ƶ)
Carpenters with Northwest Framing Systems install roof joists. (Josh Kulla/91Ƶ)
Carpenters with Northwest Framing Systems install roof joists. (Josh Kulla/91Ƶ)
Erik Halstead, a carpenter with Emerick Construction and member of Local 1503, constructs formwork at Image Elementary School. (Josh Kulla/91Ƶ)
Erik Halstead, a carpenter with Emerick Construction and member of Local 1503, constructs formwork at Image Elementary School. (Josh Kulla/91Ƶ)
Michael Nottingham of Northwest Framing Systems cuts studs. (Josh Kulla/91Ƶ)
Michael Nottingham of Northwest Framing Systems cuts studs. (Josh Kulla/91Ƶ)
The school's design is from a prototype by LSW Architects that is being used by Evergreen School District on three new elementary schools. (Josh Kulla/91Ƶ)
The school’s design is from a prototype by LSW Architects that is being used by Evergreen School District on three new elementary schools. (Josh Kulla/91Ƶ)
Apprentice carpenter Issac Guerrero, a member of Local 1503 and an employee of Emerick Construction, constructs foundation formwork. (Josh Kulla//91Ƶ)
Apprentice carpenter Issac Guerrero, a member of Local 1503 and an employee of Emerick Construction, constructs foundation formwork. (Josh Kulla//91Ƶ)
Mitchell Cummings frames an exterior wall. (Josh Kulla/91Ƶ)
Mitchell Cummings frames an exterior wall. (Josh Kulla/91Ƶ)
Journeman carpenter Aaron Dobroth of Northwest Framing Systems sheets an exterior wall. (Josh Kulla/91Ƶ)
Journeman carpenter Aaron Dobroth of Northwest Framing Systems sheets an exterior wall. (Josh Kulla/91Ƶ)
Chuck Johnson, carpentry foreman for Emerick Construction and a member of Local 1503, carries a piece of rebar across foundation formwork at Image Elementary. (Josh Kulla/91Ƶ)
Chuck Johnson, carpentry foreman for Emerick Construction and a member of Local 1503, carries a piece of rebar across foundation formwork at Image Elementary. (Josh Kulla/91Ƶ)
Crews are now framing the interior of the classroom wing at Image Elementary. (Josh Kulla/91Ƶ)
Crews are now framing the interior of the classroom wing at Image Elementary. (Josh Kulla/91Ƶ)

The post School builders working through site challenges appeared first on Daily Journal of Commerce.

]]>
School takes shape from prototype design /news/2019/11/25/vancouver-school-takes-shape-prototype-design/ Mon, 25 Nov 2019 21:49:26 +0000 /?p=196737 The new Sifton Elementary under construction in Vancouver, Washington, will be the first of multiple new schools produced from a prototype design by LSW Architects.

The post School takes shape from prototype design appeared first on Daily Journal of Commerce.

]]>
Journeyman carpenter Jeffrey Swift of DSL Builders installs a glulam beam at Sifton Elementary School in Vancouver. (Josh Kulla/91Ƶ)
Journeyman carpenter Jeffrey Swift of installs a glulam beam at Sifton Elementary School in Vancouver. (Josh Kulla/91Ƶ)

in Vancouver, Washington, is putting to work $695 million of bond money approved by voters in February 2018. Dozens of school buildings are being renovated or replaced; one of the first is Sifton Elementary School, in Northeast Vancouver.

General contractor is tackling the $38 million project to replace an existing school built in 1958. The new, two-story, 62,000-square-foot Sifton Elementary will be the first of multiple new schools produced from a prototype design by .

Construction crews broke ground in April. These days, large glulam structural members are being erected for the gymnasium and auditorium, and exterior and interior walls are being framed. Soon, other tradespeople will arrive on site to begin rough-in work, but right now framers are working to get the building roofed and dried in before weather becomes harsher.

Wood framing is being used for the new school.

“It was a judgment call that we made early on in the design process,” senior project manager Dan Bodell said. “Two years ago, construction costs were going nuts. Now, it’s not the same month-to-month creep that was going on; it’s a little more like a three-percent-a-year kind of cost creep. But we had to think: What can we do in the bones of the building to save money? And that’s why we went to wood framing.”

Crews with Salem-based DSL Builders are framing interior walls away from the main building and using a crane to fly them into place.

“Everybody will do some level of pre-fabbing,” Bodell said. “But here it’s all being done on site. At PS 22 they’re framing them in place and standing them up – not building them 100 feet away and swinging them into place. It’s just about different styles.”

“PS 22” is a new school, not yet named, being built by general contractor Contractors on Northeast 162nd Avenue. Meanwhile, a replacement for the existing Image Elementary School is being built by on Northeast 131st Avenue. All three project teams are expected to finish their work by summer 2020, in time for the facilities to open for the 2020-21 school year.

Daniel Ramirez, center, helps fellow DSL Builders carpenters Brian Mickel, left, and Daniel Barnes lower a wall panel into place. (Josh Kulla/91Ƶ)
Daniel Ramirez, center, helps fellow DSL Builders carpenters Brian Mickel, left, and Daniel Barnes lower a wall panel into place. (Josh Kulla/91Ƶ)
The 62,000-square-foot school is the first of multiple campuses to be built from prototype designs by LSW Architects. (Josh Kulla/91Ƶ)
The 62,000-square-foot school is the first of multiple campuses to be built from prototype designs by LSW Architects. (Josh Kulla/91Ƶ)
Carpenter Daniel Barnes, an employee of DSL Builders, secures a wall into place. (Josh Kulla/91Ƶ)
Carpenter Daniel Barnes, an employee of DSL Builders, secures a wall into place. (Josh Kulla/91Ƶ)
Carpenters with DSL Builders guide a wall into place. (Josh Kulla/91Ƶ)
Carpenters with DSL Builders guide a wall into place. (Josh Kulla/91Ƶ)
Journeyman carpenter Chris Samuelson secures a glulam beam in the school's gymnasium. (Josh Kulla/91Ƶ)
Journeyman carpenter Chris Samuelson secures a glulam beam in the school’s gymnasium. (Josh Kulla/91Ƶ)
The new school contains two stories of classroom space throughout, save for a single-story kindergarten wing. (Josh Kulla/91Ƶ)
The new school contains two stories of classroom space throughout, save for a single-story kindergarten wing. (Josh Kulla/91Ƶ)
Journeyman carpenter Daniel Ramirez of DSL Builders takes a measurement as his crew lowers a wall panel into place. (Josh Kulla/91Ƶ)
Journeyman carpenter Daniel Ramirez of DSL Builders takes a measurement as his crew lowers a wall panel into place. (Josh Kulla/91Ƶ)
Framing is under way on the school's gymnasium. (Josh Kulla/91Ƶ)
Framing is under way on the school’s gymnasium. (Josh Kulla/91Ƶ)
Carpenters David Ramirez, top, and Daniel Barnes, both employees of DSL Builders, frame interior walls. (Josh Kulla/91Ƶ)
Carpenters David Ramirez, top, and Daniel Barnes, both employees of DSL Builders, frame interior walls. (Josh Kulla/91Ƶ)
(Josh Kulla/91Ƶ)
(Josh Kulla/91Ƶ)
Carpenters with DSL Builders frame interior walls. (Josh Kulla/91Ƶ)
Carpenters with DSL Builders frame interior walls. (Josh Kulla/91Ƶ)
Brian Mickel, a carpenter with DSL Builders, helps lower a wall panel into place. (Josh Kulla/91Ƶ)
Brian Mickel, a carpenter with DSL Builders, helps lower a wall panel into place. (Josh Kulla/91Ƶ)
Sifton Elementary is one of three new elementary schools being constructed by Evergreen Public Schools that are based on the same prototype design created by LSW Architects. (Josh Kulla/91Ƶ)
Sifton Elementary is one of three new elementary schools being constructed by Evergreen Public Schools that are based on the same prototype design created by LSW Architects. (Josh Kulla/91Ƶ)

The post School takes shape from prototype design appeared first on Daily Journal of Commerce.

]]>
Building toward advancement in education /news/2019/08/01/building-toward-advancement-education/ Thu, 01 Aug 2019 20:00:46 +0000 /?p=192491 Use of a prototype has benefited the design process for an elementary school replacement project in Vancouver, Washington.

The post Building toward advancement in education appeared first on Daily Journal of Commerce.

]]>
Journeyman carpenter Gerardo Carrillo, left, a member of Local 1503 and an employee of Whitaker Ellis, guides the concrete pour while fellow Whitaker Ellis and Local 1503 carpenter Rick Bird stirs the mix with a vibrator. (Josh Kulla/91Ƶ)
Journeyman carpenter Gerardo Carrillo, left, a member of Local 1503 and an employee of Whitaker Ellis, guides the concrete pour while fellow Whitaker Ellis and Local 1503 carpenter Rick Bird stirs the mix with a vibrator. (Josh Kulla/91Ƶ)

The path to construction of a new Sifton Elementary School in Vancouver, Washington, actually started with a massive fire.

That 2013 blaze may have destroyed Crestline Elementary School, but the process to replace the building led officials to select a prototype by . The new school opened barely 18 months later and featured a design that could be used in the future.

Fast-forward to 2018, when voters approved a $695 million capital bond measure – a sizable amount of it for six new elementary schools. Naturally, officials referred to the Crestline project when beginning the new ones, including Sifton.

“It was great because we already had the prototypical design,” said Gail Spolar, communications director for the school district.

is serving as the construction manager and general contractor for the Sifton project, which was designed by LSW Architects. Also, is handling project management duties.

The original Sifton Elementary School, at 7301 N.E. 137th Ave., was built in 1958 as a single-story structure largely with a slab-on-grade foundation and concrete masonry unit (CMU) walls. The replacement structure, with a different footprint on the same property, will feature wood framing over a slab-on-grade foundation. Exposed glulam beams will be used for both practical and aesthetic reasons.

“There are not a lot of exotics in the design itself,” R&C Management Group project manager Dan Bodell said. “There are some design concepts that are more about the teaching methods, but as far as the structure itself we have a one-story gym with administrative on the front and then a two-story classroom wing and the nice views of (Mount Hood).”

Jose Guzman, a journeyman ironworker with Bar M Steel, ties rebar at the Sifton Elementary School project in Vancouver. (Josh Kulla/91Ƶ)
Jose Guzman, a journeyman ironworker with Bar M Steel, ties rebar at the Sifton Elementary School project in Vancouver. (Josh Kulla/91Ƶ)

Although the Crestline design was the basis for the new Sifton facility, improvements have been made, according to Sue Steinbrenner, Evergreen Public Schools’ director of facilities.

“Our other prototype really had the media (center) self-contained within its own room,” she said. “So we put the libraries here front and center so you have to walk through it, which is ironically how a lot of our buildings from the 1970s are.

“It’s about being sensitive to noise issues and having spaces for the students to break out and choose how to interact,” she added. “The other big difference is splitting the commons from the gym so we can use the gym for after-hours activities and close down the academic wing and make it more about the community partnership.”

Bill Wantaja, a journeyman electrician with Prairie Electric, places conduit inside foundation formwork. (Josh Kulla/91Ƶ)
Bill Wantaja, a journeyman electrician with , places conduit inside foundation formwork. (Josh Kulla/91Ƶ)

The new Sifton school will have a capacity of 550 students. A single-story wing will hold the gymnasium and administrative space, along with the media center and commons. A learning stair in the commons area will serve as the bridge to the two-story classroom wing. Outside, a playground area and a soccer field will be built.

The district’s bond program calls for construction to take place through 2025. Currently, three new elementary schools are being built: replacements for Sifton and Image, and a completely new one not yet named.

One advantage of using the same design prototype on those projects, Bodell said, is that representatives of the three general contractors involved – Pence Construction, and Contractors – are meeting regularly to discuss progress and go over any possible hiccups.

“Sifton is a month ahead of the other two and these guys have the most learning curve,” Bodell said. “But they can pass that information on to others. We’re pretty happy – from the R&C standpoint, there’s been great support from the district.”

All three schools under construction are scheduled for delivery in time for the start of the 2020-21 school year.

Nearly half of the footings have been poured for the 62,000-square-foot school. (Josh Kulla/91Ƶ)
Nearly half of the footings have been poured for the 62,000-square-foot school. (Josh Kulla/91Ƶ)
Mark Jones, a journeyman ironworker with Local 29 and an employee of Bar M Steel, ties rebar while constructing a cage for a foundation footing. (Josh Kulla/91Ƶ)
Mark Jones, a journeyman ironworker with Local 29 and an employee of Bar M Steel, ties rebar while constructing a cage for a foundation footing. (Josh Kulla/91Ƶ)
(Josh Kulla/91Ƶ)
(Josh Kulla/91Ƶ)
Seth Soucy, an apprentice carpenter with Local 1503 and an employee of Whitaker Ellis Builders, applies plastic sheeting to the inside of formwork. (Josh Kulla/91Ƶ)
Seth Soucy, an apprentice carpenter with Local 1503 and an employee of Whitaker Ellis Builders, applies plastic sheeting to the inside of formwork. (Josh Kulla/91Ƶ)
The new school will have capacity for 550 students and include a two-story classroom wing and a single-story administrative wing. (Josh Kulla/91Ƶ)
The new school will have capacity for 550 students and include a two-story classroom wing and a single-story administrative wing. (Josh Kulla/91Ƶ)
The new school will replace a 61-year-old building. (Josh Kulla/91Ƶ)
The new school will replace a 61-year-old building. (Josh Kulla/91Ƶ)

The post Building toward advancement in education appeared first on Daily Journal of Commerce.

]]>
Building a solid foundation for learning /news/2019/05/13/building-solid-foundation-learning/ Mon, 13 May 2019 16:11:28 +0000 /?p=188606 Crews in Vancouver, Washington, are working to construct a replacement elementary school.

The post Building a solid foundation for learning appeared first on Daily Journal of Commerce.

]]>
Jeremy Bridger, a journeyman ironworker with Made of Steel, welds a buckling-restrained brace to a vertical steel column Truman Elementary School in Vancouver. (Josh Kulla/91Ƶ)
Jeremy Bridger, a journeyman ironworker with Made of Steel, welds a buckling-restrained brace to a vertical steel column Truman Elementary School in Vancouver. (Josh Kulla/91Ƶ)

will be taking place in Vancouver, Washington, for years to come.

In February 2017, voters approved a $458 million bond measure for . One year later, voters approved a $695 million bond measure for the city’s other school district – .

On Northeast 42nd Avenue, crews are working on one of the Vancouver Public Schools projects – a replacement for Truman Elementary. General contractor is overseeing the effort to erect a two-story building designed by . The new school will sit on the same property as the existing one, but in a different location.

Crews broke ground in January, and work has proceeded quickly. Ironworkers from several companies are erecting structural steel and laying rebar for foundation slabs, while Todd Construction self-performs carpentry.

“We’ve got some of the slab-on-grade foundation down and we’ve started the first section of structural steel,” Todd Construction superintendent Monte Carothers said at the project site last week. “There’s plumbing, electrical underground – everything to do with the foundation. And then as you can see, the ironworkers are there. Next week we’ll have the drywall contractor on-site and he’ll be starting his metal framing in that area.”

Additional slab-on-grade concrete and structural steel work is scheduled, Carothers added.

“The following week we’ll be going vertical in that same area out there,” he said. “It’s fun. Especially when you get to the stage where you’re pouring slabs, it starts changing fairly quickly.”

Zach Salter, an apprentice carpenter with Todd Construction, pours concrete around the base of a vertical steel column. (Josh Kulla/91Ƶ)
Zach Salter, an apprentice carpenter with Todd Construction, pours concrete around the base of a vertical steel column. (Josh Kulla/91Ƶ)
Ironworkers Twith Made of Steel install an angle beam on the roof level of the gymnasium. (Josh Kulla/91Ƶ)
Ironworkers Twith Made of Steel install an angle beam on the roof level of the gymnasium. (Josh Kulla/91Ƶ)
Journeyman carpenter Jeff Lund of Todd Construction constructs formwork for a shear wall. (Josh Kulla/91Ƶ)
Journeyman carpenter Jeff Lund of Todd Construction constructs formwork for a shear wall. (Josh Kulla/91Ƶ)
Apprentice carpenter Toby Sayre of Todd Construction installs a strip of foam weather barrier in preparation for a slab on grade concrete pour. (Josh Kulla/91Ƶ)
Apprentice carpenter Koby Sayre of Todd Construction installs a strip of foam weather barrier in preparation for a slab on grade concrete pour. (Josh Kulla/91Ƶ)
Structural steel framing of the school's gymnasium is now being completed. (Josh Kulla/91Ƶ)
Structural steel framing of the school’s gymnasium is now being completed. (Josh Kulla/91Ƶ)
Zach Salter, an apprentice carpenter with Todd Construction, pours concrete around the base of a vertical steel column. at Truman Elementary School (Josh Kulla/91Ƶ)
Zach Salter, an apprentice carpenter with Todd Construction, pours concrete around the base of a vertical steel column. at Truman Elementary School (Josh Kulla/91Ƶ)
Journeyman ironworker Tyler Roses of Made of Steel installs an angle beam on the roof level of the gymnasium. (Josh Kulla/91Ƶ)
Journeyman ironworker Tyler Roses of Made of Steel installs an angle beam on the roof level of the gymnasium. (Josh Kulla/91Ƶ)
The school will have over 90,000 square feet of floor area spread over two stories. It will replace an older structure that will be demolished next year. (Josh Kulla/91Ƶ)
The school will have over 90,000 square feet of floor area spread over two stories. It will replace an older structure that will be demolished next year. (Josh Kulla/91Ƶ)
Journeyman carpenter James Morrison of Todd Construction places a marker in preparation for a slab-on-grade pour. (Josh Kulla/91Ƶ)
Journeyman carpenter James Morrison of Todd Construction places a marker in preparation for a slab-on-grade pour. (Josh Kulla/91Ƶ)
Zach Wilde, a heavy equipment operator with Nutter Corporation, examines the bucket of his excavator as he backfills soil around an elevator shaft. (Josh Kulla/91Ƶ)
Zach Wilde, a heavy equipment operator with Nutter Corporation, examines the bucket of his excavator as he backfills soil around an elevator shaft. (Josh Kulla/91Ƶ)
Journeyman ironworker Jeremy Bridger of Made of Steel welds a buckling-restrained brace to a vertical steel column. (Josh Kulla/91Ƶ)
Journeyman ironworker Jeremy Bridger of Made of Steel welds a buckling-restrained brace to a vertical steel column. (Josh Kulla/91Ƶ)
Structural steel framing work is under way on the project. (Josh Kulla/91Ƶ)
Structural steel framing work is under way on the project. (Josh Kulla/91Ƶ)
Journeyman carpenters James Morrison, left, and Larry Jones, both of Todd Construction, do preparatory work in advance of a slab pour. (Josh Kulla/91Ƶ)
Journeyman carpenters James Morrison, left, and Larry Jones, both of Todd Construction, do preparatory work in advance of a slab pour. (Josh Kulla/91Ƶ)
Zach Wilde, right, a heavy equipment operator with Nutter Corporation, uses an excavator to backfill soil around an elevator shaft. (Josh Kulla/91Ƶ)
Zach Wilde, right, a heavy equipment operator with Nutter Corporation, uses an excavator to backfill soil around an elevator shaft. (Josh Kulla/91Ƶ)
Journeyman ironworker Jeremy Bridger of Made of Steel welds a buckling-restrained brace to a vertical steel column. (Josh Kulla/91Ƶ)
Journeyman ironworker Jeremy Bridger of Made of Steel welds a buckling-restrained brace to a vertical steel column. (Josh Kulla/91Ƶ)

The post Building a solid foundation for learning appeared first on Daily Journal of Commerce.

]]>
Educational investments taking shape /news/2018/11/15/educational-investments-taking-shape/ Thu, 15 Nov 2018 21:18:00 +0000 /?p=182162 Vancouver Public Schools is putting bond money to work on several sizable construction projects.

The post Educational investments taking shape appeared first on Daily Journal of Commerce.

]]>
Carpenters with DSL Builders frame classroom walls at the Ogden Elementary School project in Vancouver. (Josh Kulla/91Ƶ)
Carpenters with frame classroom walls at the Ogden Elementary School project in Vancouver.

Southwest Washington is abuzz with .

, for instance, has under way multiple projects being for with money from a $458 million bond measure passed by voters in 2017.

On the Washington State University-Vancouver campus, crews are building new space for iTech Preparatory – a STEM (science, technology, engineering and math)-focused magnet school that serves students throughout the district. The school, which opened in 2012, has students in grades 6 through 12; middle school pupils currently attend classes in district administration offices while high school students occupy a leased building on the WSU campus.

“We’ve never had a facility where we could house all the grades at one location,” said Todd Horenstein, an assistant superintendent and director of facility support services for Vancouver Public Schools.

The new building will have approximately 80,000 square feet of space over three stories and be able to serve up to 700 students. of Vancouver designed the facility, which is being built by Hillsboro general contractor .

Tapani Underground crews perform site work at Vancouver Public Schools' iTech Preparatory Academy project. (Josh Kulla/91Ƶ)
crews perform site work at Vancouver Public Schools’ iTech Preparatory Academy project.

The project’s budget is around $30 million, Horenstein said. The building is being constructed to Washington Sustainable Schools Protocol, an energy efficiency process with standards roughly akin to Leadership in Energy and Environmental Design silver, he added.

Currently, site work is under way at one end of the iTech Preparatory site. Meanwhile, ironworkers and carpenters are building formwork and installing rebar in preparation for concrete slab foundation and footer pours.

On Northeast 28th Street in Vancouver, ground was broken this past summer on a replacement for Peter S. Ogden Elementary School. LSW Architects and Robinson Construction are handling this project as well.

The two-story building will be wood-framed over slab-on-grade foundations. It will be able to accommodate as many as about 500 students.

Foundation work already is complete. Currently, first-floor walls, both on the interior and exterior, are being built and placed by crews from DSL Framing.

Meanwhile, on MacArthur Boulevard, two schools are being built anew. Marshall Elementary School and McLoughlin Middle School will be constructed as a single two-story structure on open land between existing facilities.

Carpenters with Skanska USA Building construct formwork for the new Marshall Elementary School in Vancouver.
Carpenters with construct formwork for the new Marshall Elementary School in Vancouver.

The two schools will be physically connected by a shared kitchen and mechanical space, as well as a media center able to be partitioned. However, each school will function separately, Horenstein said.

LSW Architects designed this project too, but Skanska USA Building is the general contractor for this project. Currently, crews from Tapani Underground, Skanska and are carrying out site work, underground utility installation and form work for upcoming foundation concrete pours.

Instead of standard steel or wood framing, however, cross-laminated timber structural elements will be used atop a concrete foundation. This will be one of the first educational buildings in the Portland-metro area to feature such construction.

, another school district in Vancouver, also has projects on tap. Voters in February approved a $695 million bond measure. Numerous construction projects totaling more than $800 million will be completed by 2024, according to the district’s website.

CJ Barton, a journeymen ironworker with Local 29 and an employee of SI Contracting, lays out rebar for foundation formwork at the iTech Preparatory Academy site.
CJ Barton, a journeymen ironworker with Local 29 and an employee of SI Contracting, lays out rebar for foundation formwork at the iTech Preparatory Academy site.
Carpenters Collin O'Connell, left, and David Ramirez, both employees of DSL Builders, frame walls for the new Ogden Elementary School.
Carpenters Collin O’Connell, left, and David Ramirez, both employees of DSL Builders, frame walls for the new Ogden Elementary School.
The new Ogden Elementary School will feature slab-on-grade foundations with two stories of wood-framed office and educational space.
The new Ogden Elementary School will feature slab-on-grade foundations with two stories of wood-framed office and educational space.
Excavation crews with Tapani Underground perform site work at the new iTech Preparatory Academy in Vancouver.
Excavation crews with Tapani Underground perform site work at the new iTech Preparatory Academy in Vancouver.
SI Contracting employees and Ironworkers Local 29 members Ryan Boyer, foreground, and CJ Barton install rebar at the iTech Preparatory Academy site. (Josh Kulla/91Ƶ)
SI Contracting employees and Ironworkers Local 29 members Ryan Boyer, foreground, and CJ Barton install rebar at the iTech Preparatory Academy site.
Tapani Underground employees work at the Ogden Elementary School project in Vancouver.
Tapani Underground employees work at the Ogden Elementary School project in Vancouver.
Carpenters with DSL Builders, from left, Daniel Barnes, Ken Jennings and Chris Johnson build classroom walls at the Ogden Elementary School project in Vancouver.
Carpenters with DSL Builders, from left, Daniel Barnes, Ken Jennings and Chris Johnson build classroom walls at the Ogden Elementary School project in Vancouver.
Mike Smith, a heavy equipment operator with Tapani Underground, works at the iTech Prepatory School site in Vancouver.
Mike Smith, a heavy equipment operator with Tapani Underground, works at the iTech Prepatory School site in Vancouver.
Collin O'Connell, a carpenter with DSL Builders, frames a wall at Ogden Elementary School.
Collin O’Connell, a carpenter with DSL Builders, frames a wall at Ogden Elementary School.
The new iTech Preparatory Academy is one of four new schools currently under construction in the Vancouver Public Schools district.
The new iTech Preparatory Academy is one of four new schools currently under construction in the Vancouver Public Schools district.
Ogden Elementary School is one of four bond-funded campuses being constructed by Vancouver Public Schools.
Ogden Elementary School is one of four bond-funded campuses being constructed by Vancouver Public Schools.

The post Educational investments taking shape appeared first on Daily Journal of Commerce.

]]>
Washington school districts poised to start building /news/2018/02/15/washington-school-districts-poised-to-start-building/ Thu, 15 Feb 2018 23:48:46 +0000 /?p=172349 A $695 million bond measure to pay for construction of nine schools for Evergreen Public Schools has passed, according to preliminary election results in Washington.

The post Washington school districts poised to start building appeared first on Daily Journal of Commerce.

]]>

A $695 million bond measure to pay for construction of nine schools for has passed, according to preliminary election results in Washington.

Approximately 61 percent of voters approved the bond measure, according to the Elections office. In Washington, a 60 percent supermajority is required to pass school bonds.

The general obligation bonds will fund construction of a new elementary school and replacements for five elementary schools, a middle school and two high schools with new buildings at existing campuses. Other schools will receive various renovations and improvements.

“The voters have placed great confidence in the district by approving the largest bond in the community’s history,” Evergreen Public Schools Board President Todd Yuzuriha stated in a news release. “When combined with anticipated state matching funds and locally collected impact fees, more than $800 million in school projects will be completed over the next six years. Thank you to the community for your incredible support.”

The Evergreen Public Schools projects are scheduled to be completed by 2024. of Vancouver is serving as design consultant.

Two other major school district bonds were on Tuesday’s ballot in Clark County. La Center School District voters comfortably approved a $48 million bond measure for construction of a new middle school, conversion of the existing La Center Middle School into an elementary school and land acquisition. The bond passed with 65.61 percent of votes in favor.

However, Battle Ground voters rejected a $225 million bond measure that would have funded construction of six schools as well as other renovations and improvements to accommodate growth. With only 58.34 percent of votes in favor, the supermajority requirement was not met.

Final results will be certified on Feb. 23.

The post Washington school districts poised to start building appeared first on Daily Journal of Commerce.

]]>