91ÊÓÆµ

Shifting bridge parts raise flag for ODOT

By: Nathalie Weinstein//June 17, 2010//

Shifting bridge parts raise flag for ODOT

Nathalie Weinstein//June 17, 2010//

Listen to this article
(Photo courtesy of ODOT)

U.S. Route 20: Pioneer Mountain to Eddyville project time line

Summer 2005 ODOT signs a contract with Yaquina River Constructors and Granite Construction. Total project cost is estimated at $150 million. Completion is projected for 2009.

May 2007 Oregon’s Department of Environmental Quality fines ODOT and general contractor Granite Construction for water quality violations related to project construction.

Sept. 2007 ODOT suspends work for a year to complete a geotechnical inspection, re-engineer the project alignment and find inexpensive ways to control erosion.

June 2008 Work resumes on the project.

Feb. 2010 Concrete bridge columns at two bridges constructed for the project are found to be shifting.

June 2010 All bridge work for the project is put on hold while engineer URS Corp. identifies the cause of the column shifting.

An Oregon Department of Transportation highway safety improvement project in Lincoln County is facing delays because of shifting highway bridge columns.

In February, several bridge columns constructed for the U.S. Route 20-Pioneer Mountain to Eddyville project were discovered to be tilting. Now, all bridge construction is on hold while engineer of record URS Corp. identifies the problem. ODOT project manager Joe Squire said that while road construction on the project will continue on schedule, the delay in bridge construction could push the project’s completion date into next summer.

Six of 10 highway bridges planned for the project have already been built, Squire said. Tilting columns were found at two of the constructed bridges. Work on the four remaining bridges will be put on hold until results come back from URS Corp.

“Our work season on the coast is so short for earthwork because of the rain,” Squire said. “If we need to do slide mitigation as a result of these columns shifting, the project could spill into next year. We only have 90 to 100 working days during the summer because we can’t do the work in winter conditions.”

URS Corp. plans to use slope inclinometers at the site to see how far the columns have shifted in the ground, according to Dan Meier, engineer and geologist with URS Corp. The tool will reveal the amount of movement that occurred as well as where the columns are moving.

“It’s a watch-and-see sort of thing,” Meier said. “This is a challenging project with challenging terrain. The cause of the shifting is an unknown at this point.”

Though Squire said it is too soon to point the finger at any one cause for the shifting, he said the project team’s calculations failed to take into account the impact of landslides that have occurred around the bridges’ columns. The design-build project is a joint venture between California firm Granite Construction and Yaquina River Constructors of Eddyville.

It’s also possible that engineers did not account for lateral loads, such as cars crossing over the bridge, Squire added.

“As the engineer of record, URS Corp. (is) responsible under (its) contract to provide a viable design and constructable project,” Squire said. “ODOT cannot accept this project unit it is 100 percent built out. It looks like URS Corp. has pulled in the best folks on the West Coast, including TY Lin International, to get this solved.”

The U.S. 20 project has faced numerous problems since work began in 2005. In June 2007, massive landslides on land clear-cut for the project led ODOT to delay the project for a year to re-engineer the project’s alignment and find better ways to control erosion. Then, in September 2007, general contractor Granite Construction was fined by the Oregon Department of Environmental Quality for 41 water quality violations due to improper erosion controls.

The project’s budget, which was $150 million in 2007, has since ballooned to $215 million due to extra earthwork and environmental remediation projects. ODOT public information officer Rick Little said there are no estimates for the length of the delay or the added costs that could result from the shifting columns.



News

See All News

Commentary

See All Commentary

COMMUNITY CALENDAR