Housed on Hewlett-Packard鈥檚 Corvallis campus, the Oregon Nanoscience and Microtechnoogies Institute at Oregon State University features 14 new research labs for the development of cutting-edge technology.

Project team + Stats

Location: Corvallis, Oregon
Cost: $7.47 million
Start Date: April 2009
Completion Date: August 2010
Owner/Developer: Oregon State University Facilities Services
Architect: IDC Architects
Engineer: IDC Architects
General Contractor: Andersen Construction

The lab has a large number of users with diverse needs, so the building features a modular and extremely flexible lab layout. 鈥淎ll of the shelving fits under the tables, so basically you can reorganize the lab to be any way you want,鈥 said Tucker Bowman, project engineer for Andersen Construction.

The work included a 14,500-square-foot development laboratory, 10,000 square feet of laboratory technology spaces and a new 6,700-square-foot classroom, and other new lab spaces.

During construction, the project team realized that excessive concrete moisture in the 18-year-old building鈥檚 original concrete slabs might cause warranty problems with rubber flooring聽 in the laboratories. IDC Architects, Andersen Construction and OSU collaborated to solve the problem by applying a surface vapor barrier that sealed all moisture issues.

Despite these challenges, the project was completed under budget and on schedule.