A 25-million-gallon underground concrete reservoir under construction in Southeast Portland is slated to go online this spring. Hoffman Construction is the contractor on the Portland Water Bureau’s $90 million project, which replaces a 10-million-gallon steel tank formerly at the site.

Work on the project began in late 2012 with the demolition of the 43-year-old tank. Following the demolition, nearly a year of excavation at the site took place, while concrete for the reservoir began being poured in fall of 2013.

Around 2,000 truckloads of concrete were brought in to pour a total of 266 squares, each measuring 20 feet by 20 feet. The squares were poured in a checkerboard pattern to control shrinkage cracking. The reservoir’s walls, roof, and 252 support columns were completed in summer 2014.

Backfilling around the sides of the reservoir began last fall, and continues with the installation of mechanically stabilized earth walls. The reservoir will begin operations after being disinfected and commissioned. Work at the site will continue with construction of access roads, fencing, landscaping and mitigation plantings. Total completion of the project is slated for this fall.

The reservoir is comprised of two cells, each with a 12.5 million gallon capacity. Both cells together measure approximatedly 400 by 300 feet, with a total of 252 support columns.
The reservoir is comprised of two cells, each with a 12.5 million gallon capacity. Both cells together measure approximatedly 400 by 300 feet, with a total of 252 support columns.
Engineered fill is dumped as crews backfill areas around the reservoir walls.
Engineered fill is dumped as crews backfill areas around the reservoir walls.
A total of five mechanically stabilized earth walls are being installed around the perimeter of the reservoir.
A total of five mechanically stabilized earth walls are being installed around the perimeter of the reservoir.
The reservoir's concrete roof is covered with hot-applied waterproofing membrane, upon which a layer of drain rock, which will then be covered with two feet of soil.
The reservoir’s concrete roof is covered with hot-applied waterproofing membrane, upon which a layer of drain rock, which will then be covered with two feet of soil.
One of the reservoir's approximately 200-by-300-foot cells is nearly filled with water while undergoing testing.
One of the reservoir’s approximately 200-by-300-foot cells is nearly filled with water while undergoing testing.
Landscapers with Native Ecosystems Northwest plant vegetation on a mechanically stabilized earth wall.
Landscapers with Native Ecosystems Northwest plant vegetation on a mechanically stabilized earth wall.
A pair of 48-inch inlet, left, and outlet pipes in the reservoir's south meter vault move water to and from the Water Bureau's Conduit 3, which runs under nearby Southeast Powell Boulevard.
A pair of 48-inch inlet, left, and outlet pipes in the reservoir’s south meter vault move water to and from the Water Bureau’s Conduit 3, which runs under nearby Southeast Powell Boulevard.
An overflow detention basin, constructed with soldier pile and shotcrete, has a 650,000-gallon capacity. In the unlikely event of a reservoir overflow, water held in the basin would flow to a stormwater pond, which then discharges into the storm system.
An overflow detention basin, constructed with soldier pile and shotcrete, has a 650,000-gallon capacity. In the unlikely event of a reservoir overflow, water held in the basin would flow to a stormwater pond, which then discharges into the storm system.
A stormwater detention basin will be planted with vegetation and slow the amount of surface runoff into the stormwater system.