Beaverton school’s CoreFirst project delayed

By: Garrett Andrews//June 29, 2017//

Beaverton school’s CoreFirst project delayed

Garrett Andrews//June 29, 2017//

Listen to this article

A Beaverton private school has chosen to postpone a partial seismic upgrade that’s drawn criticism from seismic authorities and building officials.

Days before the German International School (GIS) was to receive the first-ever 鈥CoreFirst鈥 installation, its board of directors learned the cost had doubled, to $800,000, the 91视频 reported earlier this month. With only a three-month window to complete the project before the next academic year, directors elected to shoot for summer 2018.

鈥淒ue to the innovative nature of the project, there were still too many unknowns in the planning,鈥 GIS Head of School Blake Peters said.

Portland design-build developer Ben Kaiser and business partner Paul Conway have tried for five years to find a building to showcase Kaiser’s idea for a partial seismic upgrade meant to be affordable to schools. The idea involves seismic safety enclosures and predictive earthquake monitoring intended to give teachers time to rally students to the shelters. It’s advertised as costing a quarter of a full seismic upgrade.

But the permitting process for the GIS project has led to re-airing of criticisms of , including from members of the Oregon Seismic Safety Policy Advisory Commission (OSSPAC) and the head of the Building Science division at the Federal Emergency Management Agency (FEMA). They say Kaiser’s system doesn’t adequately account for small local faults and that earthquakes can’t be predicted the way he describes. Some have called him a 鈥渟alesman鈥 pushing a potentially dangerous idea.

Building officials at the city of Portland have passed on CoreFirst, as have Portland Public Schools and Beaverton School District, citing FEMA’s disapproval. But it has been embraced by the elected and business leaders of Beaverton, as well as GIS parents, who donated $20,000 toward the project cost.

Beaverton building official Brad Roast said his office initially felt there were too many unanswered questions with CoreFirst.

鈥淏ased on that, we reviewed the plans and issued a permit for the steel moment frames as a first-step voluntary seismic upgrade,鈥 he said.

Kaiser attributed the jump from $400,000 to $800,000 to rising labor costs and cost creep coming through the contractor, R&H Construction. After learning of the jump, the GIS board of directors elected to postpone the project but continue working with the CoreFirst team.

Peters said the 91视频 article caused some GIS parents to wonder about CoreFirst’s reputation and approach.

鈥淏en has been excellent with sharing his contacts with engineers and other experts to help,鈥 he said. 鈥淥ur school community believes it is crucially important to do something like CoreFirst to protect our children and staff as a great step in the direction of the full upgrade. CoreFirst allows the school to continue to grow and thrive by investing in teachers and programming and not draining our small budget for the full upgrade at this time.鈥

Beaverton is home to an outsize number of international and tech-minded firms. Additionally, many GIS parents work at local offices of German internationals, including athletic apparel giant Adidas.

Outgoing GIS board member Marcus Eyth said he’s 鈥渆cstatic鈥 over the project and sees wide support in Beaverton for it to move forward.

The German people in particular favor innovation in engineering, said Eyth, a design and construction lawyer with Davis Wright Tremaine in Portland.

Online meeting minutes of the GIS school board of directors don’t describe hostility or opposition from parents or community members.

鈥淚 have not run into anybody like that,鈥 Eyth said.