The normally bustling OHSU Center for Health and Healing South project in Portland’s South Waterfront District was much quieter than usual on Aug. 21, when Hoffman Construction mostly shut down the site for the day due to safety and material delivery concerns brought about by the solar eclipse.
A crew of about 15 workers were the only tradespeople on site at the two-building project. They were brought in to stress concrete that was poured the previous Thursday and jump concrete forms on the Rood Family Pavilion building, which will include parking and patient guest housing. The critical path work prevented the project team from losing a week on the schedule.
The site was cleared at around 10 a.m. as the eclipse began. Crews broke for an early lunch, and others from the project’s co-location office on site wandered outside to take in the event.