OP-ED: A new era of delegated design: more risk, less certainty

By: Roger Lenneberg//February 23, 2018//

OP-ED: A new era of delegated design: more risk, less certainty

Roger Lenneberg//February 23, 2018//

Listen to this article
Roger Lenneberg
Roger Lenneberg

It is old news that construction is all about time and managing risk. The contracting parties have always used contracts to allocate the risks of unexpected costs associated with construction.

Historically, an owner would hire a design professional who furnished plans and specifications to the contractors who 鈥渂uilt per plans and specs.鈥 Through the contracting process, the price for the work shown on the plans was agreed upon and the risk of loss for over-budget costs and cost overruns was transferred to the subcontractor by holding it responsible for the 鈥渕eans, methods and costs associated with the contractor鈥檚 scope鈥 as long as the design did not change.

For example, a framing contractor was always responsible for planning and staffing its work, purchasing the supplies, and completing the work required on time. If it cost more than expected, the subcontractor paid the difference under traditional 鈥渂id build鈥 contracts.

Things have changed

More and more often subcontractors and contractors, in the private sector, get a contract by submitting proposals for partially designed scope of work at an agreed price. Depending on the project or the designers, the extent of undersigned detail and loosely defined criteria can be small or extensive and 鈥渄elegated design鈥 is born. Of course, the devil is in the details. While it is easy to overlook the significance of this change when pricing the work, delegated design changes the allocation of risk, making the subcontractor the designer.

What is delegated design? It鈥檚 the transfer of responsibility, and all associated risk, for the design of a component system or element of a project to someone other than聽an architect or engineer or design professional of record. In other words, delegated design focuses on specialty systems and is similar to design-build, but, as applied, transfers far more risk to the subcontractor.

The contract does not specify delegated design

Contracts rarely use the term delegated design, and a contractor needs to pay careful attention to understand the scope of delegation. Typically, the provisions that describe delegated design include phrases like 鈥渟cope of work includes design, delivery and installation of a functioning building system, consistent with the intent of the contract documents. Subcontractor鈥檚 proposal includes construction details and specifications omitted, or not shown, but inferable from or necessary for, a fully integrated system, compliant with local building codes and all other building systems.鈥 In other words, the plans and specs are not final, may or may not be complete, and may or may not represent the expectations of the owner. Nonetheless, cost of completing the design both on paper and for the project is included in the price.

Six tips for limiting delegated design risk

Delegated design and related concepts are here to stay and the risks cannot be eliminated. However, there are certain questions or requests that can limit or expose the extent of the risk:

1. Review all design documents for completeness before聽submitting a price. You can only accurately price what you know.

2. Limit the scope of design duties to design services 鈥渢ypically performed by trade contractors鈥 or list the design duties specifically.

3. Exclude design interface with other building systems installed by other trades.

4. Verify that insurance includes coverage for professional and design services.

5. Require all design documents that must be stamped are also stamped by the designer of record for the project.

6. Exclude design of aesthetic elements.

Roger Lenneberg is an attorney and chairman of Jordan Ramis PC鈥檚 construction law team. He previously worked as an arbitrator, mediator and in-house counsel for a national subcontractor and developer. Contact him at 503-598-5585 or [email protected].