scott.huish//May 21, 2019//

Location: Portland
Cost: $5.6 million
Start Date: July 2017
Completion Date: May 2018
Owner/Developer: The Portland Plaza
Architect: Opsis Architecture
Engineer: catena consulting engineers
General Contractor: Andersen Construction
The new system was selected to not only stop all of the leakage into the parking garage, but also because it was compatible with the adhesion system used when the original waterproofing was laid down nearly 50 years before.
With completion of the $5.6 million project, residents now enjoy new floating concrete planters, rolled glass canopies, a fire table, a water feature, elevated pavers, built-in barbeques and a new swimming pool.
Among the project’s challenges, once the new waterproofing membrane was installed, the next step was to eliminate membrane penetrations to protect the integrity of the waterproofing system. This obstacle drove the choice to have all of the concrete planters floating on top of the waterproofing system to avoid membrane tears.
In addition, the Portland Plaza takes up the entire city block between Southwest Fourth and Fifth avenues, and neither of those streets could be closed during construction. The entry to the podium deck had to be completely demolished so that the waterproofing and podium deck projects could be constructed, as access from the intersections was unavailable through the city.
The project took place completely outdoors during a particularly wet winter and spring, affecting concrete pours and installations. The weather, however, didn’t slow the building process due to a strategic schedule.