91ÊÓÆµ

Top 5 Pointers for Documenting Change Orders

By: scott.huish//March 6, 2020//

Top 5 Pointers for Documenting Change Orders

scott.huish//March 6, 2020//

Listen to this article

Top 5 Pointers for Documenting Change Orders


By James Walker & Ryan C. Hall
Miller Nash Graham & Dunn LLP

Change orders are effective tools that provide flexibility to both the contractor and the owner and are generally unavoidable on a project, no matter how much time is spent designing, planning, and drafting. Nonetheless, despite their critical role, change orders typically do not garner the level of attention and detail that they should. Failure to obtain a properly executed change order may preclude a contractor from getting paid for the work it performed on a project. Furthermore, if litigation or arbitration later arises, disputed change orders can have drastic impacts on the resolution of claims, often to the benefit of the owner. The following pointers, if implemented, will assist any contractor’s pursuit of appropriate compensation for work it performs in response to project changes.

1. Carefully evaluate each proposed change order to verify that all material terms are included.
Since a change order operates as a written modification to the construction contract, ensuring that each material term of the change is included in the order is vital. A change order should at least contain the names of the parties, the date of the order, a unique number identifying the change order, a reference to the project and/or contract, a detailed narrative description of the change in the scope of work, the amount by which the contract price is to be adjusted, and a description of the impact on the construction schedule.

The most frequently forgotten change order detail is the amount of time by which the change order will adjust the construction schedule. Every change order should explicitly address whether the adjustments to a contractor’s or subcontractor’s scope of work will result in an increase, a decrease, or no change to the date of substantial completion. Documenting impacts to the critical path in response to every change reduces the likelihood of delay claims as the project approaches completion.

Alignment among the contract parties on schedule impacts can also provide additional clarity on the cost of certain changes. If, for example, a project owner’s addition to the project scope results in an extension of the substantial completion date, then the contractor should incorporate the costs of that time extension into the change order (e.g., temporary utilities, trailers, insurance).

2. Submit a change order in accordance with the respective notice provisions of the contract.
Construction contracts typically address the procedural requirements for obtaining an executed change order. For example, the standard general terms and conditions between owners and general contractors produced by the American Institute of Architects requires contractor claims for additional compensation to be submitted at least 21 days before performing the work that is subject to the claim (see AIA Document A201-2017 Section 15.1.5).

In addition to timely submitting a change order request, a contractor should review the contract and verify that the request (a) is presented in the form required by the contract, if any; (b) contains each term that the contract requires to be included; (c) is being transmitted to the appropriate individual or entity; and (d) is being sent to that individual or entity through an approved method of communication. A contractor’s failure to strictly adhere to the relevant contract provisions may be used by the owner as a defense against later claims for payment.

3. Confirm that the appropriate representative of the owner signs the change order.
Properly submitting a change order to the owner or its representative is just the first step in obtaining a duly executed change order. The contractor should also proactively follow up with the owner or owner’s representative at regularly scheduled intervals to make sure that the change order is signed and returned to the contractor. Often, the change order provisions within the construction contract will delineate who has the authority to execute a change order on behalf of the owner, so the contractor should confirm that the individual who signed the change order has the requisite authority to approve it.

Contractors will sometimes settle for an e-mail communication approving a change order. This is ill-advised. An e-mail confirmation will likely be insufficient if the express language of the contract requires a formal, executed change order, as is usually the case.

4. Reserve rights to recover anticipated subsequent costs.
Some contracts will attempt to prohibit contractors or subcontractors from claiming additional costs by including a representation that the signed change order is a final settlement of all changed work. Although this may be appropriate in some instances, contractors and subcontractors should be cautious and reserve the ability to recover additional costs when the work must proceed but the total cost impact is unknown. For example, the additional cost for an HVAC subcontractor to reroute ductwork may be known when a change order is executed. But the impacts on the electrician or plumber may not be known at the time. Adding language to the change order that reserves the contractor’s rights to receive additional compensation for other impacted trades could be essential to the contractor recouping those costs.

5. If the change order is rejected, follow the appeal remedies within the contract.
If an owner or owner’s representative rejects a proposed change order, the contractor should review any contractual provisions relating to claims or dispute procedures so that it can adequately appeal the rejection. Construction contracts usually establish a set time within which a contractor must initiate a claim, and the contractor’s failure to ascertain and comply with these deadlines may cause the contractor’s claim to be time-barred. The contractor should also double-check that it satisfies any other requirements for initiating a claim, including but not limited to any requirements dictating where the claim is to be sent, how the claim is to be sent, or what information is required to substantiate the claim.

Change orders are an inescapable aspect of construction projects. But a contractor can reduce the possibility of incurring unreimbursed costs by implementing these tips.

James Walker is a partner with Miller Nash Graham & Dunn. He focuses his transactional practice on construction, real estate, and general business law. James can be reached by phone at 503-205-2353 or by e-mail at [email protected].

Ryan C. Hall is a construction attorney with Miller Nash Graham & Dunn. He focuses his practice on commercial construction litigation and also has experience with both transactional and general business matters. Ryan can be reached by phone at 503-205-2394 or by e-mail at [email protected].

ÌýÌýÌýÌýÌýÌý



News

See All News

Commentary

See All Commentary

COMMUNITY CALENDAR