Oregon Conservation Center
Submitting Company: Lease Crutcher Lewis
Location: Portland
Cost: $5.6 million
Start Date: April 2018
Completion Date: January 2019
Owner/Developer: Project^
Architect: Lever Architecture
Engineer: KPFF
Additional Engineering Firms: American Heating, Cosco Fire, Capitol Electric
General Contractor: Lease Crutcher Lewis
Subcontractors:Aftermath Post Construction, Arctic Sheet Metal, Artek, Bar M Steel, Buffalo Welding, Cascade Acoustics, Cash’s Drapery, Dallas Glass, Don Burke Excavation & Construction, Dr Johnson Wood Innovations, Green Earth Landscaping, Interior Technology, Ironmark, I & H Construction, Kodiak Pacific Construction, LaRusso Concrete, Mid-Valley Glass & Millwork, Ness & Campbell Crane, Northwest Scaffold Services, Pavement Protectors, Resource Maintenance & Flooring, Sawtooth Caulking, Sierra Pacific Windows, Snyder Roofing of Oregon, Spectrum Interiors, Standard TV & Appliance, Sustainable Northwest Wood, ThyssenKrupp Elevator, Ultra Quiet Floors, W.E. Given Contracting