Modern Times Brewery – The Belmont Fermentorium – 1st Place (Tenant Improvement)

By: scott.huish//December 13, 2020//

Modern Times Brewery – The Belmont Fermentorium – 1st Place (Tenant Improvement)

scott.huish//December 13, 2020//

Listen to this article

Tenant Improvement
Modern Times Brewery – The Belmont Fermentorium
Submitting Companies: Woodblock Architecture and Deacon Construction

Location: Portland
Cost: $3.75 million
Start Date: December 2017
Completion Date: October 2019
Owner/Developer: Day Management Corporation
Architect: Woodblock Architecture
Engineer: VLMK Engineering and Design
ractor: Deacon Construction
Submitting Companies: Woodblock Architecture and Deacon Construction
Subcontractors: A Cut Above Concrete Cutting, Anderson Sandblasting, BrandSafway Services, Baxter & Flaming Industries, Brix Paving Northwest, Building Material Specialties, Christenson Electric, Concrete Forming & Placing, Cornerstone Janitorial Services, D&F Plumbing, Dallas Glass, Demolition Contractors, Duke Construction & Excavation, Dynamic RFS Construction, Eagles View Construction II, Eagle Striping Services, Fireside Contracting Services, Frontier Roofing & Construction, Gregory Law Landscape, Insulation Contractors, IRS Environmental of Portland, JC Riverside Manufacturing, Johns Manville Roofing, Mill Creek Heating, NorthStar Electrical Contractors, Old Mill Cabinets & Millwork, Overhead Door Co. of Salem, Pacific Decorative Concrete, PMSI, Portland Masonry, Portland Sheet Metal Works, Purespace, River City Painting, RMC Masonry, Sawtook Caulking, Schindler Elevator, Special T Construction, Spectra Contract Flooring, Sprinkit Fire Protection, SR Contractors, TerraCalc Land Surveying, Trojan Wall Products, United Site Services of Nevada

This year’s top project in the Tenant Improvement category involves not one, but two different buildings in Southeast Portland’s Belmont neighborhood that together epitomize New Portland.

Woodblock Architecture performed design work and Deacon Construction was the general contractor for the renovation and seismic retrofit of two old warehouse buildings that now host a brewery, tap room, restaurant and roof deck for the San Diego-based Modern Times Brewery. Using new technology alongside established techniques, the project team combined the two spaces into a single 20,000-square-foot facility.

It began with the planned renovation of a former warehouse located at the corner of Southeast Sixth Avenue and Belmont Street.

“Partway through that process they threw a wildcard and said ‘Oh, by the way, we’re going to lease the adjacent building, is this killing the project?’” said Brian Peters, a principal at Woodblock Architecture. “‘It’s an existing brewery, and we’re going to take over the space, and with two 10,000-square-foot spaces, we’ll have room.’ It’s rare to have one tenant in two buildings with two different landlords.”

The project team adapted on the fly and made it work seamlessly. Shell scope of work consisted of a 20,000-square-foot full seismic upgrade, full build-out of a new 1,800-square-foot rooftop patio and penthouse accessed by a cable-suspended master stairway overlooking the tasting room and 35-tap bar below.

“We ended up using a portion of an existing skylight, enlarging it and used it to get people up to the top,” Peters said. “That’s one of my favorite parts. It’s a huge part of the circulation.”

The original plan was to renovate an existing 19th century vintage warehouse. But because the neighboring structure happened to already house a brewery, Modern Times decided to lease that building as well and incorporate it into the project. It worked like a charm. And while more work would be needed to fully incorporate the two buildings into a single cohesive space, the groundwork has already been laid.

“Being able to take advantage of the large volume and all of the exposed beams is really great,” Peters said. “And in a future phase, to create a penetration and connection between the two buildings, we’ll need a fire shutter and controls on both sides. But for daily operations it would be open and would allow more ability to move product between the two buildings.”

To connect the two buildings the project team utilized a new type of material, SR Foam from SR Contractors that acts as a structural adhesive to form a structural anchorage.

The wall of the old warehouse was originally constructed out of terra cotta. This had to be steam cleaned to remove any old paint and allow the SR foam to adhere to the wall properly. In the meantime, while foam was sprayed into a void space next to a wood shear wall, a new concrete masonry unit wall had to be built as the existing roof was attached to the adjacent building’s exterior wall – where no wall had previously existed.