OP-ED: Benefits and risks of involving a project’s contractor in the design

By: Karl Oles//March 18, 2021//

OP-ED: Benefits and risks of involving a project’s contractor in the design

Karl Oles//March 18, 2021//

Listen to this article
Karl Oles
Karl Oles

The roles of designers and contractors are being combined for more and more construction projects. This approach has benefits, but it also creates risks.

One traditional method of project delivery is called 鈥渄esign-bid-build.鈥 The owner retains an architect to prepare a design, and then it retains a contractor to build according to that design. This method is well-suited for public projects in which multiple contractors are solicited to bid based on a completed design.

An alternative method is for the owner to hire a contractor (a 鈥渃onstruction manager鈥 or 鈥淐M鈥) during design development to provide advice about constructability, budget and schedule. The CM enlists major subcontractors at this early stage to collect information about preferred design details and probable cost. This CM method is intended to align the contractor with the designer to reduce claims based on design defects, and it can result in a more informed budget and schedule than design-bid-build.

A third method is called 鈥渄esign-build.鈥 The owner hires a contractor/designer team, provides performance requirements for the project, and allows the team freedom to design and build the project to meet the stated requirements. In this method, the contractor and designer are closely aligned, which should limit claims of design defect, and work on the project can begin while the design is being developed. This method can work well for infrastructure or industrial projects in which technical performance is more important than appearance or amenities.

The foregoing methods are not exclusive. Different projects may include different roles for owner, designer and contractor. In design-bid-build, it is common to leave the design details for mechanical, electrical and plumbing as well as fire protection systems to specialized subcontractors. On the other hand, even in design-build the owner may retain control over certain design aspects.

Each method of project delivery offers advantages. However, involving the contractor in design, as happens in CM and design-build, can create risks. A project participant may fail to understand and carry out its responsibilities. For example, a contractor hired for a CM project may lack experience in pricing a developing design or analyzing it for constructability. A CM project architect may not realize what is involved in working with a CM and may defer to its preferences. An inexperienced owner on a design-build project may be tempted to intrude into design decisions without recognizing that by directing design matters it is incurring risk.

Because of the various ways that owners, designers and contractors can interact, it is important to have a clear understanding about each party鈥檚 responsibilities and to express that understanding in clearly written contracts.

In design-bid-build, the responsibility for design rests entirely (or mostly) on one party 鈥 the designer. In the CM and design-build methods, the responsibility for design is shared, so there can be misunderstandings about who is doing what, particularly when multiple parties have contributed to design decisions.

On a CM project, for example, suppose the owner wants the exterior of the building to have a series of attractive planter boxes. The architect may depict those boxes on the plans, expecting the contractor to detail them. But the contractor may say, 鈥淲ait; those boxes could be heavy and they need to drain. The architect needs to figure out how to support them structurally and where the drains should run.鈥 On a design-build project, the owner may specify that the structure must meet the seismic code but then reject the design-build team鈥檚 analysis of how the code applies and require significant design changes 鈥 thus causing a delay.

The best protection against these risks is design coordination, which begins with a clear understanding of roles and responsibilities and continues with open communication. On CM and design-build projects, the contractor and designer must work together to detect and resolve problems and conflicts.

The contractor鈥檚 role is particularly important. During the design phase, it should be preparing a comprehensive plan for constructing the project. This includes identifying work packages for subcontractors, ordering long-lead materials, and preparing a cost-loaded schedule so that critical activities can be identified and tracked. Having this constructability focus informs the contractor鈥檚 comments on the developing design and gives the owner early notice of issues that may involve a trade-off between project quality, on the one hand, and budget and schedule on the other.

To reap the benefits of getting the contractor involved in design, provide for and recognize the risks.

Karl Oles is a Stoel Rives LLP partner and a member of its construction and design practice group. Contact him at 206-386-7535 or [email protected].

The opinions, beliefs and viewpoints expressed in the preceding commentary are those of the author and do not necessarily reflect the opinions, beliefs and viewpoints of the Daily Journal of Commerce or its editors. Neither the author nor the 91视频 guarantees the accuracy or completeness of any information published herein.