91ÊÓÆµ Staff//September 16, 2022//
A weekly compilation of the largest winning bids in the Pacific Northwest, according to the Daily Journal of Commerce Project Center.
1.
Winner (intent to award): Oregon State Bridge Construction of Scio
Amount: $11,973,636
Project: SE Cornelius Pass Road Butternut Creek Bridge (Hillsboro)
Owner: Washington County
Cost estimate: $10,000,000-$15,000,000
Project team: not available
2.
Winner (intent to award): Emery & Sons Construction Group of Salem
Amount: $8,189,456
Project: Aquifer Storage and Recovery (Beaverton)
Owner: city of Beaverton
Cost estimate: not available
Project team: Murray, Smith & Associates
3.
Winner (intent to award): Pacific Tech Construction of Kelso, Washington
Amount: $2,474,000
Project: OSCI Roof Repairs (Salem)
Owner: Oregon Department of Corrections
Cost estimate: not available
Project team: not available
4.
Winner (contract awarded): Keystone Contracting of Ridgefield, Washington
Amount: $2,401,204
Project: Overlook Park Improvements (Ridgefield, Washington)
Owner: city of Ridgefield
Cost estimate: not available
Project team: not available
5.
Winner (intent to award): Pinchiff Mechanical LLC of Tukwila, Washington
Amount: $994,043
Project: Plumbing-Mechanical Services Work Order Contract (King County, Washington)
Owner: King County Procurement/Contract Services
Cost estimate: $1,000,000
Project team: not available