By: 91ÊÓÆµ Staff//February 6, 2026//
91ÊÓÆµ Staff//February 6, 2026//
A weekly compilation of the largest winning bids in the Pacific Northwest, according to the Daily Journal of Commerce Project Center.
1.
Winner (contract awarded): Tapani Inc. of Battle Ground, Washington
Amount: $12,700,000
Project: Tillamook Transmission Line Replacement Phase 1 (Tillamook)
Owner: city of Tillamook
Cost estimate: $13,000,000 to $15,000,000
Project team: Consor
2.
Winner (contract awarded): C.A. Carey Corp. of Issaquah, Washington
Amount: $4,172,118
Project: PS 56 Abandonment and Trenchless Sewer Installation 2025 (Seattle)
Owner: city of Seattle
Cost estimate: $5,638,000
Project team: not available
3.
Winner (contract awarded): Westwater Construction Co. of Renton, Washington
Amount: $2,500,850
Project: Pedestrian Scale Lighting (Seattle)
Owner: city of Seattle
Cost estimate: $2,300,000 to $2,500,000
Project team: not available
4.
Winner (intent to award): Active Construction Inc. of Tacoma, Washington
Amount: $1,738,738
Project: Stossel Right Bank Revetment Re-Bid (Carnation, Washington)
Owner: King County
Cost estimate: $1,695,217
Project team: not available
5.
Winner (contract awarded): Desert View Construction of Caldwell, Idaho
Amount: $1,203,959
Project: Nyssa Water System Improvements – New Well – Idaho Side (Parma, Idaho)
Owner: city of Nyssa
Cost estimate: not available
Project team: HECO Engineers