Top Projects 2023 – Daily Journal of Commerce /news/category/topprojects-2023/ Building and Construction News in Portland, Oregon and the Pacific Northwest Tue, 06 Jun 2023 20:26:04 +0000 en-US hourly 1 https://wordpress.org/?v=6.6.6 /files/2023/08/favicon.webp Top Projects 2023 – Daily Journal of Commerce /news/category/topprojects-2023/ 32 32 Project of the Year /news/2023/06/01/project-of-the-year/ Fri, 02 Jun 2023 04:25:42 +0000 /?p=277277 TriMet Bus Maintenance Facility Built as a temporary facility more than 45 years ago, the TriMet Powell Garage was in need of modernization to improve safety, increase capacity and improve […]

The post Project of the Year appeared first on Daily Journal of Commerce.

]]>

TriMet Bus Maintenance Facility

Built as a temporary facility more than 45 years ago, the TriMet Powell Garage was in need of modernization to improve safety, increase capacity and improve employee well-being. Construction of the new bus maintenance facility included a phased rebuild of the entire 17-acre site, all while keeping it active and operational.The first phase involved building a new 24,000-square-foot, three-bay fuel and wash building, which houses a bus wash system that reclaims and treats water, allowing TriMet to recycle 300 gallons of water per minute.

The second phase more than doubled the original bus maintenance area. The facility has 22 bus maintenance bays and a new 400,000-square-foot, concrete-paved bus yard that can accommodate more than 300 buses. A second story was constructed to create more office space and staff amenities, including a new fitness center, training rooms and spacious break area. The project also added 215 surface parking spaces for employees.

It was essential to maintain uninterrupted operation of the facility amid the demolition and replacement of nearly all existing structures. JE Dunn implemented a timely and consistent communication strategy to ensure all team members understood the plan before work began.

Great care had to be taken to avoid disturbing the main fiberoptic utility feeding Portland’s 911 Call Center, which ran directly through TriMet’s site. The project team successfully relocated the fiber into an underground vault system, and then continued to work around the fiber during mass excavation, foundations and underground utilities without interrupting 911 service at any point during the four-year project.

The facility’s electrification supports TriMet’s commitment to having a 100 percent zero-emission fleet by 2040 and the upgrade allows the facility to power electric buses. New articulated buses, which can hold 60 percent more riders than the 40-foot buses, also will operate out of the site.

HIGHLIGHTS:

  • Powell Bus Maintenance Facility maintains, services and operates more than 50 percent more buses.
  • 130,000-square-foot facility doubles the capacity of the original and houses 22 bus maintenance bays and more than 300 buses in the yard.
  • Bus wash system reclaims and treats water, allowing TriMet to recycling 300 gallons of water per minute during operation.
  • Electrification of the facility supports TriMet’s commitment to having a 100 percent zero-emission fleet by 2040.
  • Insulated concrete tile panels were used for ease and efficiency of construction, as well as for extended lifecycle of the thermal properties of the exterior walls, providing long-term value.
  • 10,000-square-foot vehicle repair basement allows workers to access and maintain the underside of buses from lifts.
  • Articulated buses – which hold 60 percent more riders than 40-foot buses – will operate out of the site.
  • Project achieved 26 percent COBID firm participation.

In addition to sustainability, employee health and well-being was a focus for TriMet. The new structure provides more opportunities to get active and encourages walking by providing catwalks and pathways around the exterior edges to the building, as well as a new exercise facility. The building also includes a covered rooftop patio and a sculpture garden to comfortably enjoy the outdoors, fresh air and relax.

Aggressive and creative efforts made by JE Dunn during the bidding process and preconstruction led to successful COBID participation on the project. During the bid packaging process prior to bid, a major focus was on how to create bid packages that were well-suited to minority and disadvantaged business enterprises in the community. This included creating smaller bid packages, as well as dividing some packages that would typically be combined, to allow for more specialized small businesses to be competitive.

It also included sit-down meetings with larger and GMP trade partners to ensure they understood participation requirements, some of whom were somewhat inexperienced with such requirements. JE Dunn introduced them to COBID firms in the community, creating relationships and turning those relationships into project partnerships.

In the end, the project achieved more than 26 percent participation by COBID firms.

The post Project of the Year appeared first on Daily Journal of Commerce.

]]>
Affordable Housing – 1st place /news/2023/06/01/affordable-housing-1st-place/ Fri, 02 Jun 2023 04:23:39 +0000 /?p=277267 Rockwood Village Location: Gresham Size: 269,945 square feet Cost: $68,116,895 Start: February 2020 Completion: August 2022 Owner/Developer: Community Development Partners (with Hacienda CDC) Architect: Waechter Architecture Engineer: DCI Engineers, Jet […]

The post Affordable Housing – 1st place appeared first on Daily Journal of Commerce.

]]>

Rockwood Village

Photo credits: Jeremy Bittermann/JBSA Images; TRW Images/Twin Moons Staging (family room)

Location: Gresham
Size: 269,945 square feet
Cost: $68,116,895
Start: February 2020
Completion: August 2022
Owner/Developer: Community Development Partners (with Hacienda CDC)
Architect: Waechter Architecture
Engineer: DCI Engineers, Jet Industries, KPFF
General Contractor: LMC Construction
Submitting Company: Waechter Architecture
Other Associates/Consultants: Atlas Plumbing, Daniel Burton, GEO Consultants Northwest, JLC Architectural Consulting, Kittelson & Associates, Little Fish Lighting, Multnomah Tree Experts, PLACE, QED
Subcontractors: 2C Building Services, Advanced Surface Innovations, American Sani-Can, Ankrom Moisan, Authority Dock & Door, Benelli Construction, BLG, BrandSafway Services, Carlson Testing, Carrillo’s Janitorial Service, Cascade Radon, Cistus Design Nursery, City of Gresham, Comcast Business Services, Comcast Construction, Contract Flooring & Interiors, De-El Enterprises, Eagle Striping Services, East Wind Roofing & Sheet Metal, Eastside Paving, Frontier Metal Fabrications, Frontier Roofing & Construction, Gresham Roofing and Construction, Guardian Management, Haier US Appliance Solutions dba GE Appliances, Huntco Site Furnishings, Interior Technology, Jet Industries, KO Construction, Lanz Cabinet Shop, LaRusso Concrete, Lauzon Contracting, Legend Custom Woodworking, Lewis Audio Video, LJP Construction, Mailbox Connection, Meyer Sign Co. of Oregon, Modular Paving Systems, Point Monitor, Polaris Electric, Polygon US, Procore Technologies, Qualified Enclosure Consultants, RC Building Specialties, Recreation Services, Skyline Sheet Metal, Standard TV & Appliance, Stephen Waldroup Construction, Superior Fence & Construction, TerraCalc Land Surveying, Teufel Nursery, Time Frame, TK Elevator, Topline Counters, Van Lom Structures, VPI Quality Windows, Westside Drywall, W.H. Cress

Rockwood Village addresses the need for affordable housing in the heart of the Rockwood neighborhood in Gresham. The project was designed to embrace and engage Oregon’s youngest, most diverse and fastest-growing district. The median age is 27, and more than 60 languages are spoken.

There are four four-story buildings, one three-story building and a central, freestanding community building that collectively provides 224 apartment homes that range from one- to four-bedroom units. Each unit boasts Energy Star appliances, LED lighting, integrated AC window ports, and low-flow plumbing fixtures. To date, about 53.1 percent of the property’s units have been leased to BIPOC households.

The community building includes a large gathering space with a full kitchen for events and social interaction, along with audio visual equipment that provides community space for seminars or workshops. The outdoor area boasts a spacious children’s play area, various walking paths and picnic areas, as well as community gardens and an urban farm. Rockwood Village also frames and connects the area’s newest public square, called Neighbors’ Park, which encourages residents to get outside and experience the Pacific Northwest’s unmatched beauty.

Other key aspects of Rockwood Village were developed through an approach known as Asset Based Community Development, facilitated by Portland State University’s Center for Public Interest Design. This “ABCD” approach helps identify and understand community and program needs, then focuses on filling in missing components and leveraging community resources.

Rockwood Village was built to accommodate households as their needs change. The combination of a single community building, a housing complex and the proximity to Neighbors’ Park and public transportation demonstrates a commitment to not just creating an affordable living space, but building a supportive and robust community.

The post Affordable Housing – 1st place appeared first on Daily Journal of Commerce.

]]>
Arts, Culture & Entertainment – 1st place /news/2023/06/01/arts-culture-entertainment-1st-place/ Fri, 02 Jun 2023 04:18:46 +0000 /?p=277263 The Farmers Market Pavilion and Plaza Location: Eugene Size: 8,515 square feet Cost: $9 million Start: June 2021 Completion: June 2022 Owner/Developer: city of Eugene Owner’s representative: Shiels Obletz Johnsen […]

The post Arts, Culture & Entertainment – 1st place appeared first on Daily Journal of Commerce.

]]>

The Farmers Market Pavilion and Plaza

Photo credit: Eric Brown

Location: Eugene
Size: 8,515 square feet
Cost: $9 million
Start: June 2021
Completion: June 2022
Owner/Developer: city of Eugene
Owner’s representative: Shiels Obletz Johnsen
Main Tenant: Lane County Farmers Market
Architect: Cameron McCarthy Gilbert, FFA Architecture + Interiors
Engineer: Mazzetti, PAE
General Contractor: Lease Crutcher Lewis
Submitting Company: Lease Crutcher Lewis
Subcontractors: Advance Cabinet Designs, Bell Hardware of Eugene, Colors NW, Delta Construction, DR Johnson Wood Innovations, ES&A Sign & Awning Co., Hermanson Co., Jet Industries, Lacey Glass, McKenzie Glass, Mid-Valley Commercial Construction, Overhead Door Co. of Eugene-Springfield, Primo Construction, Richey Wrecking, Rubenstein’s Contract Carpet, Smith Sheet Metal, Snyder Roofing of Oregon, SteelFab Oregon, Superior Electric & Construction, Third Generation Paint

The Farmers Market Pavilion and Plaza has breathed new life back into the downtown core of Eugene and will help encourage economic growth for the quaint, yet vibrant community for many years to come. The ‘town square’ concept utilizes the downtown park blocks and creates a permanent home for both the Lane County Farmers Market and Eugene Saturday Market. To ensure the project incorporated the community’s vision, there were nearly 10,000 people that provided feedback through surveys, attendance at stakeholder and public events, and via email and social outreach. The goal was to create a pavilion that was inclusive yet unique to Eugene, where people could feel a sense of community and belonging.

Inspired by the simplicity of greenhouses, the design utilizes polycarbonate and glass facades that light up the building at night. There is a large market hall indoors, along with a demonstration kitchen, storage, and all-user restrooms. There are large glass roll-up doors, and the pavilion interior was crafted with a mass timber wood structure composed of cross-laminated timber (CLT) fabricated by local, family-owned business DR Johnson.

Colored concrete, carefully crafted in a mosaic pattern, along with native trees strategically placed throughout, brings an artsy warmth to the space. To ensure ADA accessibility and walkability, the team used a Silva Cell system beneath the trees so the tree roots can expand below grade. In addition, the plaza features a demonstration pollinator garden, lush with native plant species that attract bees.

The site originally held a parking garage demolished before construction could begin. The demolition contractor crushed all concrete from the parking garage and reused it on-site. This amount of concrete provided the base fill for the project site. The team partnered with BRING, one of the nation’s oldest non-profit building recyclers, who took material that couldn’t be reused on-site, such as pavers and cyclone fencing, to resell for builders in need.

The post Arts, Culture & Entertainment – 1st place appeared first on Daily Journal of Commerce.

]]>
Education – 1st place /news/2023/06/01/education-1st-place/ Fri, 02 Jun 2023 04:17:09 +0000 /?p=277260 Lincoln High School Location: Portland Size: 292,000 square feet Cost: $196 million Start: January 2020 Completion: April 2023 Owner/Developer: Portland Public Schools Owner’s representative: Turner & Townsend Heery Architect: Bora […]

The post Education – 1st place appeared first on Daily Journal of Commerce.

]]>

Lincoln High School

Photo credit: Turner & Townsend Heery

Location: Portland
Size: 292,000 square feet
Cost: $196 million
Start: January 2020
Completion: April 2023
Owner/Developer: Portland Public Schools
Owner’s representative: Turner & Townsend Heery
Architect: Bora Architects
Engineers: Interface Engineering, KPFF, and Harper Houf Peterson Righellis
General Contractor: Hoffman-Pacificmark JV
Submitting Company: Hoffman-Pacificmark JV
Other Associates/Consultants: JBK Consulting and Design, Mayer Reed, RWDI, The Greenbusch Group, The Shalleck Collaborative
Subcontractors: ADP Lemco, Axiom Division 7, Brown Contracting, Building Material Specialties, Carr Construction, Cosco Fire Protection, Culver Glass, DeaMor Associates, Elite Storage Products, Floor Solutions, Hoffman Specialty Contracting, Hollywood Lights, Hydro-Temp, Interior Technology, JM Painting, Keller North America, Klinger Masonry, Kone, Laboratory Design & Construction, LMS Earthworks, Mari Designs, Material Flow & Conveyor Systems, McKinstry, Ming Surveyors, Nationwide Lifts Oregon, Nor-Pac Seating, Pacific Foundation, Prairie Electrical, Prestige Tile & Stone, Pure Floors, Quantum Assets & Consulting, Ramsay Sign, Salem Wood Products, Schuff Steel, Seattle Sounds & Vibration, Series Seating, Smith & Greene, Straight Up Carpentry, T&T Contractors, Teufel, Town & Country Fence, Wenger Corp., Westview Productions, Whitaker/Ellis, Zana Construction

Lincoln Cardinal students and faculty flocked to a new “nest” this past fall when their 292,000-square-foot high school opened. The six-story urban “high-rise” building is designed to accommodate a surge in student population in Portland Public Schools.

Hoffman Construction completed the project in a joint venture with COBID-certified Pacificmark Construction. Despite COVID, wildfires and supply chain challenges, Hoffman-Pacificmark delivered the project on budget and on schedule.

The school was built on the athletic fields at one end of the school’s campus to allow students to occupy the old facility during construction. Stringent safety protocols and intensive preconstruction planning protected students on the active campus.

The new building includes specialized classrooms for 2D and 3D fine arts, adjacent flex spaces, STEM labs and a maker space. The building has a variety of sustainability features and innovative wayfinding to help students and staff navigate the “high-rise” wing of the school. New athletic facilities include a 1,700-seat main gym, auxiliary gym, weight room, wrestling/dance room, and a new track and field. Primary features include a new commons and outdoor plaza at the main entrance.

The team worked with Portland’s Regional Arts and Culture Council on a large mural that fronts the building. Also included are a new 500-seat auditorium, black box theatre, dedicated band and choir classrooms, and associated practice rooms, along with a career technical education space.

Providing opportunities for COBID-certified construction firms was a key project goal. Pacificmark, an MBE, managed 22 percent of the overall work. The firm mentors small MBE/SBE firms and played an important role in preconstruction. PPS’s goal for the project was 18 percent COBID firm participation and Hoffman-Pacificmark set a goal of 22 percent, with the added goal of engaging women and people of color in 20 percent of apprenticeships. Ultimately the project provided abundant opportunities for growing capacity and skills for diverse workers and firms, surpassing PPS’s diversity goals and ensuring the school was built by people who represent the community it serves.

The post Education – 1st place appeared first on Daily Journal of Commerce.

]]>
Healthcare & Life Sciences – 1st place /news/2023/06/01/healthcare-life-sciences-1st-place/ Fri, 02 Jun 2023 04:16:09 +0000 /?p=277257 The Vancouver Clinic – Salmon Creek 2 Location: Vancouver, Washington Size: 80,000 square feet Cost: not disclosed Start: February 2021 Completion: September 2022 Owner/Developer: Pacific Medical Buildings Architect: ZGF Architects […]

The post Healthcare & Life Sciences – 1st place appeared first on Daily Journal of Commerce.

]]>

The Vancouver Clinic –
Salmon Creek 2

Photo credits: Lincoln Barbour

Location: Vancouver, Washington
Size: 80,000 square feet
Cost: not disclosed
Start: February 2021
Completion: September 2022
Owner/Developer: Pacific Medical Buildings
Architect: ZGF Architects
Engineer: KPFF, Mackay Sposito, PAE, Stantec
General Contractor: Andersen Construction
Submitting Company: Andersen Construction
Subcontractors: ABC Roofing, AIG, Alliant, Anning-Johnson, Arctic Sheet Metal, ASI, ASSA Abloy, B&B, BMS, Broadfence, Culver Glass, D&H Flagging, Drakes, Elmer’s, Floor Factors, Forms & Surfaces, Gibson Door & Millwork, Hanset, HLK Visions, Huntco, Interior Tech, LaRusso, Maintenance Man, McDonald, McKinstry, Metro Watch, Mill Plain Electric, Minister Glaeser, North Fork, NW Scaffold, Oregon Commercial Painters, Palmer Group, Paulson’s Flooring, Pioneer Waterproofing, Polygon, Straight Up, Streimer, Superior, ThyssenKrupp, Tube Art, Victor Stanley, VPI, Wessco, WPI

Vancouver Clinic, the largest private, multispecialty clinic in Clark County, has an 80-year legacy in southwest Washington. With more than 1,200 employees and 400 providers, the clinic has seen rapid growth, building three new clinics in just five years. To date, the newest three-story, 80,000-square-foot space is the most advanced, built to serve the rapidly growing population. Constructed in just 19.5 months, the first floor features a 13-exam-room urgent care facility, two triage rooms, a CT and X-ray room, and a physical therapy center.

The second floor houses a pain man-agement procedure suite, as well as 39 exam rooms and three X-ray rooms with room for a fourth later. This area will primarily cater to patients needing access to medical care in the areas of orthopedics, physical therapy, podiatry, and sports medicine.

The third floor boasts six operating rooms with 18 pre/post operative rooms for same-day surgeries. In addition, there is an expanded sterile processing department.
The building’s HVAC system features two dedicated and redundant air handlers, and state-of-the-art ceiling operating room systems that include prefabricated supply air diffusers and ultraviolet light sterilization systems.

Additionally, the facility uses surgical robots and visual and graphics for the operating suites. To ensure that the building design was functional and to get boots-on-the-ground feedback, the team conducted mockups, site walks and progress reviews with key staff members.

The project was completed with a team-oriented Progressive Design-Build approach, where the relationship between the design team, TVC and Andersen was crucial to delivering the project within the schedule. The team relied heavily on relationships developed through the previous two successful projects in this series. Despite some weather delays and issues with procuring materials, The Vancouver Clinic –Salmon Creek 2 finished ahead of schedule and under budget.

The post Healthcare & Life Sciences – 1st place appeared first on Daily Journal of Commerce.

]]>
Hospitality & Special Purposes – 1st place /news/2023/06/01/hospitality-special-purposes-1st-place/ Fri, 02 Jun 2023 04:15:34 +0000 /?p=277252 Oregon Humane Society – The New Road Ahead Location: Portland Size: 71,100 square feet Cost: not disclosed Start: January 2018 Completion: October 2022 Owner/Developer: Oregon Humane Society Architect: Scott Edwards […]

The post Hospitality & Special Purposes – 1st place appeared first on Daily Journal of Commerce.

]]>

Oregon Humane Society –
The New Road Ahead

Photo credits: Quanta Collectiv

Location: Portland
Size: 71,100 square feet
Cost: not disclosed
Start: January 2018
Completion: October 2022
Owner/Developer: Oregon Humane Society
Architect: Scott Edwards Architecture
Engineer: Humber Design Group, KPFF, PAE
General Contractor: Lease Crutcher Lewis
Other Associates/Consultants: ABD Engineering and Design, PLACE
Submitting Company: Scott Edwards Architecture
Subcontractors: A2 Fabrication, ABC Roofing, Acousti-Level Floor Systems, All Seal, American Concrete, Anker Constructors, Arctic Sheet Metal, B&B Tile and Masonry, Bargreen Ellingson of Oregon, Capitol Electric, Cascade Acoustics, Cash’s Drapery, Cosco Fire Protection D&H Flagging, Dynamic Expansion, Engineered Products, Floor Solutions, Gibson Door & Millwork, Green Earth Landscaping, Ha’s Painting, Interior Technology, Kodiak Pacific Construction, Lake Oswego Insulation, LDC, LGL Animal Care Products, Mid-Valley Glass & Millwork, Northwest Surveying, P.R. Worth, Piper Mechanical, Salem Wood Products, Schindler Elevator, South Town Glass, Superior Fence & Construction, The Stoner Electric Group, Van Lom Concrete, W.H. Cress, Western Wood Structures, Zavala, Zeeland Janitorial

Founded more than 150 years ago, Oregon Humane Society has established itself as one of the country’s most respected animal welfare organizations. The New Road Ahead project required out-of-the-box thinking and the approach that “no detail was too small to question.” The project goal: to combine a comprehensive veterinary hospital for the community, a highly specialized animal crimes forensics center, an adaptable rescue space, and a spacious location that supports innovative approaches to animal behavior modification. The result is an innovative space that will take the organization through many generations of animal rescue and rehabilitation.

This 71,000-square-foot expansion en-compasses two buildings: one houses the Community Veterinary Hospital and the Animal Crimes Forensics Center, and the other houses the Behavior Modification and Rescue Center. The site is next to OHS’s existing shelter and expands the campus from one building to three.

The Behavior Modification and Rescue Center building (BRC) includes 68 new kennels for animals to rest. The BRC rehabilitation facilities also include four “Real Life Rooms,” which simulate human-occupied spaces with furniture, TVs and a toy bin. Also, a large training room offers a staircase that helps teach dogs how to go up landings and to walk on leashes.

The Animal Crimes Forensics Center is only the second of its kind in the United States, supporting investigations for criminal cases in a science-based facility that may be used in animal abuse cases or trials.

Throughout each phase of the process, the team viewed things through the lens of the animals. For example, polished concrete mockups were compared to determine which one was the most subtle, as to calm the most skittish animals. Fiberglass doors and wall paneling were used throughout because it can withstand animal wear and tear. Acoustic panels were installed to dampen noise, and inverted truss design allowed for high-clerestory windows that funneled natural light into rescue pods while dispersing sound.

The post Hospitality & Special Purposes – 1st place appeared first on Daily Journal of Commerce.

]]>
Industrial, Manufacturing, Logistics – 1st place /news/2023/06/01/industrial-manufacturing-logistics-1st-place/ Fri, 02 Jun 2023 04:09:38 +0000 /?p=277243 NE 10th Avenue: NE 149th Street to NE 154th Street Location: Vancouver, Washington Size: Quarter mile Cost: $8,359,825 Start: May 2021 Completion: September 2022 Owner/Developer: Clark County Architect: Clark County […]

The post Industrial, Manufacturing, Logistics – 1st place appeared first on Daily Journal of Commerce.

]]>

NE 10th Avenue:
NE 149th Street to NE 154th Street

Photo credit: Tapani Inc.

Location: Vancouver, Washington
Size: Quarter mile
Cost: $8,359,825
Start: May 2021
Completion: September 2022
Owner/Developer: Clark County
Architect: Clark County Public Works
Engineer: Clark County Public Works
General Contractor: Tapani Inc.
Submitting Company: Tapani Inc.
Subcontractors: 3 Kings Environmental, Aquatic Contracting, Brad’s Septic Service, Brothers Concrete Cutting, City Electric, Dietrich Trucking, Em3, Glacier Drilling, Green Sweep, Jeffries Construction, Keller North America, Lakeside Industries, McDonald Excavating, Molecular, North 40 Fence, Northwest LNG GEOTXTL PRD, Pacific Rim, Ralph’s Concrete Pumping, Site One, Specialized Pavement Marketings, Superior Gunite, Tapani Trucking, Taylor Transport, West Coast Sand and Gravel, West Coast Soil Solutions

With significant growth happening in Clark County – especially in the greater Ridgefield area – roads are seeing higher volumes of traffic and activity. Such is the case for the NE 10th Avenue Project, which aimed to improve access from Salmon Creek to the popular Clark County Fairgrounds.

Before construction began on 10th Avenue, there were only two lanes with no shoulder, limited visibility of oncoming traffic, and the road was unable to keep traffic moving during peak flow times. The project aimed to widen the street to two travel lanes with a center left turn lane, as well as add bicycle lanes and sidewalks. It also included the addition of a traffic signal to improve traffic flow. The project required a complete reconstruction of 10th Avenue from 149th Street to 154th Street.

This stretch of road is strategically located near a creek bed, where high water conditions and other environmental issues needed to be considered. The most critical part of the project was elevating the road 20 feet over an unnamed Whipple Creek outlet. This required detailed planning on how to best preserve and work within the wetland area, while ensuring erosion control methods were followed. To develop the nearby embankment, the teams placed 32,350 cubic yards of gravel borrow, which secured the foundation of the new roadway. Construction teams also used 13,600 cubic yards of deep soil mixing, which helped increase the stability of the area. More than 4,055 tons of asphalt pavement was placed during final paving which finished the roadway over the creek.

With new retaining walls, a culvert that draws attention to the creek and wetland, and a wider, more stable road that welcomes pedestrians, vehicles, and bikes, the area now provides improved access to the area without the need to travel on Interstate 5.

The post Industrial, Manufacturing, Logistics – 1st place appeared first on Daily Journal of Commerce.

]]>
Infrastructure & Telecom – 1st place /news/2023/06/01/infrastructure-telecom-1st-place/ Fri, 02 Jun 2023 04:07:58 +0000 /?p=277238 TriMet Bus Maintenance Facility Location: Portland Size: 130,000 square feet main facility, 24,000 square feet fuel/wash building Cost: not disclosed Start: August 2018 Completion: November 2022 Owner/Developer: TriMet Architect: Stantec […]

The post Infrastructure & Telecom – 1st place appeared first on Daily Journal of Commerce.

]]>

TriMet Bus Maintenance Facility

Photo credits: Amy Winterowd (building exterior), Josh Partee (interiors), Katie Scott (two JE Dunn team members)

Location: Portland
Size: 130,000 square feet main facility, 24,000 square feet fuel/wash building
Cost: not disclosed
Start: August 2018
Completion: November 2022
Owner/Developer: TriMet
Architect: Stantec
Engineers: David Evans and Associates, Glumac
General Contractor: JE Dunn Construction Co.
Submitting Company: JE Dunn Construction Co.
Subcontractors: 2C Building Services, Advanced Security, Affordable Electric, American Medical Response Northwest, API Group Life Safety USA, Authority Dock and Door, Benson Industries, Brix Paving Northwest, Charter Mechanical Contractors, Chick of All Trades dba COAT Flagging, Damac & Associates Clean, Diverse Works, Drakes Striping & Painting, Egami Construction, Floor Factors, General Sheet Metal Works, GeoDesign, J&S Masonry, JIC Construction dba Sterling-Pacific, K&D Services of Oregon, KPFF, Lacey Glass, Lovett, Market Contractors, MHW Savage Enterprises dba Green Man Construction, Moore Excavation, Northwest Enforcement, Northwest Infrastructure, OEG, Oldcastle Infrastructure, Pacific Foundation, Penhall Co., Performance Contracting, Polygon US, Prestige Tile and Stone, Professional Roof Consultants, QED Lab, Raimore Construction, RWDI USA, Sawtooth Caulking, Schindler Elevator, Snyder Roofing of Oregon, Specialized Pavement Marking, Superior Interiors, SXD USA, TerraCalc Land Surveying, Town & Country Fence Co. of Oregon, Treewise, Tube Art Displays dba Tube Art Group, Valley Growers Nursery & Landscaping

Founded five decades ago, TriMet has played a key role in the growth of Portland and its surrounding area. To meet the growing transportation needs of Oregonians, TriMet has expanded its vital services significantly over the years, yet the TriMet Powell Garage – built 45 years ago as a temporary facility – remained mostly unchanged. Constructing a new bus maintenance facility was needed to improve safety and increase capacity.

This four-year project included a phased rebuild of the entire 17-acre site, while maintaining uninterrupted public transit service. The first phase included building a 24,000-square-foot, three-bay fuel and wash building that featured a bus wash system that recycles up to 300 gallons of water a minute.

The second phase involved expanding the original bus maintenance area to include 22 maintenance bays and a 400,000-square-foot concrete bus yard that can accommodate more than 300 buses. To support the increase of new electric-powered buses and to provide charging stations for them, electrical service enhancements and structural upgrades were required in the bus storage and maintenance area. The second story of this building augmented office space and added more amenities, including a training room, roof-top patio, bigger employee break room, a new fitness center, and the addition of more than 200 parking spaces.

The larger space – along with its focus on sustainability and efficiency – will serve the community for decades to come. In total, the project will accommodate 50 percent more buses, including larger buses that align with TriMet’s initiative of having a 100 percent zero-emission fleet of electric buses by 2040.

The post Infrastructure & Telecom – 1st place appeared first on Daily Journal of Commerce.

]]>
Multi-Family & Mixed Use – 1st place /news/2023/06/01/multi-family-mixed-use-1st-place/ Fri, 02 Jun 2023 04:06:54 +0000 /?p=277235 Rose Villa Senior Living Phase 3 Location: Portland Size: 136,100 square feet Cost: not disclosed Start: November 2018 Completion: December 2022 Owner/Developer: Rose Villa Senior Living Architect: Scott Edwards Architecture […]

The post Multi-Family & Mixed Use – 1st place appeared first on Daily Journal of Commerce.

]]>

Rose Villa Senior Living Phase 3

Photo credits: David Papazian

Location: Portland
Size: 136,100 square feet
Cost: not disclosed
Start: November 2018
Completion: December 2022
Owner/Developer: Rose Villa Senior Living
Architect: Scott Edwards Architecture
Engineer: Humber Design Group, Interface Engineering, WDY
General Contractor: Bremik Construction
Submitting Company: Scott Edwards Architecture
Other Associates/Consultants: Biohabitats, Gawron Turgeon Architects, JBK Consulting and Design, Shapiro Didway
Subcontractors: ABC Co., AA Asphalting, Acadamy Specialties, Acousti-Level Floor System, Advance Fire Proofing & Insulation, American Direct, American Heating, Apex Coating Services, BASCO, Building Material Specialties, Build Pro, Cali Bambo, Compaction & Recycling Equipment, Chase Jones & Associates, Colors NW, Columbia Cascade, Commercial Cabinets Works, Cosco Fire Protection, D&R Masonry Restoration, Dallas Glass & Window, DE-EL Enterprises, Duke Construction & Excavation, Eagle Striping Services, Elmer Flags & Banner, FE Bennet, Fireside Home Solutions, Funax Services, GBS NW, Gelco Construction, Hard-core Contractors, Hunt Painting, Huntco Supply, Interior Exterior Specialist, InPro, Intiron/Microfridge, IRS Environmental, JB Insulation, Kraft Masonrhy, Lisac’s Fireplaces & Stoves, LOI Environmental & Demolition Services, LoveTEAK, McDonald & Wetle, Merit Electric of Spokane, Metro Protection Services, Mt. Hood Window Coverings, Natural Stone Design, Northwest Masonry Restoration, Northwest Playground Equipment, Northwest Industrial Services, Overhead Door Co. of Portland, Paragon Tile and Stone, Paulson’s Floor Covering, Pioneer Sheet Metal, Piper Mechanical, Quality Door Service, Scaffold Erectors, Skyles Drilling, Smith & Greene, Standard TV & Appliances, T.A Onchi, ThyssenKrupp Elevator, Timberland, TRV Surveying, Twinco Cutting & Coring, UnderCover Systems, Waypoint Sign, Waste Equipment Sales & Services (Wessco), Won-Door

Rose Villa Senior Living completed a functional expansion on the urban core of its 22-acre garden campus. The four-year project incorporated sustainable features, uniquely prioritized environmental stewardship, and focused on creating a place that is healthy for staff, residents and nature.

The project added two new buildings at its south end – Schroeder Lofts and Madrona Grove. At first glance, Madrona Grove, a four-story, steel-framed building with a two-story licensed residential long-term care facility, and Schroeder Lofts, a five-story, wood-framed, multi-use building, may seem like separate projects. However, they are connected below grade and were designed, permitted and constructed together as one. The buildings surround a shared landscaped courtyard that serves as an outdoor room, which encourages social interaction and outdoor living, and creates further dialogue between buildings.

This project prioritized the quality of life for people that live, work and visit here. One way that the team did this was by incorporating as much natural daylight as possible into the design. Hence, there are south-facing sunrooms on each floor of the Madrona Grove building and the Schroeder Lofts have decks or patios for outdoor living, floor-to-ceiling window walls in the living spaces, and shared outdoor amenity spaces.

Sustainability also was key, demonstrated with use of low-flow fixtures, LED lighting, R-values in walls and roofs that are above code requirements, and tinting of the windows to enhance efficiency for the mechanical heating and cooling systems. The landscaping focuses on native plant integration and aims to meet Backyard Habitat Certification Gold requirements.

The use of ROSIE (Recycled Organic “Stuff” is Everywhere), a system that recycles greywater in Schroeder Lofts, is one of the most notable sustainable features, the first-of-its-kind in the Portland senior living marketplace. The system is a water conservation approach that is designed to reduce the use of potable water for things like toilet flushing and irrigation and will save approximately 303,214 gallons of potable water per year.

The post Multi-Family & Mixed Use – 1st place appeared first on Daily Journal of Commerce.

]]>
Office – New Construction – 1st place /news/2023/06/01/office-new-construction-1st-place/ Fri, 02 Jun 2023 04:05:33 +0000 /?p=277230 Serena Williams Building at Nike World Headquarters Location: Beaverton Size: 1,023,000 square feet Cost: not disclosed Start: October 2016 Completion: October 2021 Owner/Developer: Nike Inc. Architect: Skylab Architecture Engineer: NV5, […]

The post Office – New Construction – 1st place appeared first on Daily Journal of Commerce.

]]>

Serena Williams Building
at Nike World Headquarters

Photo credits: Jeremy Bittermann

Location: Beaverton
Size: 1,023,000 square feet
Cost: not disclosed
Start: October 2016
Completion: October 2021
Owner/Developer: Nike Inc.
Architect: Skylab Architecture
Engineer: NV5, PAE/Luma, Thornton Tomasetti
General Contractor: Hoffman Construction Co. of Oregon
Submitting Company: Skylab Architecture
Other Associates/Consultants: Ambrosini Design, Brightworks, Code Unlimited, HAD Pacific (Hammer Design Associates), KPFF, Listen Acoustics, M. Thrailkill, PLACE, RWDI (formerly Façade Group), SRG Partnership
Subcontractors: Ace Private Security, Acme Construction Supply, Acme Scenic & Display, Alex Consulting Construction Services, Alliance Industrial Group, Amodeo Structural Engineering, Arbon Equipment, Axiom Custom Products, Bassett Construction, Beynon Sports Surfaces, Big Trees Today of Oregon, BrandSafway Services, Building Material Specialties, CalPortland, Carpentry Plus, Carr Construction, Classic Woodworking, Coffman Excavation, Corradini, Cotterman Co., Culver Glass, Custom Designed Skylights, Dennis’ Seven Dees Landscaping, Digital Works Productions, DLM Inc. Architextures Division, Domus Design Center, DroneBase, Dynalectric, ERF, F.D. Thomas, Fetzers, Floor Solutions, Flynn BEC, Hillsboro Aviation, Hoffman Structures, Infinity Images, Interior Exterior Specialists, IQ Traffic Services, Iris Window Coverings NW, ISEC, J&S Masonry, Johnson-Lancaster & Associates, JS Perrott & Co., Kelly’s Home Center, Kent Crane Inspection Services, Knaphus Exterior Panel, Kone, Lafarge North America, LandCare USA, Landscape Forms, LaRusso Concrete, Masons Supply, McKinstry, Ming Surveyors, Modern Building Systems, Morrow Equipment, Moss Holding, Ness & Campbell Crane – Portland, Nor-Pac Seating, Northwest Handling Systems, Northwest Tower Crane Services, OEG, Pacific Foundation, Pacific Mobile Structures, Pacific Window Tinting, Pavement Maintenance, Penington Painting, Performance Contracting – PDX, Pioneer Waterproofing, Poltrona Frau Group North America, Preston Rentals, Pure Floors, R2M2 Rebar & Stressing, Resource Maintenance & Flooring, Servicemaster Building Services, Servpro of Tigard/Tualatin, Spacesaver Specialists, Stoncor Group, Temp Control Mechanical, The Smith Overhead Door Co., Town & Country Fence – Oregon, Trimble, Tube Art Displays, UFP Woodburn, United Site Services of Nevada, VAK Construction Engineering, Waste Management of Oregon – Precision, Waypoint Sign, Wessco, West Meyer Fence, Western Partitions, Western States Fire Protection Lake Oswego, Western Tile & Marble Contractors, Won-Door

The Nike name is synonymous with innovation and one of its newest struc-tures – the Serena Williams Building – demonstrates the company’s commitment to community, sustainability and one-of-a-kind designs. The 1,000,000-square-foot project – which took a total of five years from beginning to end – is a workplace for 2,500 occupants. It is the largest building at Nike World Headquarters in Beaverton. The building houses Nike’s Consumer Creation team: design teams, consumer insight teams, women’s, men’s and children’s teams, and apparel and footwear product merchandising teams.

The LEED-platinum certified structure has four key components: an underground parking garage and loading dock; integrated design studios; a 12-story tower with shared campus amenities; and a merchandising center for prototyping retail spaces. The Serena Williams building is the first of its kind for Nike, allowing products to move through all stages of the lifecycle in one building – sketch, prototype, final design, to retail fixture.

Informal outdoor spaces are scattered throughout the area to foster community building amongst occupants and to promote unity with nature, including courtyard gardens, plazas and a sunken tennis court. Inside, people can enjoy the aesthetics of exposed concrete, skylights, views of the wetland from workspaces, and five food and beverage venues.

Designers for each Nike brand are on a single level, while services stack vertically between levels. To further conserve Earth’s resources, the building design incorporates several environmentally friendly features. Stormwater is collected and re-distributed to the area’s surrounding wetland, 260 kw photovoltaic panels are found along the building’s roofs, and rainwater is reused for toilet flushing.

And, as the building name suggests, the life story and career accomplishments of Serena Williams are displayed throughout the various studios.

 

The post Office – New Construction – 1st place appeared first on Daily Journal of Commerce.

]]>