Aug 2, 2010

Facebook doubling size of Prineville data center

Facebook announced late last week that it will double the size of its data center currently under construction in Prineville. The expansion will add 160,000 square feet to the shell of the building, which was originally set to be 147,000 square feet.

Jul 2, 2010

PSU steam and water loop project

More than 900 feet of tunnels were built for piping needed to expand and connect the Portland State University's heating and cooling systems into centralized plants and to add emergency power backups.

Jan 11, 2010

PSU loop

Construction on the Portland State University campus will make heating and cooling there more efficient. The project, now in its second phase, connects heating and cooling systems to centralized plants and adds a power backup system.