91ÊÓÆµ

Wind energy developers face federal hurdles

By: Nathalie Weinstein//April 27, 2010//

Wind energy developers face federal hurdles

Nathalie Weinstein//April 27, 2010//

Listen to this article
Wind developers are concerned that the Federal Aviation Administration's issuance of a notice of potential hazard for Caithness Energy's Shepherd's Flat wind project in Eastern Oregon  could me hold ups for other wind projects in the area.   Photo courtesy of Iberdrola Renewables

Construction of new wind farms in Oregon usually begins in springtime, when developers hope for dry weather. But this spring, developers are concerned about more than just rain.

The Federal Aviation Administration last month sent a notice of presumed hazard for Caithness Energy‘s wind farm in Arlington, saying one of the project’s 303 turbines could interfere with transmissions from a Department of Defense-owned radar station in nearby Fossil.

Now, a study to determine whether the turbine could interfere with signals from the radar station will hold up the Eastern Oregon project well into summer. And wind developers, like Chris Taylor of Element Power, worry that their own projects may be delayed in the future.

“The troubling thing is this project was developed properly and responsibly,” Taylor said. “We need a system (with the FAA) that allows you to tell early on where the problem areas are. The fact that they came at the 11th hour is what is really problematic.”

Laura Brown, spokeswoman for the FAA, said Caithness Energy filed a notice with the FAA in September 2009, but a notice of presumed hazard wasn’t issued by the FAA until March 1, a few weeks before project construction was scheduled to begin.

Caithness had already poured concrete for Shepherd’s Flat and purchased all of the turbines it needed from General Electric, according to John Audley, executive director of the Renewable Northwest Project, a nonprofit that performs advocacy work for Oregon’s clean energy industry. Now those turbines are waiting at a terminal in the Port of Tacoma.

“Investors are in a catch-22 here,” Audley said. “The window for construction is very narrow. You have to start building now to be done by October, when the rain starts, and then be sufficiently completed by the end of the year to qualify for federal tax incentives.”

One of the difficulties in planning a wind farm project, Taylor said, is that developers will go through dozens of potential turbine layouts between concept and completion to ensure that the turbines are generating the most energy possible.

But Taylor said the FAA doesn’t have the resources to review multiple designs. Instead, it asks developers to submit an initial layout and use that to determine whether the project presents a hazard. Later, a wind developer has to resubmit the project for final approval if any changes have been made. As a result, it could be rejected.

“The concerns stem from the fact that this project sought and was given approval by FAA and they went back for final approval with minimal changes, the opinion changed,” Audley said. “That’s hard on a business making investments and financing decisions.”

vbcvbc
(Photo courtesy of Iberdrola Renewables)

“The irony is, you could stick with the unoptimized layout that has been approved by FAA and build a less efficient wind farm,” Taylor said. “We need a system that allows you to tell early on where the problem areas are. Something like, anything under 450 feet tall is OK. That’s the clarity we need.”

The increase in wind projects seeking the OK from the FAA has challenged the federal agency. Brown said that in 2004 her office saw 4,000 applications for wind turbines each year. Today, it sees 30,000 per year.

“We have been telling the wind turbine industry for a number of years that we need eight to 12 months to do these reviews,” Brown said. “We recognize that the developers want to proceed quickly. But since we have to review every single turbine, on a project that involves hundreds of turbines, that’s a bigger task.”

Brown also noted that the FAA cannot stop construction of a wind project, even if it determines a potential hazard; state and local authorities have the final say.

Iberdrola Renewables previously received a determination of no hazard for its 200-megawatt Leaning Juniper II wind farm in Arlington, and ground is slated to be broken next month. The firm recently had to resubmit a notice to the FAA because the location of some of the project’s turbines has moved, said Jan Johnson, spokeswoman for Iberdrola. Johnson said she doesn’t believe the FAA will take any issue with the new proposal.

“I think it would be unusual for the FAA to change (its) mind so quickly,” Johnson said. “We received determinations of no hazards on three wind farms in that area in 2008 and 2009. We did make some minor modifications based on state and local siting rules, and to optimize the layout to generate the most electricity possible.”

If Iberdrola were to receive a notice of potential hazard on Leaning Juniper II, or two other wind farms the firm has planned in the vicinity, it would hold off on the projects, Johnson said. Iberdrola is looking to build a 50-megawatt project and a 150-megawatt project near Bickleton, Wash.

“These three wind farms represent a $1 billion investment in Oregon and Washington,” Johnson said. “We estimate it will bring 600 construction jobs and millions (of dollars) in tax payments and landowner payments, all going to Oregon and Washington governments and residents.”

The Shepherd’s Flat project is being studied by radar experts at the Massachusetts Institute of Technology to see if turbines can reflect radar and create blind spots where airplanes can’t be seen by radar screens. Brown said her office is still reviewing information and hasn’t made a determination yet.

The outcome of the radar study could affect future wind projects near Fossil, but Audley hopes that the visibility of Shepherd’s Flat will lead to a more permanent fix for the issues surrounding FAA oversight of wind projects. He also doesn’t believe projects that have already received approval should have to suffer.

“Let the projects in the pipeline get built,” Audley said. “The larger question is how we improve this process so (the FAA) engages in advance so businesspeople can make good decisions. That’s a longer-term issue that will require legislative activity or federal policy rethinking that is a bit above my pay grade.”



News

See All News

Commentary

See All Commentary

COMMUNITY CALENDAR