Betty Oden//May 10, 2011//
Bid Date/Time: May 24, 2 p.m.
This project consists of Conger Street (Job 4679) and Wilson Street (Job 4680) pavement preservation for the city of Eugene as part of its pavement preservation program and pavement bond measure.
Work includes work-zone traffic control, erosion control, temporary striping, adjustment of manholes, cold plane pavement removal; asphalt concrete pavement repairs; pavement legends; thermoplastic and other work.
Work may not start until July 11, and all work is to be completed within 25 workdays, but not later than Sept. 1 – whichever occurs first.
and gain access to complete bid information, including specs and plans, for this project and others!