SECOND PLACE PUBLIC WORKS/INFRASTRUCTURE/TRANSPORTATION $1M - $5M
By: Lindsey O'Brien//May 26, 2011//
SECOND PLACE PUBLIC WORKS/INFRASTRUCTURE/TRANSPORTATION $1M - $5M
Lindsey O'Brien//May 26, 2011//
When a record amount of rain in December 2007 took out the Chandler Road Bridge, residents in several towns along State Route 6 found themselves without a way to cross the Chehalis River.
Location: Lewis County, Washington
Cost: $2.83 million
Start Date: May 2008 (design)/May 2010 (construction)
Completion Date: December 2010
Owner/Developer: Lewis County Public Works
Landscape Architect: Harper Houf Peterson Righellis
Engineer: GeoDesign Inc., Harper Houf Peterson Righellis, Otak
General Contractor: Quigg Bros. Inc.
Other Associates: Northwest Hydraulic Consultants Inc.
With Harper Houf Peterson Righellis Inc. providing overall project management, civil engineering, natural resource design and landscape architecture, the project team constructed a new bridge structure that was raised by more than 12 feet in order to provide clearance for future flood events.
Chris Robertson, project-managing engineer for HHPR, said raising the bridge was 鈥渁 technical feat,鈥 especially because the work was so close to the highway and the team was under tight time constraints.
The new bridge uses post-tensioned, spliced, precast girders at 240 feet, which has set a new span record for this type of structure in the western U.S.
鈥淲e knew that as soon as the bridge was built, it would be a massive lift in the lives of all the people in the area,鈥 Robertson said.