The Central Kitsap School District is accepting bids for kitchen freezer improvements at Central Kitsap Junior High School and a food service/warehouse facility.
The project consists of the demolition of an existing reach-in cooler and walk-in freezer at Central Kitsap Junior High School and the installation of new freezers at the school and a food service/warehouse facility. Work includes installation of a forklift maneuverable freezer, associated work, and mechanical and electrical connections. In addition, the project calls for minor interior repairs and installation of a chain-link fence at the school.
Site access will be granted by the school district on July 7 to begin mobilization and construction activities. Final completion for work at the school is scheduled for Sept. 9 and final completion for work at the food service/warehouse facility is scheduled for Oct. 12.