91视频 Staff//January 13, 2022//

PROJECT: Patricia Reser Center for the Arts
LOCATION: Beaverton
SIZE:听43,000 square feet
COST:听$55 million
START DATE: late 2019
ANTICIPATED END DATE: February 2022 (opening March 8)
OWNER: city of Beaverton
OWNER’S REPRESENTATIVE: Gerding Edlen
ARCHITECT: Opsis Architecture
ENGINEERS: KPFF Consulting Engineers (structural), Otak (civil), PAE (mechanical and plumbing), Reyes Engineering (electrical, tele/data low voltage)
CONSTRUCTION MANAGER/GENERAL CONTRACTOR:听Skanska USA Building
OTHER CONSULTANTS/PARTICIPANTS: Anderson Krygier (environmental graphic design), Angelo Planning Group (land use), DCW Cost Management (estimating), JLC Consulting (specifications), Morrison Hershfield (envelope), Pacific Habitat Services (environmental consultant), PLACE (landscape architecture), Stantec (acoustics), The Shalleck Collaborative (theater planning and audio/visual)
SIGNIFICANCE OF PROJECT: Located near The Round between Southwest Cedar Hills Boulevard and Southwest Hall Boulevard, the Reser Center features a 550-seat theater; an art gallery; rehearsal, workshop and meeting space; a lobby; an outdoor plaza and an adjacent parking structure. The site is near a light rail station, City Hall, Beaverton Creek, shops, restaurants and lodging. This is the first facility of its kind to be built from the ground up in the Portland area in more than three decades.
Opsis Architecture sought to blend urban and natural settings in the design. The plan included not only the main structure, but parking, a pedestrian-friendly promenade with a street festival ambience, and public art. Inspired by the metaphor of a beaver dam, wood panels and long, thin wood slats or 鈥渟ticks鈥 and incision points are integrated to enable light to pour into the atrium, while blending with state-of-the-art acoustic and theatrical systems in the Mainstage Theater. With blue seats, the theater is evocative of a body of water adjacent to a creek housing a beaver dam. The facility includes 21,000 square feet of Douglas fir. The second floor has space for a variety of educational workshops, classes, rehearsals, meetings and events. The performing and presentation spaces are designed to maximize the connection between artists and audiences.
The concept of creating a center for the arts in Beaverton started in the late 1990s. Later, a study led by Opsis and Theater Consulting Group, in conjunction with University of Oregon students, showed what a world-class arts center could look like. In July 2018, the Beaverton Arts Foundation announced a pledge of $13 million from Pat Reser to launch the project. In three years, more than 950 donors 鈥 individuals, families, foundations and businesses 鈥 provided more than $12 million to exceed the initial goal by $1 million. Gifts ranged from $2 to $1.5 million. Also, the Beaverton City Council approved a hotel lodging tax to help pay for construction and provide ongoing financial support of operations.
鈥淏uilding Blocks鈥 spotlights noteworthy projects either under construction or approaching the start of construction. To submit a project for consideration, please visit: djcoregon.com/building-blocks.





